3147 N HOLLYRIDGE DR 90068

Certificate Information: 3147 N HOLLYRIDGE DR 90068

Application / Permit
20016-20000-09539
Plan Check / Job No.
B20VN05631
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
FIRE DAMAGE REPAIR AND MAJOR REMODEL (E) TWO STORY SFD [NO ADDITION]. "COMPLY WITH DEPARTMENT ORDER effective date 10/16/2019. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 8/5/2020
Issuing Office
Current Status
Issued on 8/5/2020

Permit Application Status History

Submitted 4/21/2020 APPLICANT
Assigned to Plan Check Engineer 5/7/2020 DAWN MC NULTY
Corrections Issued 5/14/2020 DAWN MC NULTY
Quality Review Completed 5/18/2020 CHON CHIO KUO
Building Plans Picked Up 5/20/2020 APPLICANT
Applicant returned to address corrections 7/17/2020 DAWN MC NULTY
Applicant returned to address corrections 7/20/2020 DAWN MC NULTY
Plan Check Approved 8/5/2020 DAWN MC NULTY
Issued 8/5/2020 APPLICANT
Permit Finaled-Status Void 3/8/2021 JOHN TCHANG
Re-Activate Permit 3/18/2021 JOHN TCHANG

Permit Application Clearance Information

CPC Cleared 6/26/2020 MAXFIELD VERMY
Eng Process Fee Ord 176,300 Cleared 7/16/2020 JEANIE LAM
Sewer availability Cleared 7/16/2020 JEANIE LAM
Specific Plan Cleared 7/16/2020 MAY SIRINOPWONGSAGO
BHO/Hillside ordinance Cleared 7/23/2020 JEANIE LAM

Contact Information

Contractor Owner-Builder       ,
Engineer Shakiban,, George; Lic. No.: C39908 23945 CALABASAS RD STE 101      CALABASAS, CA 91302

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Deputy Steel/Welding 8/11/2020 Conditional Approval BRIAN SULLIVAN
BUILDING-Rough-Frame 11/4/2020 Approved JOHN TCHANG
ELECTRICAL-Rough 11/4/2020 Approved JOHN TCHANG
Gas Test 11/4/2020 Partial Approval JOHN TCHANG
HVAC-Rough 11/4/2020 Approved JOHN TCHANG
Interior/Exterior Lathing 11/4/2020 Approved JOHN TCHANG
PLUMBING-Rough 11/4/2020 Approved JOHN TCHANG
Rough-Elec/Plmb/HVAC 11/4/2020 Not Ready for Inspection JOHN TCHANG
Insulation 11/18/2020 Approved JOHN TCHANG
Shower Pan 11/18/2020 Approved JOHN TCHANG
Drywall Nailing 11/23/2020 Approved JOHN TCHANG
Interior/Exterior Lathing 11/23/2020 Approved JOHN TCHANG
Final 3/2/2021 Conditional Approval JOHN TCHANG
SGSOV-Seismic Gas S/O Valve 3/2/2021 SGSOV Approved JOHN TCHANG
Smoke Detectors 3/2/2021 Approved JOHN TCHANG
Final 3/8/2021 Not Ready for Inspection JOHN TCHANG
Service/Power Release 3/18/2021 Approved JOHN TCHANG