19136 W SCHOOLCRAFT ST 91335

Certificate Information: 19136 W SCHOOLCRAFT ST 91335

Application / Permit
20016-20000-09131
Plan Check / Job No.
B20VN05417
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 20'-2" X 20'-2" DETACHED GARAGE INTO NEW ACCESSORY DWELLING UNIT.
Permit Issued
Issued on 8/13/2020
Issuing Office
Valley
Current Status
CofO Issued on 7/14/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/29/2020 APPLICANT
Assigned to Plan Check Engineer 4/29/2020 SERGIO MUNIZ
Corrections Issued 4/29/2020 SERGIO MUNIZ
Building Plans Picked Up 5/1/2020 APPLICANT
Plan Check Approved 7/29/2020 ROSENDO MEDINA
Issued 8/13/2020 APPLICANT
CofO in Progress 7/1/2021 VINCENT HANLEY
Permit Finaled 7/14/2021 JOHN JANSON
CofO Issued 7/14/2021 JOHN JANSON
Permit Finaled 7/14/2021 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 5/4/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 5/4/2020 ADRIAN CASTRO
Sewer availability Cleared 5/4/2020 ADRIAN CASTRO
Construction within easement Cleared 7/1/2020 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/4/2020 Corrections Issued VINCENT HANLEY
Footing/Foundation/Slab 9/4/2020 Corrections Issued VINCENT HANLEY
Deputy Drilled-In Anchors 9/10/2020 Approved VINCENT HANLEY
PLUMBING-Rough 9/14/2020 Corrections Issued VINCENT HANLEY
PLUMBING-Rough 10/27/2020 Partial Approval VINCENT HANLEY
Sewer 10/27/2020 Approved VINCENT HANLEY
Gas Test 11/12/2020 Approved VINCENT HANLEY
Excavation/Setback/Form/Re-Bar 12/4/2020 Approved HENRY KIM
Footing/Foundation/Slab 12/4/2020 Approved HENRY KIM
ELECTRICAL-Rough 1/21/2021 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 1/21/2021 Approved VINCENT HANLEY
Green Building Rough 1/21/2021 Not Ready for Inspection VINCENT HANLEY
PLUMBING-Rough 1/21/2021 Approved VINCENT HANLEY
BUILDING-Rough-Frame 2/11/2021 Approved VINCENT HANLEY
Drywall Nailing 2/11/2021 Approved VINCENT HANLEY
Green Building Rough 2/11/2021 Approved VINCENT HANLEY
Insulation 2/11/2021 Approved VINCENT HANLEY
Shower Pan 2/11/2021 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 2/17/2021 Partial Approval VINCENT HANLEY
Interior/Exterior Lathing 2/17/2021 Approved VINCENT HANLEY
ELECTRICAL-Final 5/28/2021 Corrections Issued VINCENT HANLEY
Final 5/28/2021 Corrections Issued VINCENT HANLEY
Gas Test 5/28/2021 Approved VINCENT HANLEY
Green Building Final 5/28/2021 Approved VINCENT HANLEY
HVAC-Final 5/28/2021 Corrections Issued VINCENT HANLEY
PLUMBING-Final 5/28/2021 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 5/28/2021 SGSOV Approved VINCENT HANLEY
Smoke Detectors 5/28/2021 Approved VINCENT HANLEY
ELECTRICAL-Final 7/1/2021 Approved VINCENT HANLEY
Final 7/1/2021 OK to Issue CofO VINCENT HANLEY
Gas Test 7/1/2021 Approved VINCENT HANLEY
HVAC-Final 7/1/2021 Approved VINCENT HANLEY
PLUMBING-Final 7/1/2021 Approved VINCENT HANLEY