1935 N TAFT AVE 90068

Certificate Information: 1935 N TAFT AVE 90068

Application / Permit
20016-20000-10344
Plan Check / Job No.
B20VN06017
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED 24' X 18' 2-CAR GARAGE TO ACCESSORY DWELLING UNIT. ALL WORK DONE PER STRUCTURAL ENGINEERING.
Permit Issued
Issued on 6/26/2020
Issuing Office
Current Status
CofO Issued on 9/2/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/27/2020 APPLICANT
Assigned to Plan Check Engineer 5/1/2020 JEROME MAGAT PALMA
Corrections Issued 5/5/2020 JEROME MAGAT PALMA
Applicant returned to address corrections 5/22/2020 LUIS RINCON
Applicant returned to address corrections 6/17/2020 GURUNATH NESARAJAH
Plan Check Approved 6/18/2020 GURUNATH NESARAJAH
Issued 6/26/2020 APPLICANT
CofO in Progress 8/18/2021 JOSEPH MCGARRY
CofO Issued 9/2/2021 DEROLD HAUFF
Permit Finaled 9/2/2021 DEROLD HAUFF

Permit Application Clearance Information

HPOZ Cleared 5/6/2020 DEEPEAKA DHALIWAL
Address approval Cleared 5/14/2020 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 5/15/2020 CELINA MORENO
Grading Pre-Inspection Cleared 5/15/2020 VASIL MIHALEV
Sewer availability Cleared 5/18/2020 WALLIE JONG

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/14/2020 Approved BRIAN SULLIVAN
PLUMBING-Rough 7/14/2020 Partial Approval BRIAN SULLIVAN
BUILDING-Rough-Frame 7/28/2020 Partial Approval ENRIQUE MIRELES
ELECTRICAL-Rough 7/28/2020 Approved ENRIQUE MIRELES
Green Building Rough 7/28/2020 Approved ENRIQUE MIRELES
PLUMBING-Rough 7/28/2020 Approved ENRIQUE MIRELES
Insulation 7/30/2020 Not Ready for Inspection CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 8/6/2020 Corrections Issued JOSEPH MCGARRY
Insulation 8/6/2020 Approved JOSEPH MCGARRY
BUILDING-Rough-Frame 8/13/2020 Approved BRIAN SULLIVAN
Drywall Nailing 8/13/2020 Approved BRIAN SULLIVAN
HVAC-Rough 8/13/2020 Approved BRIAN SULLIVAN
Interior/Exterior Lathing 9/8/2020 Approved BRIAN SULLIVAN
Shower Pan 9/8/2020 Approved BRIAN SULLIVAN
Final 2/11/2021 Corrections Issued RAUL BARAJAS
Green Building Final 2/11/2021 Not Ready for Inspection RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 2/11/2021 SGSOV Approved RAUL BARAJAS
Smoke Detectors 2/11/2021 Not Ready for Inspection RAUL BARAJAS
Final 3/16/2021 Corrections Issued JOSEPH MCGARRY
Green Building Final 3/16/2021 Approved JOSEPH MCGARRY
Smoke Detectors 3/16/2021 Approved JOSEPH MCGARRY
Final 8/18/2021 OK to Issue CofO JOSEPH MCGARRY