19338 W LONDELIUS ST 91324
Certificate Information: 19338 W LONDELIUS ST 91324
- Application / Permit
- 20016-20000-09510
- Plan Check / Job No.
- B20VN05612
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (12) Laundry Plant wholesale
- Work Description
- TENANT IMPROVEMENT CHANGE OF USE FROM MANUFACTURING TO LAUNDRY PLANT WHOLESALE. INSTALL NEW LAUNDRY EQUIPMENT.& ADD 3- 4' X 8' SKYLIGHT, RESTRIPE FOR ADA PARKING .
- Permit Issued
- Issued on 9/9/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/19/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/23/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/7/2020 | CHON CHIO KUO |
| Corrections Issued | 5/14/2020 | CHON CHIO KUO |
| Quality Review Completed | 5/15/2020 | STEVEN KIM |
| Building Plans Picked Up | 5/19/2020 | APPLICANT |
| Disabled Access Plans Picked Up | 5/19/2020 | APPLICANT |
| Applicant returned to address corrections | 8/12/2020 | CHON CHIO KUO |
| Plan Check Approved | 8/27/2020 | CHON CHIO KUO |
| Issued | 9/9/2020 | APPLICANT |
| CofO in Progress | 1/19/2021 | JEFFREY FULTON |
| CofO Issued | 1/19/2021 | JEFFREY DURAN |
| Permit Finaled | 1/19/2021 | JEFFREY DURAN |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/22/2020 | GABRIEL ROBLES |
| Sewer availability | Cleared | 7/22/2020 | GABRIEL ROBLES |
| DAS Clearance | Cleared | 7/28/2020 | NORLITO MEDRANO |
| Hydrant and Access approval | Cleared | 8/17/2020 | MATTHEW CRAIG |
| Organic liquids and gases | Cleared | 8/27/2020 | SCAQMD APPROVED |
Contact Information
| Architect | Bannick,, Arthur Joseph; Lic. No.: C17986 | BANNICK ARCHITECTS 7141 VALJEAN AVE. STE. 100 VAN NUYS, CA 91406 |
| Contractor | Tiffanys Construction; Lic. No.: 1009752-B | 13034 FILMORE STREET PACOIMA, CA 91311 |
| Engineer | Mayer,, Robert; Lic. No.: S1991 | 5109 BELLAIRE AVENUE N HOLLYWOOD, CA 91607 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/5/2020 | Partial Inspection | JEFFREY FULTON |
| Wood Frame | 10/5/2020 | Partial Inspection | JEFFREY FULTON |
| Final | 10/6/2020 | Not Ready for Inspection | JEFFREY FULTON |
| Reinforced Masonry Frame | 10/6/2020 | Not Ready for Inspection | JEFFREY FULTON |
| SGSOV-Seismic Gas S/O Valve | 10/6/2020 | SGSOV Not Ready | JEFFREY FULTON |
| Smoke Detectors | 10/6/2020 | Not Ready for Inspection | JEFFREY FULTON |
| Excavation/Setback/Form/Re-Bar | 10/15/2020 | Partial Inspection | JEFFREY FULTON |
| Masonry Wall/Backfill | 10/15/2020 | Partial Inspection | JEFFREY FULTON |
| Final | 12/7/2020 | Not Ready for Inspection | JEFFREY FULTON |
| Reinforced Masonry Frame | 12/7/2020 | Approved | JEFFREY FULTON |
| SGSOV-Seismic Gas S/O Valve | 12/7/2020 | SGSOV Not Ready | JEFFREY FULTON |
| Smoke Detectors | 12/7/2020 | Approved | JEFFREY FULTON |
| Final | 12/10/2020 | OK to Issue CofO | JEFFREY FULTON |
| SGSOV-Seismic Gas S/O Valve | 12/10/2020 | SGSOV Approved | JEFFREY FULTON |