6015 S HALLDALE AVE 90047

Certificate Information: 6015 S HALLDALE AVE 90047

Application / Permit
20016-20000-09796
Plan Check / Job No.
B20VN05715
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) 16' X 24' DETACHED GARAGE TO ACCESSORY DWELLING UNIT. "COMPLY WITH DEPARTMENT ORDER effective date 04/17/2020. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 7/16/2020
Issuing Office
Current Status
CofO Issued on 10/27/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/6/2020 APPLICANT
Assigned to Plan Check Engineer 5/13/2020 ROSENDO MEDINA
Corrections Issued 5/15/2020 ROSENDO MEDINA
Plan Check Approved 7/16/2020 CRYSTEL MAALOUF
Issued 7/16/2020 APPLICANT
Building Plans Picked Up 7/17/2020 APPLICANT
CofO in Progress 8/4/2021 ANDEY CHAPARRO
Permit Finaled 10/27/2021 BRUCE TODD
CofO Issued 10/27/2021 BRUCE TODD
Permit Finaled 10/27/2021 BRUCE TODD

Permit Application Clearance Information

Address approval Cleared 5/22/2020 ELAINE LEI
Eng Process Fee Ord 176,300 Cleared 5/22/2020 ELAINE LEI
Sewer availability Cleared 5/22/2020 ELAINE LEI
ZI Cleared 5/26/2020 HELEN JADALI

Contact Information

Contractor Owner-Builder       ,
Engineer Rhee,, Kyle; Lic. No.: C78215 2753 WAVERLY DR 403      LOS ANGELES, CA 90039

Inspector Information

JOHN PARKER, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI
MICHAEL SERETTI, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI
HECTOR RODRIGUEZ, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI
BRUCE TODD, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI
JAVIER RAMOS SR, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI
MARIAN PODPORA, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 8/6/2020 Not Ready for Inspection KIM BEAUCHAMP
ELECTRICAL-Rough 8/6/2020 Not Ready for Inspection KIM BEAUCHAMP
Green Building Rough 8/6/2020 Corrections Issued KIM BEAUCHAMP
PLUMBING-Rough 8/6/2020 Not Ready for Inspection KIM BEAUCHAMP
Deputy Drilled-In Anchors 8/28/2020 Approved ENRIQUE PREZA
Footing/Foundation/Slab 9/3/2020 Corrections Issued KIM BEAUCHAMP
Deputy Drilled-In Anchors 9/23/2020 Approved KIM BEAUCHAMP
Footing/Foundation/Slab 9/24/2020 Approved KIM BEAUCHAMP
BUILDING-Rough-Frame 10/2/2020 Approved KIM BEAUCHAMP
ELECTRICAL-Rough 10/2/2020 Approved KIM BEAUCHAMP
Green Building Rough 10/2/2020 Approved KIM BEAUCHAMP
Insulation 10/2/2020 Approved KIM BEAUCHAMP
PLUMBING-Rough 10/2/2020 Approved KIM BEAUCHAMP
Drywall Nailing 10/13/2020 Approved KIM BEAUCHAMP
Shower Pan 10/13/2020 Approved KIM BEAUCHAMP
HVAC-Rough 10/29/2020 Corrections Issued KIM BEAUCHAMP
Interior/Exterior Lathing 10/29/2020 Approved KIM BEAUCHAMP
Final 3/10/2021 Corrections Issued ANDEY CHAPARRO
Green Building Final 3/10/2021 Not Ready for Inspection ANDEY CHAPARRO
SGSOV-Seismic Gas S/O Valve 3/10/2021 SGSOV Approved ANDEY CHAPARRO
Smoke Detectors 3/10/2021 Approved ANDEY CHAPARRO
Final 4/19/2021 Corrections Issued ANDEY CHAPARRO
Green Building Final 4/19/2021 Approved ANDEY CHAPARRO
ELECTRICAL-Final 8/3/2021 Approved ANDEY CHAPARRO
Final 8/3/2021 OK to Issue CofO ANDEY CHAPARRO
HVAC-Final 8/3/2021 Approved ANDEY CHAPARRO
PLUMBING-Final 8/3/2021 Approved ANDEY CHAPARRO