2362 N ALLVIEW TER EAST 90068
Certificate Information: 2362 N ALLVIEW TER EAST 90068
- Application / Permit
- 20016-20000-09117
- Plan Check / Job No.
- B20VN05407
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ALTER REPAIR OF EXISITING (32'-0"x 67'-0") IRR SHAPE CONCRETE DECK TO (E) SINGLE FAMILY DWELLING. "COMPLY WITH DEPARTMENT ORDER effective date 03/20/2020. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE". WORK PER ENGINEER.
- Permit Issued
- Issued on 6/3/2021
- Issuing Office
- Current Status
- Permit Finaled on 11/3/2022
Permit Application Status History
| Submitted | 4/8/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/23/2020 | TROY DEGUZMAN |
| Corrections Issued | 4/29/2020 | TROY DEGUZMAN |
| Quality Review Completed | 4/30/2020 | CHON CHIO KUO |
| Building Plans Picked Up | 4/30/2020 | APPLICANT |
| Applicant returned to address corrections | 6/10/2020 | TROY DEGUZMAN |
| Applicant returned to address corrections | 6/29/2020 | TROY DEGUZMAN |
| Plan Check Approved | 6/29/2020 | TROY DEGUZMAN |
| Issued | 6/3/2021 | APPLICANT |
| Permit Finaled | 11/2/2022 | JOHN TCHANG |
Permit Application Clearance Information
| Low Impact Development | Cleared | 5/26/2020 | SARAH YOUSSEF |
| ZI | Cleared | 5/26/2020 | LAUREN PADICK |
| GPI Written Notices | Cleared | 6/10/2020 | TROY DEGUZMAN |
| Grading Pre-Inspection | Cleared | 6/10/2020 | TROY DEGUZMAN |
Contact Information
| Contractor | Fanello Construction; Lic. No.: 308170-B | 216 15TH PLACE MANHATTAN BEACH, CA 90266 |
| Engineer | Franceschi,, Paul; Lic. No.: S4309 | 2388 KENILWORTH AVE LOS ANGELES, CA 90039 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/14/2021 | Approved | JOHN TCHANG |
| Excavation/Setback/Form/Re-Bar | 6/17/2021 | Conditional Approval | JOHN TCHANG |
| Footing/Foundation/Slab | 7/29/2021 | Partial Approval | JOHN TCHANG |
| Footing/Foundation/Slab | 8/16/2021 | Partial Approval | JOHN TCHANG |
| Footing/Foundation/Slab | 11/30/2021 | Approved | JOHN TCHANG |
| BUILDING-Rough-Frame | 11/2/2022 | Approved | JOHN TCHANG |
| Final | 11/2/2022 | Permit Finaled | JOHN TCHANG |
| SGSOV-Seismic Gas S/O Valve | 11/2/2022 | SGSOV Approved | JOHN TCHANG |
| Smoke Detectors | 11/2/2022 | Approved | JOHN TCHANG |