6129 N ALONZO AVE 91316
Certificate Information: 6129 N ALONZO AVE 91316
- Application / Permit
- 20016-20000-09974
- Plan Check / Job No.
- B20VN05810
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ECPC: CONVERT THE (E) DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 2/25/2021
- Issuing Office
- Current Status
- CofO Issued on 9/30/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/22/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/27/2020 | KAVIAN REFAHI |
| Corrections Issued | 4/27/2020 | KAVIAN REFAHI |
| Building Plans Picked Up | 4/30/2020 | APPLICANT |
| Applicant returned to address corrections | 6/25/2020 | PARISA ZAHABI |
| Plan Check Approved | 7/6/2020 | JEROME MAGAT PALMA |
| Issued | 2/25/2021 | APPLICANT |
| CofO in Progress | 9/15/2025 | MORRIS JACKSON |
| Permit Finaled | 9/30/2025 | MICHAEL PELHAM |
| CofO Issued | 9/30/2025 | MICHAEL PELHAM |
| Permit Finaled | 9/30/2025 | MICHAEL PELHAM |
Permit Application Clearance Information
| Address approval | Cleared | 6/12/2020 | ADRIAN CASTRO |
| Construction within easement | Cleared | 6/12/2020 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 6/12/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 6/12/2020 | ADRIAN CASTRO |
| ZI | Cleared | 6/16/2020 | PABLO ESTRADA |
Contact Information
| Contractor | Turn Key Construction And Design Inc; Lic. No.: 1061590-B | 527 N VERDUGO ROAD GLENDALE, CA 91206 |
| Engineer | Azarbin,, Hamid Reza; Lic. No.: C64515 | 22655 COVELLO ST WEST HILLS, CA 91307 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/18/2021 | Approved | TROY SANDERS |
| PLUMBING-Rough | 5/18/2021 | Partial Approval | TROY SANDERS |
| Underground Mechanical | 5/18/2021 | Approved | TROY SANDERS |
| ELECTRICAL-Rough | 7/12/2021 | No Access for Inspection | STEVEN BACK |
| PLUMBING-Rough | 7/12/2021 | No Access for Inspection | STEVEN BACK |
| PLUMBING-Rough | 8/12/2021 | Corrections Issued | STEVEN BACK |
| BUILDING-Rough-Frame | 10/7/2021 | Corrections Issued | STEVEN BACK |
| PLUMBING-Rough | 10/7/2021 | Corrections Issued | STEVEN BACK |
| ELECTRICAL-Rough | 11/17/2021 | Corrections Issued | SEAN HAUPT |
| PLUMBING-Rough | 11/17/2021 | Approved | SEAN HAUPT |
| ELECTRICAL-Rough | 1/31/2022 | Corrections Issued | SEAN WIRCH |
| Floor/Roof Diaphrgm/Shear Wall | 1/31/2022 | Partial Approval | SEAN WIRCH |
| Green Building Rough | 1/31/2022 | Not Ready for Inspection | SEAN WIRCH |
| BUILDING-Rough-Frame | 2/8/2022 | Approved | SEAN HAUPT |
| ELECTRICAL-Rough | 2/8/2022 | Approved | SEAN HAUPT |
| Green Building Rough | 2/8/2022 | Partial Approval | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 3/15/2022 | Approved | SEAN HAUPT |
| Insulation | 3/15/2022 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 3/15/2022 | Approved | SEAN HAUPT |
| Drywall Nailing | 3/22/2022 | Approved | MORRIS JACKSON |
| Shower Pan | 3/22/2022 | Approved | MORRIS JACKSON |
| Interior/Exterior Lathing | 5/2/2022 | Approved | SEAN HAUPT |
| Underground Mechanical | 5/2/2022 | Approved | SEAN HAUPT |
| BUILDING-Rough-Frame | 7/15/2025 | Approved | MORRIS JACKSON |
| Final | 7/15/2025 | Corrections Issued | MORRIS JACKSON |
| Green Building Final | 7/15/2025 | Approved | MORRIS JACKSON |
| Green Building Rough | 7/15/2025 | Approved | MORRIS JACKSON |
| SGSOV-Seismic Gas S/O Valve | 7/15/2025 | SGSOV Approved | MORRIS JACKSON |
| Service/Power Release | 7/15/2025 | Approved | MORRIS JACKSON |
| Smoke Detectors | 7/15/2025 | Corrections Issued | MORRIS JACKSON |
| Final | 8/28/2025 | Not Ready for Inspection | MORRIS JACKSON |
| Smoke Detectors | 8/28/2025 | Not Ready for Inspection | MORRIS JACKSON |
| Final | 9/2/2025 | Not Ready for Inspection | MORRIS JACKSON |
| Smoke Detectors | 9/2/2025 | Approved | MORRIS JACKSON |
| Final | 9/15/2025 | OK to Issue CofO | MORRIS JACKSON |