16617 W COVELLO ST 91406
Certificate Information: 16617 W COVELLO ST 91406
- Application / Permit
- 20016-20000-09379
- Plan Check / Job No.
- B20VN05554
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 19'-2" X 21'-10" DETACHED GARAGE TO (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(E)(1)(A). ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 9/16/2020
- Issuing Office
- Current Status
- CofO Issued on 1/15/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/13/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/13/2020 | SARKIS HARABEDIAN |
| Corrections Issued | 4/22/2020 | JENNIFER LEE |
| Applicant returned to address corrections | 8/26/2020 | JENNIFER LEE |
| Plan Check Approved | 9/15/2020 | JENNIFER LEE |
| Issued | 9/16/2020 | APPLICANT |
| CofO in Progress | 11/3/2021 | RAUL OLAGI |
| CofO Issued | 1/15/2022 | MICHAEL SMITH |
| Permit Finaled | 1/15/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 4/24/2020 | GUILLERMO PETRA |
| Sewer availability | Cleared | 4/24/2020 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 6/24/2020 | ROSE MARIE SMITH |
| Construction near power lines | Cleared | 7/1/2020 | RIDWAN HARDY |
| Construction within easement | Cleared | 7/1/2020 | RIDWAN HARDY |
Contact Information
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 6631 MURIETTA AVE LOS ANGELES, CA 91405 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/3/2021 | Approved | ARTHUR SARGSYAN |
| Underground Mechanical | 2/9/2021 | Approved | ARTHUR SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/1/2021 | Partial Approval | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 7/1/2021 | Approved | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/14/2021 | Approved | JACK KARGODORIAN |
| HVAC-Rough | 7/14/2021 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Rough | 8/6/2021 | Corrections Issued | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/6/2021 | Partial Approval | JACK KARGODORIAN |
| Interior/Exterior Lathing | 8/6/2021 | Not Ready for Inspection | JACK KARGODORIAN |
| Insulation | 8/23/2021 | Not Ready for Inspection | DAVID STEPANYAN |
| BUILDING-Rough-Frame | 8/30/2021 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Rough | 8/30/2021 | Approved | JACK KARGODORIAN |
| Green Building Rough | 8/30/2021 | Approved | JACK KARGODORIAN |
| Insulation | 8/30/2021 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 8/30/2021 | Partial Approval | JACK KARGODORIAN |
| Drywall Nailing | 9/3/2021 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 9/24/2021 | Approved | AMY COLIN |
| Shower Pan | 9/24/2021 | Approved | AMY COLIN |
| ELECTRICAL-Final | 10/14/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 10/14/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 10/14/2021 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 10/14/2021 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 10/14/2021 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 10/14/2021 | SGSOV Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 10/14/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Smoke Detectors | 10/14/2021 | Partial Approval | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 10/18/2021 | Approved | RAUL OLAGI |
| Green Building Final | 10/18/2021 | Approved | RAUL OLAGI |
| PLUMBING-Final | 10/18/2021 | Approved | RAUL OLAGI |
| Smoke Detectors | 10/18/2021 | Approved | RAUL OLAGI |
| Final | 11/3/2021 | OK to Issue CofO | RAUL OLAGI |
| Special/Order Compliance | 12/6/2021 | Approved | MICHAEL TEMPLE |