6441 N WOODLAKE AVE 91307

Certificate Information: 6441 N WOODLAKE AVE 91307

Application / Permit
20016-20000-09474
Plan Check / Job No.
B20VN05587
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 21'-1.5" X 22'-2.5" DETACHED GARAGE TO ACCESSORY DWELLING UNIT. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 5/20/2020
Issuing Office
Valley
Current Status
CofO Issued on 9/8/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/15/2020 APPLICANT
Assigned to Plan Check Engineer 4/17/2020 RAPHAEL ROSAS
Corrections Issued 4/20/2020 RAPHAEL ROSAS
Plan Check Approved 4/29/2020 SARKIS HARABEDIAN
Issued 5/20/2020 LADBS
CofO in Progress 8/27/2020 TROY SANDERS
CofO Issued 9/8/2020 JOHN JANSON
Permit Finaled 9/8/2020 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 4/23/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 4/23/2020 JOHN TRIANTAFYLLOS
Roof/Waste drainage to street Cleared 4/23/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 4/23/2020 JOHN TRIANTAFYLLOS

Contact Information

Contractor Owner-Builder       ,
Engineer , ; Lic. No.: C91162       ,

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/22/2020 Partial Approval JOHN KIDWELL
Footing/Foundation/Slab 5/28/2020 Approved JOHN KIDWELL
Sewer 5/29/2020 Approved HENRY KIM
Underground Mechanical 5/29/2020 Approved HENRY KIM
BUILDING-Rough-Frame 7/1/2020 Partial Approval TROY SANDERS
ELECTRICAL-Rough 7/1/2020 Approved TROY SANDERS
HVAC-Rough 7/1/2020 Corrections Issued TROY SANDERS
PLUMBING-Rough 7/1/2020 Approved TROY SANDERS
Green Building Rough 7/7/2020 Approved TROY SANDERS
HVAC-Rough 7/7/2020 Approved TROY SANDERS
Insulation 7/7/2020 Approved TROY SANDERS
BUILDING-Rough-Frame 7/9/2020 Approved TROY SANDERS
Green Building Rough 7/9/2020 Approved TROY SANDERS
HVAC-Rough 7/9/2020 Approved TROY SANDERS
Interior/Exterior Lathing 7/9/2020 Approved TROY SANDERS
Wood Frame 7/9/2020 Approved TROY SANDERS
Drywall Nailing 7/13/2020 Approved TROY SANDERS
Interior/Exterior Lathing 7/13/2020 Approved TROY SANDERS
Shower Pan 7/17/2020 Approved TROY SANDERS
SGSOV-Seismic Gas S/O Valve 8/21/2020 SGSOV Not Ready TROY SANDERS
ELECTRICAL-Final 8/25/2020 Approved TROY SANDERS
Final 8/25/2020 Corrections Issued TROY SANDERS
HVAC-Final 8/25/2020 Not Ready for Inspection TROY SANDERS
PLUMBING-Final 8/25/2020 Approved TROY SANDERS
Service/Power Release 8/25/2020 Not Ready for Inspection TROY SANDERS
Final 8/27/2020 OK to Issue CofO TROY SANDERS
Green Building Final 8/27/2020 Approved TROY SANDERS
SGSOV-Seismic Gas S/O Valve 8/27/2020 SGSOV Approved TROY SANDERS
Service/Power Release 8/27/2020 Approved TROY SANDERS
Smoke Detectors 8/27/2020 Approved TROY SANDERS