5407-5409 N CLYBOURN AVE 91601
Certificate Information: 5407-5409 N CLYBOURN AVE 91601
- Application / Permit
- 20016-20000-10340
- Plan Check / Job No.
- B20VN06014
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- SUPPLEMENTAL TO 18014-20000-04254 TO CONVERT 28'3-1/2" X18'3" PORTION OF THE (E) SFD INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (e) AND ADD 9'7-1/2" X 8'3" PATIO COVER. "COMPLY WITH DEPARTMENT ORDER effective date 07/02/2018. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
- Permit Issued
- Issued on 3/13/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/19/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/13/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/20/2020 | MARVEL DELACRUZ |
| Corrections Issued | 5/28/2020 | MARVEL DELACRUZ |
| Applicant returned to address corrections | 4/20/2022 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 6/23/2022 | RAPHAEL ROSAS |
| Building Plans Picked Up | 6/27/2022 | APPLICANT |
| Applicant returned to address corrections | 2/13/2023 | MARVEL DELACRUZ |
| Plan Check Approved | 3/13/2023 | MARVEL DELACRUZ |
| Issued | 3/13/2023 | APPLICANT |
| CofO in Progress | 1/25/2024 | SCOTT SHUSTER |
| Permit Finaled | 4/19/2024 | DAVID JAMES |
| CofO Issued | 4/19/2024 | DAVID JAMES |
| Permit Finaled | 4/19/2024 | DAVID JAMES |
Permit Application Clearance Information
| Address approval | Cleared | 4/2/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 4/4/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 4/4/2022 | CARLOS AGUILERA |
| Low Impact Development | Cleared | 11/7/2022 | AMMAR ELTAWIL |
| Roof/Waste drainage to street | Cleared | 11/18/2022 | JOHN LIN |
Contact Information
| Architect | Lepair,, Yoram A; Lic. No.: C36127 | 1551 S ROBERTSON BLVD #D LOS ANGELES, CA 90035 |
| Contractor | Owner-Builder | , |
| Engineer | Truong,, Phong; Lic. No.: C70784 | 20439 E CRESTLINE DRIVE WALNUT, CA 91789 |
Inspector Information
| ARA SINANIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HASANTHA WEERASEKARA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| SCOTT SHUSTER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOEL GUARDADO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIYA MIHALEVA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOSE RUBIO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID JAMES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID HICKMAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN HAMILTON, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN STEPHENS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| PIERRE VEGA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK VAN SLOOTEN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MICKEY YAMASHITA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RICHARD ROBLES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HAGOP BADOSSIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM BEAUCHAMP, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK DOVICO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| THOMAS WOODS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL VASQUEZ, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| AUGUSTUS ALBAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| FELIPE PENICHE, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| LEO MILBAUER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/12/2023 | Partial Inspection | SCOTT SHUSTER |
| BUILDING-Rough-Frame | 9/26/2023 | Partial Approval | SCOTT SHUSTER |
| ELECTRICAL-Rough | 9/26/2023 | Partial Approval | SCOTT SHUSTER |
| Green Building Rough | 9/26/2023 | Partial Approval | SCOTT SHUSTER |
| PLUMBING-Rough | 9/26/2023 | Approved | SCOTT SHUSTER |
| BUILDING-Rough-Frame | 10/3/2023 | Partial Inspection | SCOTT SHUSTER |
| Green Building Rough | 10/3/2023 | Partial Inspection | SCOTT SHUSTER |
| BUILDING-Rough-Frame | 10/24/2023 | Partial Inspection | SCOTT SHUSTER |
| ELECTRICAL-Rough | 10/24/2023 | Approved | SCOTT SHUSTER |
| Green Building Rough | 10/24/2023 | Approved | SCOTT SHUSTER |
| PLUMBING-Rough | 10/24/2023 | Approved | SCOTT SHUSTER |
| Insulation | 10/26/2023 | Approved | SCOTT SHUSTER |
| BUILDING-Rough-Frame | 10/30/2023 | Approved | SCOTT SHUSTER |
| Drywall Nailing | 10/30/2023 | Partial Approval | SCOTT SHUSTER |
| Footing/Foundation/Slab | 10/30/2023 | Approved | SCOTT SHUSTER |
| Drywall Nailing | 11/2/2023 | Approved | SCOTT SHUSTER |
| ELECTRICAL-Final | 11/14/2023 | Partial Approval | SCOTT SHUSTER |
| Final | 11/14/2023 | Partial Approval | SCOTT SHUSTER |
| Green Building Final | 11/14/2023 | Approved | SCOTT SHUSTER |
| HVAC-Final | 11/14/2023 | Partial Approval | SCOTT SHUSTER |
| PLUMBING-Final | 11/14/2023 | Approved | SCOTT SHUSTER |
| Smoke Detectors | 11/14/2023 | Approved | SCOTT SHUSTER |
| ELECTRICAL-Final | 12/7/2023 | Approved | SCOTT SHUSTER |
| Final | 12/7/2023 | Conditional Approval | SCOTT SHUSTER |
| HVAC-Final | 12/7/2023 | Approved | SCOTT SHUSTER |
| PLUMBING-Final | 12/7/2023 | Approved | SCOTT SHUSTER |
| Final | 1/25/2024 | OK to Issue CofO | SCOTT SHUSTER |