9506-9506 1/2 S GRAPE ST 90002
Certificate Information: 9506-9506 1/2 S GRAPE ST 90002
- Application / Permit
- 20016-20000-08889
- Plan Check / Job No.
- B20VN05286
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT THE (E) GARAGE AND A PORTION OF THE (E) SFD INTO A (N) ACCESSORY DWELLING UNIT. ALL WORK PER WFPP.
- Permit Issued
- Issued on 8/14/2020
- Issuing Office
- Current Status
- CofO Issued on 6/26/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/23/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/2/2020 | GURUNATH NESARAJAH |
| Corrections Issued | 7/2/2020 | ARTIN ZARUKIAN |
| Issued | 8/14/2020 | APPLICANT |
| CofO in Progress | 6/21/2025 | DAVID FEILER |
| Permit Finaled | 6/26/2025 | RICHARD STEINBACH |
| CofO Issued | 6/26/2025 | RICHARD STEINBACH |
| Permit Finaled | 6/26/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 5/4/2020 | WALLIE JONG |
| Sewer availability | Cleared | 5/4/2020 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 5/21/2020 | WALLIE JONG |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/15/2021 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| Footing/Foundation/Slab | 4/22/2021 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 5/6/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| ELECTRICAL-Rough | 5/6/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| Green Building Rough | 5/6/2021 | Corrections Issued | EUGENE CASSIDY |
| ELECTRICAL-Rough | 5/11/2021 | Corrections Issued | EUGENE CASSIDY |
| ELECTRICAL-Rough | 5/27/2021 | No Access for Inspection | DAVID FEILER |
| PLUMBING-Rough | 5/27/2021 | No Access for Inspection | DAVID FEILER |
| ELECTRICAL-Rough | 5/28/2021 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 5/28/2021 | Partial Approval | EUGENE CASSIDY |
| PLUMBING-Rough | 6/4/2021 | Approved | EUGENE CASSIDY |
| Sewer | 6/4/2021 | Approved | EUGENE CASSIDY |
| Insulation | 6/9/2021 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 6/15/2021 | Corrections Issued | EUGENE CASSIDY |
| Green Building Rough | 6/15/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| Drywall Nailing | 6/18/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| Green Building Rough | 6/18/2021 | Corrections Issued | EUGENE CASSIDY |
| Drywall Nailing | 6/29/2021 | Not Ready for Inspection | DAVID FEILER |
| Green Building Rough | 6/29/2021 | Corrections Issued | DAVID FEILER |
| Drywall Nailing | 7/7/2021 | Corrections Issued | EUGENE CASSIDY |
| Green Building Rough | 7/7/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| Drywall Nailing | 7/16/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 7/16/2021 | Approved | EUGENE CASSIDY |
| Green Building Rough | 7/16/2021 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 7/26/2021 | Approved | EUGENE CASSIDY |
| Green Building Final | 10/15/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| Green Building Final | 10/21/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| Interior/Exterior Lathing | 10/21/2021 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 2/25/2022 | No Access for Inspection | JOHN KLARIN |
| Final | 2/25/2022 | No Access for Inspection | JOHN KLARIN |
| Green Building Final | 2/25/2022 | No Access for Inspection | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 2/25/2022 | SGSOV Not Ready | JOHN KLARIN |
| Smoke Detectors | 2/25/2022 | No Access for Inspection | JOHN KLARIN |
| BUILDING-Rough-Frame | 3/15/2022 | Approved | JOHN KLARIN |
| Final | 3/15/2022 | Corrections Issued | JOHN KLARIN |
| Green Building Final | 3/15/2022 | Corrections Issued | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 3/15/2022 | SGSOV Approved | JOHN KLARIN |
| Smoke Detectors | 3/15/2022 | Approved | JOHN KLARIN |
| Final | 3/21/2022 | Not Ready for Inspection | JOHN KLARIN |
| Green Building Final | 3/21/2022 | Not Ready for Inspection | JOHN KLARIN |
| ELECTRICAL-Final | 3/25/2022 | Approved | JOHN KLARIN |
| Final | 3/25/2022 | Not Ready for Inspection | JOHN KLARIN |
| Green Building Final | 3/25/2022 | Approved | JOHN KLARIN |
| HVAC-Final | 3/25/2022 | Approved | JOHN KLARIN |
| PLUMBING-Final | 3/25/2022 | Approved | JOHN KLARIN |
| Final | 6/21/2025 | OK to Issue CofO | DAVID FEILER |