429 N GENESEE AVE 90036
Certificate Information: 429 N GENESEE AVE 90036
- Application / Permit
- 20016-20000-08962
- Plan Check / Job No.
- B20VN05334
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- INTERIOR REMODEL TO UNITS 1,2 AND 3: Create a new bathroom, enlarge kitchen, remodel (e) bathroom, closets and bedroom in each unit.
- Permit Issued
- Issued on 11/9/2020
- Issuing Office
- Current Status
- Permit Finaled on 4/5/2024
Permit Application Status History
| Submitted | 4/7/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/16/2020 | SAM CHANG |
| Corrections Issued | 4/23/2020 | SAM CHANG |
| Quality Review Completed | 5/6/2020 | ARMEN JIVALAGIAN |
| Building Plans Picked Up | 5/12/2020 | APPLICANT |
| Applicant returned to address corrections | 7/8/2020 | SAM CHANG |
| Plan Check Approved | 11/6/2020 | SAM CHANG |
| Issued | 11/9/2020 | APPLICANT |
| Permit Finaled | 4/4/2024 | MARTIN TAVITIAN |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 7/1/2020 | PHILLIP MUNGUIA |
| CPC | Cleared | 8/4/2020 | ANNA VIDAL |
| Historic monument | Cleared | 10/29/2020 | MICAELA TORRES-GIL |
Contact Information
| Architect | Schneider,, Brent T; Lic. No.: C21821 | 2282 TOWNSGATE ROAD SUITE 3 WESTLAKE VILLAGE, CA 91361 |
| Contractor | B H C; Lic. No.: 960037-B | 4607 LAKEVIEW CANYON RD #595 WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| IAN BLINN, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRISTOPHER BLACKWOOD, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Special/Order Compliance | 2/1/2021 | Corrections Issued | TIMOTHY BUXTON |
| Special/Order Compliance | 2/9/2021 | Approved | TIMOTHY BUXTON |
| Footing/Foundation/Slab | 2/22/2021 | Approved | TIMOTHY BUXTON |
| Deputy Reinf. Concrete | 2/24/2021 | Conditional Approval | TIMOTHY BUXTON |
| Special/Order Compliance | 4/5/2021 | Partial Approval | TIMOTHY BUXTON |
| Special/Order Compliance | 4/21/2021 | Partial Inspection | TIMOTHY BUXTON |
| Wood Frame | 4/14/2023 | Not Ready for Inspection | ALFREDO LOPEZ |
| Wood Frame | 8/1/2023 | Partial Approval | MARTIN TAVITIAN |
| Insulation | 9/7/2023 | Approved | ALFREDO LOPEZ |
| Interior/Exterior Lathing | 9/7/2023 | Approved | ALFREDO LOPEZ |
| Deputy Wood Construction | 9/11/2023 | No Access for Inspection | ALFREDO LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 9/19/2023 | Partial Approval | JEROME BLACKWOOD |
| Drywall Nailing | 10/19/2023 | Approved | RICARDO ROBLES |
| Interior/Exterior Lathing | 10/19/2023 | Approved | ALFREDO LOPEZ |
| Final | 4/4/2024 | Permit Finaled | MARTIN TAVITIAN |
| SGSOV-Seismic Gas S/O Valve | 4/4/2024 | SGSOV Approved | MARTIN TAVITIAN |
| Smoke Detectors | 4/4/2024 | Approved | MARTIN TAVITIAN |