19917-19919 W LASSEN ST 91311
Certificate Information: 19917-19919 W LASSEN ST 91311
- Application / Permit
- 20016-20000-09732
- Plan Check / Job No.
- B20VN05708
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT 20'-5" X 31'-2" IRREGULAR SHAPED PORTION OF (E) SFD TO JUNIOR ACCESSORY DWELLING UNIT AND ADD 12' X 19' PATIO COVER TO REAR OF (E) SFD. INTERIOR REMODEL TO (E) SFD FOR (N) BATHROOM. ALL WORK DONE PER WFPP.
- Permit Issued
- Issued on 10/15/2020
- Issuing Office
- Current Status
- CofO Issued on 8/17/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/28/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/6/2020 | GURUNATH NESARAJAH |
| Corrections Issued | 5/6/2020 | GURUNATH NESARAJAH |
| Applicant returned to address corrections | 6/9/2020 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 6/29/2020 | JENNIFER LEE |
| Plan Check Approved | 10/6/2020 | GURUNATH NESARAJAH |
| Issued | 10/15/2020 | APPLICANT |
| Building Plans Picked Up | 5/20/2021 | APPLICANT |
| CofO in Progress | 6/8/2021 | JEFFREY PARD |
| Permit Finaled | 8/17/2021 | JOHN JANSON |
| CofO Issued | 8/17/2021 | JOHN JANSON |
| Permit Finaled | 8/17/2021 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 5/26/2020 | GABRIEL ROBLES |
| Sewer availability | Cleared | 5/26/2020 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 5/27/2020 | GABRIEL ROBLES |
| Roof/Waste drainage to street | Cleared | 9/21/2020 | ADRIAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 11/12/2020 | Partial Approval | JEFFREY PARD |
| BUILDING-Rough-Frame | 12/24/2020 | Corrections Issued | JEFFREY PARD |
| ELECTRICAL-Rough | 12/24/2020 | Approved | JEFFREY PARD |
| Green Building Rough | 12/24/2020 | Not Ready for Inspection | JEFFREY PARD |
| HVAC-Rough | 12/24/2020 | Approved | JEFFREY PARD |
| PLUMBING-Rough | 12/24/2020 | Approved | JEFFREY PARD |
| BUILDING-Rough-Frame | 1/4/2021 | Approved | JEFFREY PARD |
| Green Building Rough | 1/4/2021 | Approved | JEFFREY PARD |
| Insulation | 1/4/2021 | Approved | JEFFREY PARD |
| Drywall Nailing | 1/25/2021 | Approved | JEFFREY PARD |
| Final | 3/22/2021 | No Access for Inspection | JEFFREY PARD |
| Footing/Foundation/Slab | 3/22/2021 | No Access for Inspection | JEFFREY PARD |
| Green Building Final | 3/22/2021 | No Access for Inspection | JEFFREY PARD |
| SGSOV-Seismic Gas S/O Valve | 3/22/2021 | SGSOV Not Ready | JEFFREY PARD |
| Smoke Detectors | 3/22/2021 | No Access for Inspection | JEFFREY PARD |
| Pre-Inspection | 3/26/2021 | Corrections Issued | JEFFREY PARD |
| Final | 4/5/2021 | Partial Approval | JEFFREY PARD |
| Footing/Foundation/Slab | 4/5/2021 | Approved | JEFFREY PARD |
| Green Building Final | 4/5/2021 | Approved | JEFFREY PARD |
| SGSOV-Seismic Gas S/O Valve | 4/5/2021 | SGSOV Approved | JEFFREY PARD |
| Smoke Detectors | 4/5/2021 | Approved | JEFFREY PARD |