1935 N TAFT AVE 90068
Certificate Information: 1935 N TAFT AVE 90068
- Application / Permit
- 20016-20000-10344
- Plan Check / Job No.
- B20VN06017
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED 24' X 18' 2-CAR GARAGE TO ACCESSORY DWELLING UNIT. ALL WORK DONE PER STRUCTURAL ENGINEERING.
- Permit Issued
- Issued on 6/26/2020
- Issuing Office
- Current Status
- CofO Issued on 9/2/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/27/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/1/2020 | JEROME MAGAT PALMA |
| Corrections Issued | 5/5/2020 | JEROME MAGAT PALMA |
| Applicant returned to address corrections | 5/22/2020 | LUIS RINCON |
| Applicant returned to address corrections | 6/17/2020 | GURUNATH NESARAJAH |
| Plan Check Approved | 6/18/2020 | GURUNATH NESARAJAH |
| Issued | 6/26/2020 | APPLICANT |
| CofO in Progress | 8/18/2021 | JOSEPH MCGARRY |
| CofO Issued | 9/2/2021 | DEROLD HAUFF |
| Permit Finaled | 9/2/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| HPOZ | Cleared | 5/6/2020 | DEEPEAKA DHALIWAL |
| Address approval | Cleared | 5/14/2020 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 5/15/2020 | CELINA MORENO |
| Grading Pre-Inspection | Cleared | 5/15/2020 | VASIL MIHALEV |
| Sewer availability | Cleared | 5/18/2020 | WALLIE JONG |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/14/2020 | Approved | BRIAN SULLIVAN |
| PLUMBING-Rough | 7/14/2020 | Partial Approval | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 7/28/2020 | Partial Approval | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 7/28/2020 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 7/28/2020 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 7/28/2020 | Approved | ENRIQUE MIRELES |
| Insulation | 7/30/2020 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 8/6/2020 | Corrections Issued | JOSEPH MCGARRY |
| Insulation | 8/6/2020 | Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 8/13/2020 | Approved | BRIAN SULLIVAN |
| Drywall Nailing | 8/13/2020 | Approved | BRIAN SULLIVAN |
| HVAC-Rough | 8/13/2020 | Approved | BRIAN SULLIVAN |
| Interior/Exterior Lathing | 9/8/2020 | Approved | BRIAN SULLIVAN |
| Shower Pan | 9/8/2020 | Approved | BRIAN SULLIVAN |
| Final | 2/11/2021 | Corrections Issued | RAUL BARAJAS |
| Green Building Final | 2/11/2021 | Not Ready for Inspection | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 2/11/2021 | SGSOV Approved | RAUL BARAJAS |
| Smoke Detectors | 2/11/2021 | Not Ready for Inspection | RAUL BARAJAS |
| Final | 3/16/2021 | Corrections Issued | JOSEPH MCGARRY |
| Green Building Final | 3/16/2021 | Approved | JOSEPH MCGARRY |
| Smoke Detectors | 3/16/2021 | Approved | JOSEPH MCGARRY |
| Final | 8/18/2021 | OK to Issue CofO | JOSEPH MCGARRY |