8841 N TILDEN AVE 91402

Certificate Information: 8841 N TILDEN AVE 91402

Application / Permit
20016-20000-09874
Plan Check / Job No.
B20VN05750
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 18' X 20' DETACHED GARAGE TO (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(E)(1)(D) AND LAMC 12.22.A.33(C), (D), AND (G). ALL WORK PER WFPP.
Permit Issued
Issued on 8/13/2020
Issuing Office
Current Status
CofO Issued on 5/22/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/8/2020 APPLICANT
Assigned to Plan Check Engineer 5/14/2020 SEAN SHAHMIRI
Corrections Issued 5/15/2020 SEAN SHAHMIRI
Building Plans Picked Up 5/19/2020 APPLICANT
Plan Check Approved 8/12/2020 JENNIFER LEE
Issued 8/13/2020 APPLICANT
CofO in Progress 3/8/2021 GREGG CUMMINGS
CofO Issued 5/22/2021 MICHAEL SMITH
Permit Finaled 5/22/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 5/21/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 5/21/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 6/23/2020 JOHN TRIANTAFYLLOS
Construction near power lines Cleared 7/29/2020 RIDWAN HARDY
Construction within easement Cleared 7/29/2020 RIDWAN HARDY

Contact Information

Contractor A R M Builders Inc; Lic. No.: 915352-B 1080 S LA CIENEGA #311      LOS ANGELES, CA 90035

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/16/2020 Not Ready for Inspection GREGG CUMMINGS
Footing/Foundation/Slab 9/25/2020 Approved GREGG CUMMINGS
PLUMBING-Rough 9/25/2020 Partial Approval GREGG CUMMINGS
Sewer 9/25/2020 Approved GREGG CUMMINGS
BUILDING-Rough-Frame 10/15/2020 Corrections Issued GREGG CUMMINGS
ELECTRICAL-Rough 10/15/2020 Partial Inspection GREGG CUMMINGS
Green Building Rough 10/15/2020 Not Ready for Inspection GREGG CUMMINGS
BUILDING-Rough-Frame 10/20/2020 Approved GREGG CUMMINGS
ELECTRICAL-Rough 10/20/2020 Approved GREGG CUMMINGS
HVAC-Rough 10/20/2020 Approved GREGG CUMMINGS
PLUMBING-Rough 10/20/2020 Approved GREGG CUMMINGS
Insulation 10/26/2020 Approved MICHEL ABAJAN
Interior/Exterior Lathing 10/26/2020 Approved MICHEL ABAJAN
Green Building Rough 11/4/2020 Approved GREGG CUMMINGS
Shower Pan 11/4/2020 Approved GREGG CUMMINGS
Drywall Nailing 11/10/2020 Approved MICHEL ABAJAN
Interior/Exterior Lathing 11/10/2020 Approved MICHEL ABAJAN
Service/Power Release 1/29/2021 Not Ready for Inspection GREGG CUMMINGS
Final 2/4/2021 Corrections Issued GREGG CUMMINGS
Green Building Final 2/4/2021 Corrections Issued GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 2/4/2021 SGSOV Approved GREGG CUMMINGS
Smoke Detectors 2/4/2021 Approved GREGG CUMMINGS
Final 3/1/2021 Corrections Issued GREGG CUMMINGS
Green Building Final 3/1/2021 Approved GREGG CUMMINGS
ELECTRICAL-Final 3/8/2021 Approved GREGG CUMMINGS
Final 3/8/2021 OK to Issue CofO GREGG CUMMINGS
HVAC-Final 3/8/2021 Approved GREGG CUMMINGS
PLUMBING-Final 3/8/2021 Approved GREGG CUMMINGS