4027 1/2 S HALLDALE AVE 90062

Certificate Information: 4027 1/2 S HALLDALE AVE 90062

Application / Permit
20016-20000-08865
Plan Check / Job No.
B20VN05276
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 27' 5" X 42' IRR.-SHAPE DETACHED 2-CAR GARAGE/STORAGE/WORKSHOP TO ACCESSORY DWELLING UNIT. ALL WORK DONE PER WFPP.
Permit Issued
Issued on 11/18/2020
Issuing Office
Current Status
CofO Issued on 6/17/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Plan Check Approved 6/23/2020 GURUNATH NESARAJAH
Issued 11/18/2020 APPLICANT
CofO in Progress 4/9/2021 WILL MCCONNAUGHY
Permit Finaled 6/17/2021 DEROLD HAUFF
CofO Issued 6/17/2021 DEROLD HAUFF
Permit Finaled 6/17/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 4/23/2020 RENZ SORIANO
Sewer availability Cleared 4/23/2020 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 4/27/2020 RENZ SORIANO
Construction near power lines Cleared 6/7/2020 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/18/2020 Not Ready for Inspection ROBERT MCDOWELL
Footing/Foundation/Slab 12/18/2020 Not Ready for Inspection ROBERT MCDOWELL
Footing/Foundation/Slab 12/23/2020 Not Ready for Inspection ROBERT MCDOWELL
Underground Mechanical 12/23/2020 Approved ROBERT MCDOWELL
Excavation/Setback/Form/Re-Bar 12/28/2020 Not Ready for Inspection ROBERT MCDOWELL
Excavation/Setback/Form/Re-Bar 12/30/2020 Approved ROBERT MCDOWELL
Floor/Roof Diaphrgm/Shear Wall 1/19/2021 Approved ROBERT MCDOWELL
Green Building Rough 1/19/2021 Not Ready for Inspection ROBERT MCDOWELL
Rough-Elec/Plmb/HVAC 1/25/2021 Corrections Issued ROBERT MCDOWELL
BUILDING-Rough-Frame 2/1/2021 Approved ROBERT MCDOWELL
ELECTRICAL-Rough 2/1/2021 Approved ROBERT MCDOWELL
Green Building Rough 2/1/2021 Approved ROBERT MCDOWELL
PLUMBING-Rough 2/1/2021 Approved ROBERT MCDOWELL
Insulation 2/2/2021 Corrections Issued DAVID FEILER
Interior/Exterior Lathing 2/2/2021 Not Ready for Inspection DAVID FEILER
HVAC-Rough 2/9/2021 Approved ROBERT MCDOWELL
Insulation 2/9/2021 Approved ROBERT MCDOWELL
Interior/Exterior Lathing 2/9/2021 Approved ROBERT MCDOWELL
Drywall Nailing 2/22/2021 Approved ROBERT MCDOWELL
ELECTRICAL-Final 3/8/2021 Corrections Issued FREDDIE RIVERA
Service/Power Release 3/8/2021 Not Ready for Inspection FREDDIE RIVERA
Final 3/12/2021 Corrections Issued ROBERT MCDOWELL
Green Building Final 3/12/2021 Not Ready for Inspection ROBERT MCDOWELL
SGSOV-Seismic Gas S/O Valve 3/12/2021 SGSOV Not Ready ROBERT MCDOWELL
Smoke Detectors 3/12/2021 Not Ready for Inspection ROBERT MCDOWELL
Final 3/25/2021 Corrections Issued ROBERT MCDOWELL
Green Building Final 3/25/2021 Approved ROBERT MCDOWELL
SGSOV-Seismic Gas S/O Valve 3/25/2021 SGSOV Approved ROBERT MCDOWELL
Smoke Detectors 3/25/2021 Approved ROBERT MCDOWELL
ELECTRICAL-Final 4/5/2021 Approved ROBERT MCDOWELL
Final 4/5/2021 OK to Issue CofO ROBERT MCDOWELL
HVAC-Final 4/5/2021 Approved ROBERT MCDOWELL
PLUMBING-Final 4/5/2021 Approved ROBERT MCDOWELL
Service/Power Release 4/5/2021 Approved ROBERT MCDOWELL