4027 1/2 S HALLDALE AVE 90062
Certificate Information: 4027 1/2 S HALLDALE AVE 90062
- Application / Permit
- 20016-20000-08865
- Plan Check / Job No.
- B20VN05276
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 27' 5" X 42' IRR.-SHAPE DETACHED 2-CAR GARAGE/STORAGE/WORKSHOP TO ACCESSORY DWELLING UNIT. ALL WORK DONE PER WFPP.
- Permit Issued
- Issued on 11/18/2020
- Issuing Office
- Current Status
- CofO Issued on 6/17/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Plan Check Approved | 6/23/2020 | GURUNATH NESARAJAH |
| Issued | 11/18/2020 | APPLICANT |
| CofO in Progress | 4/9/2021 | WILL MCCONNAUGHY |
| Permit Finaled | 6/17/2021 | DEROLD HAUFF |
| CofO Issued | 6/17/2021 | DEROLD HAUFF |
| Permit Finaled | 6/17/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/23/2020 | RENZ SORIANO |
| Sewer availability | Cleared | 4/23/2020 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 4/27/2020 | RENZ SORIANO |
| Construction near power lines | Cleared | 6/7/2020 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/18/2020 | Not Ready for Inspection | ROBERT MCDOWELL |
| Footing/Foundation/Slab | 12/18/2020 | Not Ready for Inspection | ROBERT MCDOWELL |
| Footing/Foundation/Slab | 12/23/2020 | Not Ready for Inspection | ROBERT MCDOWELL |
| Underground Mechanical | 12/23/2020 | Approved | ROBERT MCDOWELL |
| Excavation/Setback/Form/Re-Bar | 12/28/2020 | Not Ready for Inspection | ROBERT MCDOWELL |
| Excavation/Setback/Form/Re-Bar | 12/30/2020 | Approved | ROBERT MCDOWELL |
| Floor/Roof Diaphrgm/Shear Wall | 1/19/2021 | Approved | ROBERT MCDOWELL |
| Green Building Rough | 1/19/2021 | Not Ready for Inspection | ROBERT MCDOWELL |
| Rough-Elec/Plmb/HVAC | 1/25/2021 | Corrections Issued | ROBERT MCDOWELL |
| BUILDING-Rough-Frame | 2/1/2021 | Approved | ROBERT MCDOWELL |
| ELECTRICAL-Rough | 2/1/2021 | Approved | ROBERT MCDOWELL |
| Green Building Rough | 2/1/2021 | Approved | ROBERT MCDOWELL |
| PLUMBING-Rough | 2/1/2021 | Approved | ROBERT MCDOWELL |
| Insulation | 2/2/2021 | Corrections Issued | DAVID FEILER |
| Interior/Exterior Lathing | 2/2/2021 | Not Ready for Inspection | DAVID FEILER |
| HVAC-Rough | 2/9/2021 | Approved | ROBERT MCDOWELL |
| Insulation | 2/9/2021 | Approved | ROBERT MCDOWELL |
| Interior/Exterior Lathing | 2/9/2021 | Approved | ROBERT MCDOWELL |
| Drywall Nailing | 2/22/2021 | Approved | ROBERT MCDOWELL |
| ELECTRICAL-Final | 3/8/2021 | Corrections Issued | FREDDIE RIVERA |
| Service/Power Release | 3/8/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Final | 3/12/2021 | Corrections Issued | ROBERT MCDOWELL |
| Green Building Final | 3/12/2021 | Not Ready for Inspection | ROBERT MCDOWELL |
| SGSOV-Seismic Gas S/O Valve | 3/12/2021 | SGSOV Not Ready | ROBERT MCDOWELL |
| Smoke Detectors | 3/12/2021 | Not Ready for Inspection | ROBERT MCDOWELL |
| Final | 3/25/2021 | Corrections Issued | ROBERT MCDOWELL |
| Green Building Final | 3/25/2021 | Approved | ROBERT MCDOWELL |
| SGSOV-Seismic Gas S/O Valve | 3/25/2021 | SGSOV Approved | ROBERT MCDOWELL |
| Smoke Detectors | 3/25/2021 | Approved | ROBERT MCDOWELL |
| ELECTRICAL-Final | 4/5/2021 | Approved | ROBERT MCDOWELL |
| Final | 4/5/2021 | OK to Issue CofO | ROBERT MCDOWELL |
| HVAC-Final | 4/5/2021 | Approved | ROBERT MCDOWELL |
| PLUMBING-Final | 4/5/2021 | Approved | ROBERT MCDOWELL |
| Service/Power Release | 4/5/2021 | Approved | ROBERT MCDOWELL |