7546-7548 N LILLA PL 91304

Certificate Information: 7546-7548 N LILLA PL 91304

Application / Permit
20016-20000-09615
Plan Check / Job No.
B20VN05669
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
FIRE DAMAGE INTERIOR REPAIR AND REFRAME ROOF AT ENTRY/LIVING ROOM/KITCHEN, CONVERT 615SF EXISTING GARAGE TO (N) CCESSORY DWELLING, ADD 486SF NEW PATIO AT REAR, AND REROOF ENTIRE BUILDING.
Permit Issued
Issued on 9/11/2020
Issuing Office
Current Status
CofO Issued on 8/26/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/22/2020 APPLICANT
Assigned to Plan Check Engineer 5/7/2020 DAWN MC NULTY
Corrections Issued 5/12/2020 DAWN MC NULTY
Quality Review Completed 5/13/2020 CHON CHIO KUO
Building Plans Picked Up 5/15/2020 APPLICANT
Green Plans Picked Up 5/19/2020 APPLICANT
Applicant returned to address corrections 6/30/2020 DAWN MC NULTY
Applicant returned to address corrections 7/31/2020 DAWN MC NULTY
Plan Check Approved 8/14/2020 DAWN MC NULTY
Issued 9/11/2020 APPLICANT
CofO in Progress 8/26/2021 DAVID STEPANYAN
Permit Finaled 8/26/2021 JOHN JANSON
CofO Issued 8/26/2021 JOHN JANSON
Permit Finaled 8/26/2021 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 6/8/2020 JOHN LIN
CPC Cleared 6/9/2020 STEVEN WECHSLER
Eng Process Fee Ord 176,300 Cleared 6/9/2020 JOHN LIN
Green Code Cleared 6/23/2020 AARON COSTA
Grading Pre-Inspection Cleared 7/29/2020 PATRICK MISCHLICH
Low Impact Development Cleared 8/6/2020 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 8/20/2020 JOHN LIN
Sewer availability Cleared 8/20/2020 JOHN LIN

Contact Information

Architect Althaus,, Andrew Ernst; Lic. No.: C25002 340 N WESTLAKE BLVD # 250      WESTLAKE VILLAGE, CA 91362
Contractor Blackpointe Group Construction & Management Inc; Lic. No.: 969297-B 3483 OLD CONEJO ROAD SUITE 206      NEWBURY, CA 91320
Engineer Judd,, Shane Dennis; Lic. No.: C70991 17 E HIGH ST STE A      MOORPARK, CA 93021

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/2/2020 Corrections Issued DAVID STEPANYAN
Excavation/Setback/Form/Re-Bar 11/23/2020 Partial Approval DAVID STEPANYAN
Footing/Foundation/Slab 11/23/2020 Partial Approval DAVID STEPANYAN
Deputy Drilled-In Anchors 12/18/2020 Conditional Approval DAVID STEPANYAN
Floor/Roof Diaphrgm/Shear Wall 12/23/2020 Partial Approval DAVID STEPANYAN
Footing/Foundation/Slab 12/23/2020 Corrections Issued DAVID STEPANYAN
HVAC-Rough 12/23/2020 Corrections Issued DAVID STEPANYAN
Deputy Drilled-In Anchors 12/31/2020 No Access for Inspection DAVID STEPANYAN
Deputy Drilled-In Anchors 1/6/2021 Approved DAVID STEPANYAN
ELECTRICAL-Rough 1/7/2021 Not Ready for Inspection DAVID STEPANYAN
Footing/Foundation/Slab 1/7/2021 Approved DAVID STEPANYAN
Deputy Drilled-In Anchors 2/10/2021 Partial Approval CHRISTOPHER DELLEFIELD
Deputy Wood Construction 2/24/2021 Conditional Approval DAVID STEPANYAN
HVAC-Rough 2/25/2021 Corrections Issued DAVID STEPANYAN
Interior/Exterior Lathing 2/25/2021 Not Ready for Inspection DAVID STEPANYAN
PLUMBING-Rough 2/25/2021 Partial Approval DAVID STEPANYAN
BUILDING-Rough-Frame 3/10/2021 Not Ready for Inspection DAVID STEPANYAN
ELECTRICAL-Rough 3/10/2021 Corrections Issued DAVID STEPANYAN
Green Building Rough 3/10/2021 Not Ready for Inspection DAVID STEPANYAN
HVAC-Rough 3/10/2021 Partial Approval DAVID STEPANYAN
Interior/Exterior Lathing 3/10/2021 Not Ready for Inspection DAVID STEPANYAN
PLUMBING-Rough 3/10/2021 Corrections Issued DAVID STEPANYAN
Shower Pan 3/10/2021 Approved DAVID STEPANYAN
Special/Order Compliance 3/10/2021 Partial Approval DAVID STEPANYAN
ELECTRICAL-Rough 3/19/2021 Approved DAVID STEPANYAN
PLUMBING-Rough 3/19/2021 Approved DAVID STEPANYAN
BUILDING-Rough-Frame 4/1/2021 Approved DAVID STEPANYAN
Green Building Rough 4/1/2021 Approved DAVID STEPANYAN
HVAC-Rough 4/1/2021 Approved DAVID STEPANYAN
Insulation 4/1/2021 Partial Approval DAVID STEPANYAN
Drywall Nailing 4/14/2021 Partial Approval DAVID STEPANYAN
Insulation 4/14/2021 Approved DAVID STEPANYAN
Interior/Exterior Lathing 5/4/2021 Approved DAVID STEPANYAN
HVAC-Rough 5/14/2021 Approved DAVID STEPANYAN
Drywall Nailing 6/28/2021 Approved DAVID STEPANYAN
ELECTRICAL-Final 6/28/2021 Corrections Issued DAVID STEPANYAN
Final 6/28/2021 Corrections Issued DAVID STEPANYAN
Green Building Final 6/28/2021 Corrections Issued DAVID STEPANYAN
HVAC-Final 6/28/2021 Corrections Issued DAVID STEPANYAN
PLUMBING-Final 6/28/2021 Corrections Issued DAVID STEPANYAN
SGSOV-Seismic Gas S/O Valve 6/28/2021 SGSOV Approved DAVID STEPANYAN
Smoke Detectors 6/28/2021 Approved DAVID STEPANYAN
ELECTRICAL-Final 7/23/2021 Not Ready for Inspection DAVID STEPANYAN
Final 7/23/2021 Not Ready for Inspection DAVID STEPANYAN
Green Building Final 7/23/2021 Approved DAVID STEPANYAN
HVAC-Final 7/23/2021 Corrections Issued DAVID STEPANYAN
PLUMBING-Final 7/23/2021 Approved DAVID STEPANYAN
ELECTRICAL-Final 8/2/2021 Approved DAVID STEPANYAN
Final 8/2/2021 Not Ready for Inspection DAVID STEPANYAN
HVAC-Final 8/2/2021 Approved DAVID STEPANYAN
Service/Power Release 8/2/2021 Approved DAVID STEPANYAN
Final 8/18/2021 Partial Approval DAVID STEPANYAN
Final 8/26/2021 OK to Issue CofO DAVID STEPANYAN