10341 N BARTEE AVE 91331

Certificate Information: 10341 N BARTEE AVE 91331

Application / Permit
20016-20000-08732
Plan Check / Job No.
B20VN05197
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED 20' X 18' 2-CAR GARAGE TO ACCESSORY DWELLING UNIT. ALL WORK DONE PER WFPP.
Permit Issued
Issued on 6/4/2020
Issuing Office
Current Status
CofO Issued on 11/12/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Plan Check Approved 6/1/2020 OMAR GARNICA
Issued 6/4/2020 APPLICANT
CofO in Progress 10/21/2020 JENNIFER RABUCHIN
Permit Finaled 11/12/2020 MICHAEL SMITH
CofO Issued 11/12/2020 MICHAEL SMITH
Permit Finaled 11/12/2020 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 4/21/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 4/21/2020 ADRIAN CASTRO
Sewer availability Cleared 4/21/2020 ADRIAN CASTRO
Construction near power lines Cleared 5/21/2020 OSCAR CASTRO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/15/2020 Corrections Issued JENNIFER RABUCHIN
Footing/Foundation/Slab 7/14/2020 Approved JENNIFER RABUCHIN
PLUMBING-Rough 7/14/2020 Partial Approval JENNIFER RABUCHIN
Sewer 7/14/2020 Corrections Issued JENNIFER RABUCHIN
BUILDING-Rough-Frame 7/29/2020 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Rough 7/29/2020 Corrections Issued JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 7/29/2020 Approved JENNIFER RABUCHIN
Gas Test 7/29/2020 Partial Approval JENNIFER RABUCHIN
Green Building Rough 7/29/2020 Partial Inspection JENNIFER RABUCHIN
MERV13>=Rough 7/29/2020 Approved JENNIFER RABUCHIN
METHANE-Rough 7/29/2020 Approved JENNIFER RABUCHIN
METHANE-Subgrade 7/29/2020 Approved JENNIFER RABUCHIN
PLUMBING-Rough 7/29/2020 Corrections Issued JENNIFER RABUCHIN
Sewer 7/29/2020 Not Ready for Inspection JENNIFER RABUCHIN
Insulation 7/30/2020 Approved JENNIFER RABUCHIN
Shower Pan 7/30/2020 Approved JENNIFER RABUCHIN
Drywall Nailing 8/3/2020 Approved DANIEL ORRANTE
Interior/Exterior Lathing 8/3/2020 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 9/29/2020 Approved JENNIFER RABUCHIN
Final 9/29/2020 Corrections Issued JENNIFER RABUCHIN
Green Building Final 9/29/2020 Corrections Issued JENNIFER RABUCHIN
Green Building Rough 9/29/2020 Approved JENNIFER RABUCHIN
MERV13>=Final 9/29/2020 Approved JENNIFER RABUCHIN
PLUMBING-Final 9/29/2020 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 9/29/2020 SGSOV Approved JENNIFER RABUCHIN
Smoke Detectors 9/29/2020 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 10/9/2020 Approved JENNIFER RABUCHIN
Final 10/9/2020 OK to Issue CofO JENNIFER RABUCHIN
Green Building Final 10/9/2020 Approved JENNIFER RABUCHIN
HVAC-Final 10/9/2020 Approved JENNIFER RABUCHIN
PLUMBING-Final 10/9/2020 Approved JENNIFER RABUCHIN
PLUMBING-Final 10/21/2020 Approved JENNIFER RABUCHIN
Special/Order Compliance 10/21/2020 Approved JENNIFER RABUCHIN