623 W 43RD ST 90037

Certificate Information: 623 W 43RD ST 90037

Application / Permit
20016-20000-09727
Plan Check / Job No.
B20VN05705
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT 30'-0" x 20'-0" (E)DETACHED GARAGE AND RECREATION ROOM/STORAGE INTO A (N) ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A).
Permit Issued
Issued on 7/6/2021
Issuing Office
Current Status
CofO Issued on 8/20/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/21/2020 APPLICANT
Assigned to Plan Check Engineer 4/24/2020 VLADIMIR ARUTYUNYAN
Corrections Issued 4/28/2020 VLADIMIR ARUTYUNYAN
Applicant returned to address corrections 3/3/2021 SARKIS HARABEDIAN
Plan Check Approved 5/6/2021 SARKIS HARABEDIAN
Issued 7/6/2021 APPLICANT
Building Plans Picked Up 10/18/2021 APPLICANT
CofO in Progress 8/17/2022 HORACE FULTZ
Permit Finaled 8/20/2022 DEROLD HAUFF
CofO Issued 8/20/2022 DEROLD HAUFF
Permit Finaled 8/20/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/11/2020 EMIL KYUPELYAN
Sewer availability Cleared 6/11/2020 EMIL KYUPELYAN
Eng Process Fee Ord 176,300 Cleared 8/25/2020 PAMELA TENEZA
Construction near power lines Cleared 1/6/2021 RIDWAN HARDY

Contact Information

Contractor Aguirre Rosales Construction Inc; Lic. No.: 1039164-B 19055 PARTHENIA STREET      NORTHRIDGE, CA 91324
Engineer Munroe,, Massie; Lic. No.: C59905 PO BOX 189      LA CANADA FLINTRIDGE, CA 91012

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/3/2021 Approved SABAS ALONSO
Footing/Foundation/Slab 12/21/2021 Partial Approval SABAS ALONSO
Footing/Foundation/Slab 1/19/2022 Approved SABAS ALONSO
Sewer 1/25/2022 Approved SABAS ALONSO
Underground Mechanical 1/25/2022 Approved SABAS ALONSO
BUILDING-Rough-Frame 2/28/2022 Partial Approval AMY COLIN
ELECTRICAL-Rough 2/28/2022 Approved AMY COLIN
PLUMBING-Rough 2/28/2022 Approved AMY COLIN
Insulation 3/11/2022 Partial Approval ADAM ESCOTO
Interior/Exterior Lathing 3/11/2022 Partial Approval ADAM ESCOTO
Floor/Roof Diaphrgm/Shear Wall 3/25/2022 Approved SABAS ALONSO
Insulation 3/25/2022 Approved SABAS ALONSO
Drywall Nailing 4/4/2022 Approved SABAS ALONSO
Interior/Exterior Lathing 4/4/2022 Approved SABAS ALONSO
BUILDING-Rough-Frame 5/27/2022 Approved SABAS ALONSO
Final 5/27/2022 Corrections Issued SABAS ALONSO
Green Building Final 5/27/2022 Corrections Issued SABAS ALONSO
Green Building Rough 5/27/2022 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 5/27/2022 SGSOV Not Ready SABAS ALONSO
Smoke Detectors 5/27/2022 Approved SABAS ALONSO
Final 6/10/2022 Corrections Issued SABAS ALONSO
Green Building Final 6/10/2022 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 6/10/2022 SGSOV Approved SABAS ALONSO
Final 8/8/2022 OK to Issue CofO SABAS ALONSO