21829 W DUMETZ ROAD 91364
Certificate Information: 21829 W DUMETZ ROAD 91364
- Application / Permit
- 20016-20000-09214
- Plan Check / Job No.
- B20VN05462
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT THE (E) DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A).
- Permit Issued
- Issued on 3/31/2021
- Issuing Office
- Current Status
- CofO Issued on 2/14/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/20/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/20/2020 | ARTIN ZARUKIAN |
| Corrections Issued | 4/20/2020 | ARTIN ZARUKIAN |
| Plan Check Approved | 3/31/2021 | ARTIN ZARUKIAN |
| Issued | 3/31/2021 | APPLICANT |
| Building Plans Picked Up | 4/1/2021 | APPLICANT |
| CofO in Progress | 2/2/2023 | PETER FOLLING |
| CofO Issued | 2/14/2023 | JOHN JANSON |
| Permit Finaled | 2/14/2023 | JOHN JANSON |
Permit Application Clearance Information
| Construction near power lines | Cleared | 4/21/2020 | WALTER RAMIREZ |
| Address approval | Cleared | 4/24/2020 | GUILLERMO PETRA |
| Sewer availability | Cleared | 4/24/2020 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 5/5/2020 | GUILLERMO PETRA |
| Specific Plan | Cleared | 7/8/2020 | DOMINICK ORTIZ |
| ZI | Cleared | 7/8/2020 | DOMINICK ORTIZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN HAYES, (818) 774-4302 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/8/2021 | Partial Approval | VINCENT HANLEY |
| Sewer | 4/8/2021 | Partial Approval | VINCENT HANLEY |
| Underground Mechanical | 4/8/2021 | Partial Approval | VINCENT HANLEY |
| Sewer | 6/24/2021 | Approved | PETER FOLLING |
| ELECTRICAL-Rough | 6/13/2022 | Not Ready for Inspection | PETER FOLLING |
| PLUMBING-Rough | 6/13/2022 | Not Ready for Inspection | PETER FOLLING |
| BUILDING-Rough-Frame | 7/12/2022 | Not Ready for Inspection | PETER FOLLING |
| Green Building Rough | 7/12/2022 | Not Ready for Inspection | PETER FOLLING |
| PLUMBING-Rough | 7/12/2022 | Not Ready for Inspection | PETER FOLLING |
| ELECTRICAL-Rough | 7/19/2022 | Not Ready for Inspection | PETER FOLLING |
| HVAC-Rough | 7/19/2022 | Not Ready for Inspection | PETER FOLLING |
| Shower Pan | 7/19/2022 | Approved | PETER FOLLING |
| ELECTRICAL-Rough | 8/8/2022 | Not Ready for Inspection | PETER FOLLING |
| HVAC-Rough | 8/8/2022 | Approved | PETER FOLLING |
| PLUMBING-Rough | 8/8/2022 | Approved | PETER FOLLING |
| ELECTRICAL-Rough | 8/15/2022 | Not Ready for Inspection | PETER FOLLING |
| Interior/Exterior Lathing | 8/15/2022 | Partial Approval | PETER FOLLING |
| ELECTRICAL-Rough | 9/1/2022 | Approved | PETER FOLLING |
| BUILDING-Rough-Frame | 9/9/2022 | Approved | PETER FOLLING |
| Green Building Rough | 9/9/2022 | Approved | PETER FOLLING |
| Insulation | 9/14/2022 | Approved | PETER FOLLING |
| Deputy Drilled-In Anchors | 9/21/2022 | Conditional Approval | MORRIS JACKSON |
| Drywall Nailing | 9/23/2022 | Approved | MORRIS JACKSON |
| Final | 1/23/2023 | Corrections Issued | PETER FOLLING |
| Green Building Final | 1/23/2023 | Approved | PETER FOLLING |
| SGSOV-Seismic Gas S/O Valve | 1/23/2023 | SGSOV Not Ready | PETER FOLLING |
| Smoke Detectors | 1/23/2023 | Approved | PETER FOLLING |
| Final | 2/1/2023 | OK to Issue CofO | PETER FOLLING |
| SGSOV-Seismic Gas S/O Valve | 2/1/2023 | SGSOV Approved | PETER FOLLING |
| Service/Power Release | 2/1/2023 | Approved | PETER FOLLING |