4070 N RANONS AVE 90065
Certificate Information: 4070 N RANONS AVE 90065
- Application / Permit
- 20016-20000-09130
- Plan Check / Job No.
- B20VN05416
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT THE (E) 18' X 21'-9" DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(E)(1)(A). ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 8/19/2020
- Issuing Office
- Current Status
- CofO Issued on 11/5/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/15/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/16/2020 | SERGIO MUNIZ |
| Corrections Issued | 4/29/2020 | SERGIO MUNIZ |
| Plan Check Approved | 8/18/2020 | JENNIFER LEE |
| Issued | 8/19/2020 | APPLICANT |
| CofO in Progress | 10/13/2021 | HAMIK HARTOUNIAN |
| Permit Finaled | 11/5/2021 | DEROLD HAUFF |
| CofO Issued | 11/5/2021 | DEROLD HAUFF |
| Permit Finaled | 11/5/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 6/15/2020 | CECILIO NAVARRO |
| Sewer availability | Cleared | 6/15/2020 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 6/19/2020 | CECILIO NAVARRO |
| Grading Pre-Inspection | Cleared | 7/29/2020 | PATRICK MISCHLICH |
| Supp. Use District POD/CDO/TDO | Cleared | 8/4/2020 | ADRINEH MELKONIAN |
Contact Information
| Contractor | Secure It Construction Co; Lic. No.: 750431-B | 1180 CURRIER AVE SIMI VALLEY, CA 93065 |
| Engineer | Garcia,, Francisco Diaz; Lic. No.: C88029 | 7333 RANCHITO AVE VAN NUYS, CA 91405 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Special/Order Compliance | 8/28/2020 | Approved | CHRISTOPHER DELLEFIELD |
| Underground Mechanical | 8/28/2020 | Corrections Issued | HAMIK HARTOUNIAN |
| Pre-Inspection | 9/17/2020 | Approved | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 9/29/2020 | Approved | HAMIK HARTOUNIAN |
| Sewer | 10/15/2020 | Approved | HAMIK HARTOUNIAN |
| Shower Pan | 11/9/2020 | Approved | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 12/16/2020 | Approved | HAMIK HARTOUNIAN |
| HVAC-Rough | 12/16/2020 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 12/16/2020 | Approved | HAMIK HARTOUNIAN |
| Rough-Elec/Plmb/HVAC | 12/16/2020 | Partial Inspection | HAMIK HARTOUNIAN |
| Underground Mechanical | 12/16/2020 | Conditional Approval | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 1/12/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Rough | 1/12/2021 | Approved | HAMIK HARTOUNIAN |
| Insulation | 1/12/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 1/12/2021 | Partial Approval | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 3/8/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 4/14/2021 | Approved | HAMIK HARTOUNIAN |
| Insulation | 4/14/2021 | Approved | HAMIK HARTOUNIAN |
| Drywall Nailing | 4/24/2021 | Approved | KATHRYN BUTTERWORTH |
| Interior/Exterior Lathing | 5/19/2021 | No Access for Inspection | THOMAS LOGRASSO |
| ELECTRICAL-Final | 8/6/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Final | 8/6/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Green Building Final | 8/6/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| HVAC-Final | 8/6/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| PLUMBING-Final | 8/6/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 8/6/2021 | SGSOV Not Ready | HAMIK HARTOUNIAN |
| Smoke Detectors | 8/6/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| ELECTRICAL-Final | 9/16/2021 | Approved | HAMIK HARTOUNIAN |
| Final | 9/16/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| Gas Test | 9/16/2021 | Approved | HAMIK HARTOUNIAN |
| Green Building Final | 9/16/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| HVAC-Final | 9/16/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| PLUMBING-Final | 9/16/2021 | Approved | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 9/16/2021 | SGSOV Not Ready | HAMIK HARTOUNIAN |
| Smoke Detectors | 9/16/2021 | Approved | HAMIK HARTOUNIAN |
| ELECTRICAL-Final | 10/12/2021 | Approved | HAMIK HARTOUNIAN |
| Final | 10/12/2021 | OK to Issue CofO | HAMIK HARTOUNIAN |
| Green Building Final | 10/12/2021 | Approved | HAMIK HARTOUNIAN |
| HVAC-Final | 10/12/2021 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Final | 10/12/2021 | Approved | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 10/12/2021 | SGSOV Approved | HAMIK HARTOUNIAN |