529 N GOWER ST 90004
Certificate Information: 529 N GOWER ST 90004
- Application / Permit
- 20016-20000-09630
- Plan Check / Job No.
- B20VN05678
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert (E) garage to accessory dwelling unit per GCS 65852.2(e)(1)(A). All work per engineered design. See comments.
- Permit Issued
- Issued on 7/22/2021
- Issuing Office
- Current Status
- CofO Issued on 11/2/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/16/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/22/2020 | JASON JANGADA |
| Corrections Issued | 4/22/2020 | JASON JANGADA |
| Building Plans Picked Up | 5/4/2020 | APPLICANT |
| Applicant returned to address corrections | 1/7/2021 | JASON JANGADA |
| Applicant returned to address corrections | 2/22/2021 | JASON JANGADA |
| Plan Check Approved | 7/19/2021 | KHUONG TRUONG |
| Issued | 7/22/2021 | APPLICANT |
| CofO in Progress | 11/30/2021 | MASHEL JONGERT |
| No Progress | 1/25/2023 | SCOTT FINNILA |
| CofO in Progress | 10/30/2023 | SCOTT FINNILA |
| CofO Issued | 11/2/2023 | DEROLD HAUFF |
| Permit Finaled | 11/2/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 12/7/2020 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 12/7/2020 | RENZ SORIANO |
| Sewer availability | Cleared | 12/7/2020 | RENZ SORIANO |
| Construction near power lines | Cleared | 12/21/2020 | OSCAR CASTRO |
| Construction within easement | Cleared | 12/21/2020 | OSCAR CASTRO |
Contact Information
| Contractor | Root Enterprises Inc; Lic. No.: 872584-B | 17216 SATICOY ST #180 VAN NUYS, CA 91406 |
| Engineer | Garcia,, Lionel Jesus; Lic. No.: S4653 | 24702 NARBONNE AVE LOMITA, CA 90717 |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 7/30/2021 | Approved | CHRIS CHRISTENSEN |
| HVAC-Rough | 7/30/2021 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 7/30/2021 | Approved | CHRIS CHRISTENSEN |
| Wood Frame | 7/30/2021 | Partial Approval | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 8/9/2021 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 8/9/2021 | Conditional Approval | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 8/9/2021 | Partial Approval | CHRIS CHRISTENSEN |
| METHANE-Rough | 8/9/2021 | Approved | CHRIS CHRISTENSEN |
| Insulation | 8/17/2021 | Approved | ARTHUR SARGSYAN |
| Shower Pan | 8/17/2021 | Approved | ARTHUR SARGSYAN |
| Drywall Nailing | 8/27/2021 | Conditional Approval | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 9/16/2021 | Partial Approval | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 11/19/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| Final | 11/19/2021 | Corrections Issued | ARTHUR SARGSYAN |
| Green Building Final | 11/19/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| Green Building Rough | 11/19/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 11/19/2021 | SGSOV Approved | ARTHUR SARGSYAN |
| Smoke Detectors | 11/19/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| BUILDING-Rough-Frame | 11/29/2021 | Approved | MASHEL JONGERT |
| ELECTRICAL-Final | 11/29/2021 | Approved | MASHEL JONGERT |
| Final | 11/29/2021 | OK to Issue CofO | MASHEL JONGERT |
| Green Building Final | 11/29/2021 | Approved | MASHEL JONGERT |
| Green Building Rough | 11/29/2021 | Approved | MASHEL JONGERT |
| HVAC-Final | 11/29/2021 | Approved | MASHEL JONGERT |
| Interior/Exterior Lathing | 11/29/2021 | Approved | MASHEL JONGERT |
| PLUMBING-Final | 11/29/2021 | Approved | MASHEL JONGERT |
| Smoke Detectors | 11/29/2021 | Approved | MASHEL JONGERT |
| Special/Order Compliance | 1/27/2023 | Corrections Issued | JEFFREY MEAD |