23044-23046 W LULL ST 91304
Certificate Information: 23044-23046 W LULL ST 91304
- Application / Permit
- 20016-20000-09348
- Plan Check / Job No.
- B20VN05530
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) 20'-4" X 21'-5" ATTACHED GARAGE TO ACCESSORY DWELLING UNIT. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 5/21/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/11/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Plan Check Approved | 5/4/2020 | ROSENDO MEDINA |
| Issued | 5/21/2020 | LADBS |
| CofO in Progress | 5/5/2021 | DAVID STEPANYAN |
| Permit Finaled | 5/11/2021 | JOHN JANSON |
| CofO Issued | 5/11/2021 | JOHN JANSON |
| Permit Finaled | 5/11/2021 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 4/24/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 4/24/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 4/28/2020 | ADRIAN CASTRO |
| Hold | Cleared | 6/5/2020 | JASON SHEETS |
Contact Information
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 6631 MURIETTA AVE LOS ANGELES, CA 91405 |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/9/2020 | Corrections Issued | DAVID STEPANYAN |
| BUILDING-Rough-Frame | 7/7/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| Footing/Foundation/Slab | 7/7/2020 | Partial Approval | DAVID STEPANYAN |
| PLUMBING-Rough | 7/7/2020 | Corrections Issued | DAVID STEPANYAN |
| BUILDING-Rough-Frame | 8/13/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| PLUMBING-Rough | 8/13/2020 | Partial Approval | DAVID STEPANYAN |
| Sewer | 8/13/2020 | Approved | DAVID STEPANYAN |
| ELECTRICAL-Rough | 8/27/2020 | No Access for Inspection | DAVID STEPANYAN |
| ELECTRICAL-Rough | 8/31/2020 | Approved | DAVID STEPANYAN |
| Footing/Foundation/Slab | 8/31/2020 | Approved | DAVID STEPANYAN |
| PLUMBING-Final | 9/30/2020 | Corrections Issued | DAVID STEPANYAN |
| PLUMBING-Rough | 10/7/2020 | Approved | DAVID STEPANYAN |
| BUILDING-Rough-Frame | 10/23/2020 | Corrections Issued | DAVID STEPANYAN |
| Green Building Rough | 10/23/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| HVAC-Rough | 10/23/2020 | Corrections Issued | DAVID STEPANYAN |
| Interior/Exterior Lathing | 11/4/2020 | Corrections Issued | DAVID STEPANYAN |
| BUILDING-Rough-Frame | 12/4/2020 | No Access for Inspection | DAVID STEPANYAN |
| Footing/Foundation/Slab | 12/4/2020 | No Access for Inspection | DAVID STEPANYAN |
| Green Building Rough | 12/4/2020 | No Access for Inspection | DAVID STEPANYAN |
| Insulation | 12/4/2020 | No Access for Inspection | DAVID STEPANYAN |
| Interior/Exterior Lathing | 12/4/2020 | No Access for Inspection | DAVID STEPANYAN |
| Insulation | 12/9/2020 | Partial Approval | DAVID STEPANYAN |
| Drywall Nailing | 12/16/2020 | Not Ready for Inspection | RONALD COWAN |
| Green Building Rough | 12/16/2020 | Approved | RONALD COWAN |
| BUILDING-Rough-Frame | 3/31/2021 | Approved | DAVID STEPANYAN |
| Drywall Nailing | 3/31/2021 | Corrections Issued | DAVID STEPANYAN |
| ELECTRICAL-Final | 3/31/2021 | Approved | DAVID STEPANYAN |
| Final | 3/31/2021 | Corrections Issued | DAVID STEPANYAN |
| Green Building Final | 3/31/2021 | Corrections Issued | DAVID STEPANYAN |
| HVAC-Final | 3/31/2021 | Corrections Issued | DAVID STEPANYAN |
| HVAC-Rough | 3/31/2021 | Approved | DAVID STEPANYAN |
| PLUMBING-Final | 3/31/2021 | Corrections Issued | DAVID STEPANYAN |
| SGSOV-Seismic Gas S/O Valve | 3/31/2021 | SGSOV Approved | DAVID STEPANYAN |
| Smoke Detectors | 3/31/2021 | Corrections Issued | DAVID STEPANYAN |
| Final | 4/7/2021 | Not Ready for Inspection | DAVID STEPANYAN |
| HVAC-Final | 4/7/2021 | Not Ready for Inspection | DAVID STEPANYAN |
| PLUMBING-Final | 4/7/2021 | Not Ready for Inspection | DAVID STEPANYAN |
| Gas Test | 4/15/2021 | Approved | DAVID STEPANYAN |
| HVAC-Final | 4/15/2021 | Not Ready for Inspection | DAVID STEPANYAN |
| Shower Pan | 4/15/2021 | Not Ready for Inspection | DAVID STEPANYAN |
| Drywall Nailing | 4/22/2021 | Approved | DAVID STEPANYAN |
| Interior/Exterior Lathing | 4/22/2021 | Approved | DAVID STEPANYAN |
| Shower Pan | 4/22/2021 | Approved | DAVID STEPANYAN |
| Smoke Detectors | 4/22/2021 | Approved | DAVID STEPANYAN |
| Final | 5/4/2021 | OK to Issue CofO | DAVID STEPANYAN |
| Green Building Final | 5/4/2021 | Approved | DAVID STEPANYAN |