5407-5409 N CLYBOURN AVE 91601

Certificate Information: 5407-5409 N CLYBOURN AVE 91601

Application / Permit
20016-20000-10340
Plan Check / Job No.
B20VN06014
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
SUPPLEMENTAL TO 18014-20000-04254 TO CONVERT 28'3-1/2" X18'3" PORTION OF THE (E) SFD INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (e) AND ADD 9'7-1/2" X 8'3" PATIO COVER. "COMPLY WITH DEPARTMENT ORDER effective date 07/02/2018. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 3/13/2023
Issuing Office
Valley
Current Status
CofO Issued on 4/19/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/13/2020 APPLICANT
Assigned to Plan Check Engineer 5/20/2020 MARVEL DELACRUZ
Corrections Issued 5/28/2020 MARVEL DELACRUZ
Applicant returned to address corrections 4/20/2022 RAPHAEL ROSAS
Applicant returned to address corrections 6/23/2022 RAPHAEL ROSAS
Building Plans Picked Up 6/27/2022 APPLICANT
Applicant returned to address corrections 2/13/2023 MARVEL DELACRUZ
Plan Check Approved 3/13/2023 MARVEL DELACRUZ
Issued 3/13/2023 APPLICANT
CofO in Progress 1/25/2024 SCOTT SHUSTER
Permit Finaled 4/19/2024 DAVID JAMES
CofO Issued 4/19/2024 DAVID JAMES
Permit Finaled 4/19/2024 DAVID JAMES

Permit Application Clearance Information

Address approval Cleared 4/2/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 4/4/2022 CARLOS AGUILERA
Sewer availability Cleared 4/4/2022 CARLOS AGUILERA
Low Impact Development Cleared 11/7/2022 AMMAR ELTAWIL
Roof/Waste drainage to street Cleared 11/18/2022 JOHN LIN

Contact Information

Architect Lepair,, Yoram A; Lic. No.: C36127 1551 S ROBERTSON BLVD #D      LOS ANGELES, CA 90035
Contractor Owner-Builder       ,
Engineer Truong,, Phong; Lic. No.: C70784 20439 E CRESTLINE DRIVE      WALNUT, CA 91789

Inspector Information

ARA SINANIAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
HASANTHA WEERASEKARA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
SCOTT SHUSTER, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOEL GUARDADO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARIYA MIHALEVA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOSE RUBIO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
DAVID JAMES, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
DAVID HICKMAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOHN HAMILTON, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOHN STEPHENS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
PIERRE VEGA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARK VAN SLOOTEN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MICKEY YAMASHITA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
RICHARD ROBLES, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
HAGOP BADOSSIAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
KIM BEAUCHAMP, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARK DOVICO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
THOMAS WOODS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
RAUL VASQUEZ, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
AUGUSTUS ALBAS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
FELIPE PENICHE, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
LEO MILBAUER, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/12/2023 Partial Inspection SCOTT SHUSTER
BUILDING-Rough-Frame 9/26/2023 Partial Approval SCOTT SHUSTER
ELECTRICAL-Rough 9/26/2023 Partial Approval SCOTT SHUSTER
Green Building Rough 9/26/2023 Partial Approval SCOTT SHUSTER
PLUMBING-Rough 9/26/2023 Approved SCOTT SHUSTER
BUILDING-Rough-Frame 10/3/2023 Partial Inspection SCOTT SHUSTER
Green Building Rough 10/3/2023 Partial Inspection SCOTT SHUSTER
BUILDING-Rough-Frame 10/24/2023 Partial Inspection SCOTT SHUSTER
ELECTRICAL-Rough 10/24/2023 Approved SCOTT SHUSTER
Green Building Rough 10/24/2023 Approved SCOTT SHUSTER
PLUMBING-Rough 10/24/2023 Approved SCOTT SHUSTER
Insulation 10/26/2023 Approved SCOTT SHUSTER
BUILDING-Rough-Frame 10/30/2023 Approved SCOTT SHUSTER
Drywall Nailing 10/30/2023 Partial Approval SCOTT SHUSTER
Footing/Foundation/Slab 10/30/2023 Approved SCOTT SHUSTER
Drywall Nailing 11/2/2023 Approved SCOTT SHUSTER
ELECTRICAL-Final 11/14/2023 Partial Approval SCOTT SHUSTER
Final 11/14/2023 Partial Approval SCOTT SHUSTER
Green Building Final 11/14/2023 Approved SCOTT SHUSTER
HVAC-Final 11/14/2023 Partial Approval SCOTT SHUSTER
PLUMBING-Final 11/14/2023 Approved SCOTT SHUSTER
Smoke Detectors 11/14/2023 Approved SCOTT SHUSTER
ELECTRICAL-Final 12/7/2023 Approved SCOTT SHUSTER
Final 12/7/2023 Conditional Approval SCOTT SHUSTER
HVAC-Final 12/7/2023 Approved SCOTT SHUSTER
PLUMBING-Final 12/7/2023 Approved SCOTT SHUSTER
Final 1/25/2024 OK to Issue CofO SCOTT SHUSTER