10512 N GENESTA AVE 91344

Certificate Information: 10512 N GENESTA AVE 91344

Application / Permit
20016-20000-09282
Plan Check / Job No.
B20VN05509
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED 20' X 18' 3" 2-CAR GARAGE TO ACCESSORY DWELLING UNIT. ALL WORK DONE PER WFPP.
Permit Issued
Issued on 7/7/2020
Issuing Office
Current Status
CofO Issued on 3/15/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/22/2020 APPLICANT
Assigned to Plan Check Engineer 4/22/2020 HAYATO TSUCHIYA
Corrections Issued 4/28/2020 HAYATO TSUCHIYA
Plan Check Approved 6/19/2020 GURUNATH NESARAJAH
Issued 7/7/2020 APPLICANT
CofO in Progress 3/12/2021 JEFFREY PARD
Permit Finaled 3/15/2021 JOHN JANSON
CofO Issued 3/15/2021 JOHN JANSON
Permit Finaled 3/15/2021 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 4/27/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 4/27/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 4/27/2020 JOHN TRIANTAFYLLOS
Construction near power lines Cleared 6/10/2020 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Valencia,, Byron Steve; Lic. No.: C87372 13719 OXNARD ST 101      VAN NUYS, CA 91401

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 10/27/2020 Not Ready for Inspection JEFFREY PARD
Gas Test 11/10/2020 Not Ready for Inspection JEFFREY PARD
Sewer 11/10/2020 Approved JEFFREY PARD
Footing/Foundation/Slab 11/12/2020 Partial Approval JEFFREY PARD
Footing/Foundation/Slab 11/17/2020 Approved WILLIAM KUEHN
Gas Test 11/23/2020 Not Ready for Inspection JEFFREY PARD
Underground Mechanical 11/23/2020 Not Ready for Inspection JEFFREY PARD
ELECTRICAL-Rough 12/1/2020 Approved JEFFREY PARD
Wood Frame 12/1/2020 Partial Approval JEFFREY PARD
ELECTRICAL-Rough 12/4/2020 Partial Approval JEFFREY PARD
Gas Test 12/4/2020 Partial Approval JEFFREY PARD
PLUMBING-Rough 12/4/2020 Partial Approval JEFFREY PARD
HVAC-Rough 12/10/2020 Approved JEFFREY PARD
Insulation 12/16/2020 Approved JEFFREY PARD
Drywall Nailing 12/22/2020 Approved JEFFREY PARD
BUILDING-Rough-Frame 2/17/2021 Approved JEFFREY PARD
Final 2/17/2021 Not Ready for Inspection JEFFREY PARD
Green Building Final 2/17/2021 Corrections Issued JEFFREY PARD
Green Building Rough 2/17/2021 Approved JEFFREY PARD
SGSOV-Seismic Gas S/O Valve 2/17/2021 SGSOV Approved JEFFREY PARD
Smoke Detectors 2/17/2021 Approved JEFFREY PARD
Final 3/11/2021 OK to Issue CofO JEFFREY PARD
Green Building Final 3/11/2021 Approved JEFFREY PARD