5706-5706 1/2 N COMANCHE AVE 91367
Certificate Information: 5706-5706 1/2 N COMANCHE AVE 91367
- Application / Permit
- 20016-20000-10296
- Plan Check / Job No.
- B20VN05987
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT 22' 7" X 21' 7" ATTACHED 2-CAR GARAGE AND 10' 1" X 21' 7" PORTION OF (E) SFD TO (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(E)(1)(A). ALL WORK DONE PER WFPP.
- Permit Issued
- Issued on 8/5/2020
- Issuing Office
- Current Status
- CofO Issued on 10/25/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/28/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/6/2020 | GURUNATH NESARAJAH |
| Corrections Issued | 5/6/2020 | GURUNATH NESARAJAH |
| Plan Check Approved | 8/4/2020 | JENNIFER LEE |
| Issued | 8/5/2020 | APPLICANT |
| CofO in Progress | 10/20/2021 | HENRY KIM |
| Permit Finaled | 10/25/2021 | JOHN JANSON |
| CofO Issued | 10/25/2021 | JOHN JANSON |
| Permit Finaled | 10/25/2021 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 5/13/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 5/13/2020 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 5/14/2020 | JOHN TRIANTAFYLLOS |
| Grading Pre-Inspection | Cleared | 8/4/2020 | GURUNATH NESARAJAH |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/16/2020 | Approved | HENRY KIM |
| PLUMBING-Rough | 9/16/2020 | Partial Approval | HENRY KIM |
| Pre-Inspection | 9/16/2020 | Approved | HENRY KIM |
| BUILDING-Rough-Frame | 10/1/2020 | Corrections Issued | HENRY KIM |
| ELECTRICAL-Rough | 10/1/2020 | Corrections Issued | HENRY KIM |
| PLUMBING-Rough | 10/1/2020 | Approved | HENRY KIM |
| Pre-Inspection | 2/10/2021 | Approved | HENRY KIM |
| ELECTRICAL-Rough | 2/22/2021 | Not Ready for Inspection | HENRY KIM |
| Insulation | 2/22/2021 | Partial Approval | HENRY KIM |
| PLUMBING-Rough | 2/22/2021 | Not Ready for Inspection | HENRY KIM |
| Insulation | 3/2/2021 | Partial Approval | HENRY KIM |
| Rough-Elec/Plmb/HVAC | 3/2/2021 | Approved | HENRY KIM |
| Drywall Nailing | 3/8/2021 | Partial Approval | HENRY KIM |
| BUILDING-Rough-Frame | 3/11/2021 | Approved | HENRY KIM |
| Green Building Rough | 3/11/2021 | Approved | HENRY KIM |
| Interior/Exterior Lathing | 3/11/2021 | Approved | HENRY KIM |
| MERV13>=Rough | 3/11/2021 | Approved | HENRY KIM |
| Drywall Nailing | 3/19/2021 | Approved | HENRY KIM |
| Green Building Final | 3/19/2021 | Not Ready for Inspection | HENRY KIM |
| Green Building Final | 3/24/2021 | Partial Approval | HENRY KIM |
| ELECTRICAL-Final | 6/25/2021 | Corrections Issued | HENRY KIM |
| Final | 6/25/2021 | Corrections Issued | HENRY KIM |
| Gas Test | 6/25/2021 | Corrections Issued | HENRY KIM |
| Green Building Final | 6/25/2021 | Corrections Issued | HENRY KIM |
| HVAC-Final | 6/25/2021 | Corrections Issued | HENRY KIM |
| PLUMBING-Final | 6/25/2021 | Corrections Issued | HENRY KIM |
| SGSOV-Seismic Gas S/O Valve | 6/25/2021 | SGSOV Approved | HENRY KIM |
| Smoke Detectors | 6/25/2021 | Approved | HENRY KIM |
| ELECTRICAL-Final | 8/13/2021 | Corrections Issued | HENRY KIM |
| Final | 8/13/2021 | Corrections Issued | HENRY KIM |
| Gas Test | 8/13/2021 | Corrections Issued | HENRY KIM |
| Green Building Final | 8/13/2021 | Approved | HENRY KIM |
| HVAC-Final | 8/13/2021 | Corrections Issued | HENRY KIM |
| MERV13>=Final | 8/13/2021 | Approved | HENRY KIM |
| PLUMBING-Final | 8/13/2021 | Approved | HENRY KIM |
| ELECTRICAL-Final | 10/20/2021 | Approved | HENRY KIM |
| Final | 10/20/2021 | OK to Issue CofO | HENRY KIM |
| Gas Test | 10/20/2021 | Approved | HENRY KIM |
| HVAC-Final | 10/20/2021 | Approved | HENRY KIM |
| Service/Power Release | 10/20/2021 | Approved | HENRY KIM |