20428-20430 W BALTAR ST 91306
Certificate Information: 20428-20430 W BALTAR ST 91306
- Application / Permit
- 20016-20000-09614
- Plan Check / Job No.
- B20VN05667
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 18'-2" X 20'-3" ATTACHED GARAGE TO ACCESSORY DWELLING UNIT.
- Permit Issued
- Issued on 7/1/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/28/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/21/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/27/2020 | RAPHAEL ROSAS |
| Corrections Issued | 4/28/2020 | RAPHAEL ROSAS |
| Plan Check Approved | 6/17/2020 | ROSENDO MEDINA |
| Issued | 7/1/2020 | APPLICANT |
| CofO in Progress | 5/27/2021 | HENRY KIM |
| CofO Issued | 5/28/2021 | MICHAEL SMITH |
| Permit Finaled | 5/28/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 5/19/2020 | GABRIEL ROBLES |
| Permit | Cleared | 5/19/2020 | GABRIEL ROBLES |
| Roof/Waste drainage to street | Cleared | 5/19/2020 | GABRIEL ROBLES |
| Sewer availability | Cleared | 5/19/2020 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 5/26/2020 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/4/2020 | Approved | HENRY KIM |
| Pre-Inspection | 10/20/2020 | Approved | HENRY KIM |
| PLUMBING-Rough | 11/24/2020 | Corrections Issued | HENRY KIM |
| Pre-Inspection | 11/24/2020 | Corrections Issued | HENRY KIM |
| Footing/Foundation/Slab | 12/1/2020 | Partial Approval | HENRY KIM |
| PLUMBING-Rough | 12/1/2020 | Partial Approval | HENRY KIM |
| Footing/Foundation/Slab | 12/3/2020 | Approved | HENRY KIM |
| ELECTRICAL-Rough | 12/8/2020 | Corrections Issued | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 12/8/2020 | Partial Inspection | HENRY KIM |
| ELECTRICAL-Rough | 12/14/2020 | Approved | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 12/14/2020 | Corrections Issued | HENRY KIM |
| Insulation | 12/14/2020 | Corrections Issued | HENRY KIM |
| Interior/Exterior Lathing | 12/14/2020 | Corrections Issued | HENRY KIM |
| BUILDING-Rough-Frame | 12/29/2020 | Approved | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 12/29/2020 | Approved | HENRY KIM |
| Green Building Rough | 12/29/2020 | Approved | HENRY KIM |
| Insulation | 12/29/2020 | Corrections Issued | HENRY KIM |
| Interior/Exterior Lathing | 12/29/2020 | Approved | HENRY KIM |
| PLUMBING-Rough | 12/29/2020 | Approved | HENRY KIM |
| HVAC-Rough | 1/4/2021 | Corrections Issued | HENRY KIM |
| Insulation | 1/4/2021 | Approved | HENRY KIM |
| Drywall Nailing | 1/7/2021 | Approved | HENRY KIM |
| Interior/Exterior Lathing | 1/7/2021 | Approved | HENRY KIM |
| Green Building Final | 1/13/2021 | Approved | HENRY KIM |
| Shower Pan | 1/13/2021 | Approved | HENRY KIM |
| Sewer | 3/10/2021 | Approved | HENRY KIM |
| ELECTRICAL-Final | 4/23/2021 | Corrections Issued | VINCENT HANLEY |
| Final | 4/23/2021 | Corrections Issued | VINCENT HANLEY |
| Final | 5/20/2021 | Corrections Issued | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 5/20/2021 | SGSOV Approved | DAVID SCANTLIN |
| Smoke Detectors | 5/20/2021 | Approved | DAVID SCANTLIN |
| ELECTRICAL-Final | 5/27/2021 | Approved | HENRY KIM |
| Final | 5/27/2021 | OK to Issue CofO | HENRY KIM |
| HVAC-Final | 5/27/2021 | Approved | HENRY KIM |
| PLUMBING-Final | 5/27/2021 | Approved | HENRY KIM |