7215 W HILLSIDE AVE 90046
Certificate Information: 7215 W HILLSIDE AVE 90046
- Application / Permit
- 20016-20000-09216
- Plan Check / Job No.
- B20VN05463
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- CONVERT (E) OFFICE & STORAGE ROOM ACCESSORY TO (E) APT BLDG INTO (2) NEW ACCESSORY DWELLING UNITS CREATING A 2-STORY 47-UNIT APT BLDG W/ (2) ACCESSORY DWELLING UNITS
- Permit Issued
- Issued on 7/30/2020
- Issuing Office
- Current Status
- CofO Corrected on 3/24/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/21/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/30/2020 | NILOOFAR MEHRAIN |
| Corrections Issued | 5/7/2020 | NILOOFAR MEHRAIN |
| Quality Review Completed | 5/7/2020 | STEVEN KIM |
| Building Plans Picked Up | 5/12/2020 | APPLICANT |
| Green Plans Picked Up | 5/28/2020 | APPLICANT |
| Plan Check Approved | 7/28/2020 | NILOOFAR MEHRAIN |
| Issued | 7/30/2020 | APPLICANT |
| CofO in Progress | 3/21/2022 | SORIN CIRSTOIU |
| CofO Issued-Status Void | 3/21/2022 | ERNESTO CORRAL |
| Permit Finaled-Status Void | 3/21/2022 | ERNESTO CORRAL |
| Re-Activate Permit | 3/24/2022 | ERNESTO CORRAL |
| CofO Corrected | 3/24/2022 | ERNESTO CORRAL |
| Permit Finaled | 3/24/2022 | ERNESTO CORRAL |
Permit Application Clearance Information
| "Q" conditions | Cleared | 5/18/2020 | PABLO ESTRADA |
| Miscellaneous | Cleared | 5/18/2020 | PABLO ESTRADA |
| Address approval | Cleared | 5/22/2020 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 5/26/2020 | WALLIE JONG |
| Miscellaneous | Cleared | 6/2/2020 | NILOOFAR MEHRAIN |
| Hydrant and Access approval | Cleared | 6/4/2020 | GEORGE SUCHAND |
| Sewer availability | Cleared | 6/4/2020 | WALLIE JONG |
| Green Code | Cleared | 7/2/2020 | MICHAEL AYERS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Almalla,, Dean; Lic. No.: C58024 | 15053 VENTURA BLVD STE 205 SHERMAN OAKS, CA 91403 |
Inspector Information
| TIMOTHY POWELL, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Green Building Rough | 12/16/2020 | Not Ready for Inspection | EDWIN GREGORYONA |
| Wood Frame | 12/16/2020 | Corrections Issued | EDWIN GREGORYONA |
| Pre-Inspection | 2/5/2021 | Approved | RUSSELL BONVOULOIR |
| Green Building Rough | 2/25/2021 | Not Ready for Inspection | RUSSELL BONVOULOIR |
| Wood Frame | 2/25/2021 | Corrections Issued | RUSSELL BONVOULOIR |
| Green Building Rough | 3/10/2021 | Not Ready for Inspection | RUSSELL BONVOULOIR |
| Wood Frame | 3/10/2021 | Corrections Issued | RUSSELL BONVOULOIR |
| Final | 7/13/2021 | Not Ready for Inspection | RUSSELL BONVOULOIR |
| Green Building Final | 7/13/2021 | Partial Inspection | RUSSELL BONVOULOIR |
| Green Building Rough | 7/13/2021 | Partial Approval | RUSSELL BONVOULOIR |
| SGSOV-Seismic Gas S/O Valve | 7/13/2021 | SGSOV Not Ready | RUSSELL BONVOULOIR |
| Smoke Detectors | 7/13/2021 | Not Ready for Inspection | RUSSELL BONVOULOIR |
| Wood Frame | 7/13/2021 | Partial Inspection | RUSSELL BONVOULOIR |
| Final | 11/16/2021 | Corrections Issued | JONATHAN QUACH |
| Green Building Final | 11/16/2021 | Partial Inspection | JONATHAN QUACH |
| Green Building Rough | 11/16/2021 | Approved | JONATHAN QUACH |
| SGSOV-Seismic Gas S/O Valve | 11/16/2021 | SGSOV Approved | JONATHAN QUACH |
| Smoke Detectors | 11/16/2021 | Approved | JONATHAN QUACH |
| Wood Frame | 11/16/2021 | Not Ready for Inspection | JONATHAN QUACH |
| Final | 11/24/2021 | Not Ready for Inspection | JONATHAN QUACH |
| Green Building Final | 11/24/2021 | Not Ready for Inspection | JONATHAN QUACH |
| Wood Frame | 11/24/2021 | Approved | JONATHAN QUACH |
| Final | 12/8/2021 | Conditional Approval | JONATHAN QUACH |
| Green Building Final | 12/8/2021 | Approved | JONATHAN QUACH |