3006 N ACRESITE ST 90039
Certificate Information: 3006 N ACRESITE ST 90039
- Application / Permit
- 20016-20000-10354
- Plan Check / Job No.
- B20VN06027
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 21'x23' DETACHED GARAGE TO NEW ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) AND (d).
- Permit Issued
- Issued on 8/12/2021
- Issuing Office
- Current Status
- CofO Issued on 5/13/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/28/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/4/2020 | LUIS RINCON |
| Corrections Issued | 5/6/2020 | LUIS RINCON |
| Applicant returned to address corrections | 6/8/2020 | LUIS RINCON |
| Applicant returned to address corrections | 8/21/2020 | ROSENDO MEDINA |
| Applicant returned to address corrections | 12/2/2020 | ROSENDO MEDINA |
| Applicant returned to address corrections | 1/13/2021 | LUIS RINCON |
| Applicant returned to address corrections | 3/23/2021 | LUIS RINCON |
| Plan Check Approved | 6/15/2021 | LUIS RINCON |
| Building Plans Picked Up | 6/25/2021 | APPLICANT |
| Issued | 8/12/2021 | APPLICANT |
| CofO in Progress | 5/9/2023 | SCOTT FINNILA |
| Permit Finaled | 5/13/2023 | DEROLD HAUFF |
| CofO Issued | 5/13/2023 | DEROLD HAUFF |
| Permit Finaled | 5/13/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Miscellaneous | Cleared | 6/30/2020 | CELINA MORENO |
| Sewer availability | Cleared | 6/30/2020 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 7/1/2020 | CELINA MORENO |
| Address approval | Cleared | 2/26/2021 | CELINA MORENO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Schwartzberg,, Leo Joshua; Lic. No.: C51851 | 7547 SEDGEWICK CT WEST HILLS, CA 91304 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/13/2021 | Partial Approval | CHRIS CHRISTENSEN |
| Pre-Inspection | 8/13/2021 | Approved | CHRIS CHRISTENSEN |
| Pre-Inspection | 10/12/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 2/3/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| Sewer | 2/3/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| Underground Mechanical | 3/21/2022 | Partial Approval | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 5/2/2022 | Partial Approval | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 5/2/2022 | Conditional Approval | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 5/2/2022 | Partial Approval | HAMIK HARTOUNIAN |
| Sewer | 6/15/2022 | Partial Approval | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 7/29/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Insulation | 7/29/2022 | Partial Approval | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 12/8/2022 | Approved | HAMIK HARTOUNIAN |
| Drywall Nailing | 12/8/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| ELECTRICAL-Final | 12/8/2022 | Approved | HAMIK HARTOUNIAN |
| Final | 12/8/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Final | 12/8/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Rough | 12/8/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| HVAC-Final | 12/8/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| MERV13>=Final | 12/8/2022 | Approved | HAMIK HARTOUNIAN |
| MERV13>=Rough | 12/8/2022 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Final | 12/8/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 12/8/2022 | Approved | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 12/8/2022 | SGSOV Not Ready | HAMIK HARTOUNIAN |
| Smoke Detectors | 12/8/2022 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 4/26/2023 | No Access for Inspection | JEFFREY MEAD |
| Drywall Nailing | 4/26/2023 | No Access for Inspection | JEFFREY MEAD |
| Final | 4/26/2023 | No Access for Inspection | JEFFREY MEAD |
| Green Building Final | 4/26/2023 | No Access for Inspection | JEFFREY MEAD |
| Green Building Rough | 4/26/2023 | No Access for Inspection | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 4/26/2023 | SGSOV Not Ready | JEFFREY MEAD |
| BUILDING-Rough-Frame | 5/2/2023 | Approved | SCOTT FINNILA |
| Drywall Nailing | 5/2/2023 | Approved | SCOTT FINNILA |
| Final | 5/2/2023 | OK to Issue CofO | SCOTT FINNILA |
| Green Building Final | 5/2/2023 | Approved | SCOTT FINNILA |
| Green Building Rough | 5/2/2023 | Approved | SCOTT FINNILA |
| HVAC-Final | 5/2/2023 | Approved | SCOTT FINNILA |
| SGSOV-Seismic Gas S/O Valve | 5/2/2023 | SGSOV Approved | SCOTT FINNILA |