7529 N OAKDALE AVE 91306

Certificate Information: 7529 N OAKDALE AVE 91306

Application / Permit
20016-20000-09023
Plan Check / Job No.
B20VN05360
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT THE (E) 22'-0"x 24'-0" TWO-CAR DETACHED GARAGE TO (N) ACCESSORY DWELLING UNIT. WORK PER DONE WFPP.
Permit Issued
Issued on 6/3/2020
Issuing Office
Current Status
CofO Issued on 11/30/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Plan Check Approved 5/2/2020 HAYATO TSUCHIYA
No Progress 5/2/2020 HAYATO TSUCHIYA
Plan Check Approved 5/8/2020 ROSENDO MEDINA
Issued 6/3/2020 APPLICANT
CofO in Progress 11/25/2020 HENRY KIM
CofO Issued 11/30/2020 JOHN JANSON
Permit Finaled 11/30/2020 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 4/23/2020 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 4/23/2020 GUILLERMO PETRA
Sewer availability Cleared 4/23/2020 GUILLERMO PETRA
Construction near power lines Cleared 5/7/2020 WALTER RAMIREZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/11/2020 Not Ready for Inspection HENRY KIM
Deputy Drilled-In Anchors 6/12/2020 Conditional Approval HENRY KIM
Footing/Foundation/Slab 6/18/2020 Approved HENRY KIM
ELECTRICAL-Rough 7/14/2020 Not Ready for Inspection HENRY KIM
PLUMBING-Rough 7/14/2020 Partial Approval HENRY KIM
BUILDING-Rough-Frame 7/16/2020 Not Ready for Inspection HENRY KIM
Sewer 7/16/2020 Approved HENRY KIM
Underground Mechanical 7/16/2020 Corrections Issued HENRY KIM
ELECTRICAL-Rough 7/17/2020 Corrections Issued HENRY KIM
Underground Mechanical 7/17/2020 Partial Approval HENRY KIM
ELECTRICAL-Rough 8/21/2020 Corrections Issued HENRY KIM
HVAC-Rough 8/21/2020 Not Ready for Inspection HENRY KIM
PLUMBING-Rough 8/21/2020 Corrections Issued HENRY KIM
Underground Mechanical 8/21/2020 Corrections Issued HENRY KIM
BUILDING-Rough-Frame 8/28/2020 Corrections Issued HENRY KIM
ELECTRICAL-Rough 8/28/2020 Approved HENRY KIM
Underground Mechanical 8/28/2020 Approved HENRY KIM
BUILDING-Rough-Frame 9/1/2020 Not Ready for Inspection HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 9/1/2020 Partial Approval HENRY KIM
PLUMBING-Rough 9/1/2020 Approved HENRY KIM
Insulation 9/8/2020 Approved HENRY KIM
Interior/Exterior Lathing 9/8/2020 Partial Approval HENRY KIM
BUILDING-Rough-Frame 9/10/2020 Approved HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 9/10/2020 Approved HENRY KIM
Green Building Rough 9/10/2020 Approved HENRY KIM
HVAC-Rough 9/10/2020 Approved HENRY KIM
Drywall Nailing 9/21/2020 Approved HENRY KIM
Green Building Final 9/21/2020 Partial Approval HENRY KIM
Shower Pan 9/21/2020 Approved HENRY KIM
ELECTRICAL-Final 11/9/2020 Corrections Issued HENRY KIM
HVAC-Final 11/9/2020 Corrections Issued HENRY KIM
Interior/Exterior Lathing 11/9/2020 Approved HENRY KIM
Final 11/13/2020 Not Ready for Inspection HENRY KIM
Green Building Final 11/13/2020 Not Ready for Inspection HENRY KIM
SGSOV-Seismic Gas S/O Valve 11/13/2020 SGSOV Not Ready HENRY KIM
Smoke Detectors 11/13/2020 Not Ready for Inspection HENRY KIM
ELECTRICAL-Final 11/20/2020 Corrections Issued HENRY KIM
Final 11/20/2020 Corrections Issued HENRY KIM
Green Building Final 11/20/2020 Approved HENRY KIM
HVAC-Final 11/20/2020 Corrections Issued HENRY KIM
PLUMBING-Final 11/20/2020 Corrections Issued HENRY KIM
SGSOV-Seismic Gas S/O Valve 11/20/2020 SGSOV Approved HENRY KIM
Smoke Detectors 11/20/2020 Not Ready for Inspection HENRY KIM
ELECTRICAL-Final 11/25/2020 Approved HENRY KIM
Final 11/25/2020 OK to Issue CofO HENRY KIM
HVAC-Final 11/25/2020 Approved HENRY KIM
PLUMBING-Final 11/25/2020 Approved HENRY KIM
Smoke Detectors 11/25/2020 Approved HENRY KIM