8331-8333 N KEOKUK AVE 91306

Certificate Information: 8331-8333 N KEOKUK AVE 91306

Application / Permit
20016-20000-10008
Plan Check / Job No.
B20VN05824
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT 18'-7" X 26'-11" ATTACHED GARAGE TO JUNIOR ACCESSORY DWELLING UNIT. ALL WORK DONE PER WFPP.
Permit Issued
Issued on 7/21/2020
Issuing Office
Current Status
CofO Corrected on 7/21/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/6/2020 APPLICANT
Assigned to Plan Check Engineer 5/13/2020 GURUNATH NESARAJAH
Corrections Issued 5/14/2020 GURUNATH NESARAJAH
Applicant returned to address corrections 6/5/2020 RAPHAEL ROSAS
Plan Check Approved 7/2/2020 RAPHAEL ROSAS
Issued 7/21/2020 APPLICANT
Building Plans Picked Up 7/23/2020 APPLICANT
CofO in Progress 7/19/2022 ROBERT GOLD
Re-Activate Permit 7/21/2022 MICHAEL SMITH
CofO Issued-Status Void 7/21/2022 MICHAEL SMITH
Permit Finaled-Status Void 7/21/2022 MICHAEL SMITH
Permit Finaled 7/21/2022 MICHAEL SMITH
CofO Corrected 7/21/2022 MICHAEL SMITH
Permit Finaled 7/21/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 5/18/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 5/18/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 5/18/2020 JOHN TRIANTAFYLLOS

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/11/2020 Corrections Issued DAVID STEPANYAN
Pre-Inspection 9/22/2020 Corrections Issued DAVID STEPANYAN
Deputy Drilled-In Anchors 12/15/2020 Conditional Approval DAVID STEPANYAN
Excavation/Setback/Form/Re-Bar 12/21/2020 Partial Approval DAVID STEPANYAN
BUILDING-Rough-Frame 1/11/2021 Partial Approval DAVID STEPANYAN
Insulation 1/11/2021 Partial Approval DAVID STEPANYAN
Floor/Roof Diaphrgm/Shear Wall 1/29/2021 Partial Approval DAVID STEPANYAN
Interior/Exterior Lathing 2/8/2021 Partial Approval DAVID STEPANYAN
Wood Frame 3/2/2022 Not Ready for Inspection DAVID SCANTLIN
Insulation 3/8/2022 Not Ready for Inspection JOHN KIDWELL
Footing/Foundation/Slab 3/14/2022 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 3/14/2022 Partial Approval CHRIS CHRISTENSEN
Wood Frame 3/22/2022 Partial Approval CHRIS CHRISTENSEN
ELECTRICAL-Rough 4/4/2022 Not Ready for Inspection CHRIS CHRISTENSEN
PLUMBING-Rough 4/4/2022 Partial Approval CHRIS CHRISTENSEN
ELECTRICAL-Rough 4/18/2022 Partial Approval CHRIS CHRISTENSEN
Insulation 6/13/2022 Corrections Issued CHRIS CHRISTENSEN
Interior/Exterior Lathing 6/13/2022 Partial Approval CHRIS CHRISTENSEN
Insulation 6/15/2022 Partial Approval JESUS PINEDA
Drywall Nailing 6/17/2022 Partial Approval KRISTEN CAUSEY
Shower Pan 6/17/2022 Corrections Issued KRISTEN CAUSEY
BUILDING-Rough-Frame 6/21/2022 Partial Approval CHRIS CHRISTENSEN
ELECTRICAL-Rough 6/21/2022 Approved CHRIS CHRISTENSEN
Insulation 6/21/2022 Partial Approval CHRIS CHRISTENSEN
Shower Pan 6/21/2022 Approved CHRIS CHRISTENSEN
Drywall Nailing 6/24/2022 Partial Approval JESUS PINEDA
Interior/Exterior Lathing 6/24/2022 Approved JESUS PINEDA
Drywall Nailing 6/29/2022 Approved CHRIS CHRISTENSEN
HVAC-Rough 6/29/2022 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 6/29/2022 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 7/1/2022 Approved CHRIS CHRISTENSEN
ELECTRICAL-Final 7/1/2022 Not Ready for Inspection CHRIS CHRISTENSEN
Final 7/1/2022 Not Ready for Inspection CHRIS CHRISTENSEN
Gas Test 7/1/2022 Not Ready for Inspection CHRIS CHRISTENSEN
Green Building Final 7/1/2022 Corrections Issued CHRIS CHRISTENSEN
Green Building Rough 7/1/2022 Approved CHRIS CHRISTENSEN
HVAC-Final 7/1/2022 Not Ready for Inspection CHRIS CHRISTENSEN
PLUMBING-Final 7/1/2022 Not Ready for Inspection CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 7/1/2022 SGSOV Not Ready CHRIS CHRISTENSEN
Smoke Detectors 7/1/2022 Not Ready for Inspection CHRIS CHRISTENSEN
Final 7/7/2022 Corrections Issued PETER FOLLING
Green Building Final 7/7/2022 Approved PETER FOLLING
SGSOV-Seismic Gas S/O Valve 7/7/2022 SGSOV Approved PETER FOLLING
Service/Power Release 7/7/2022 Approved PETER FOLLING
Smoke Detectors 7/7/2022 Approved PETER FOLLING
Deputy Drilled-In Anchors 7/19/2022 Approved ROBERT GOLD
Final 7/19/2022 OK to Issue CofO ROBERT GOLD