520 N BEACHWOOD DR 90004
Certificate Information: 520 N BEACHWOOD DR 90004
- Application / Permit
- 20016-20000-08585
- Plan Check / Job No.
- B20VN05142
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 17'-5" X 18'-3" DETACHED GARAGE AND ADD 6'-0" X 12'-9" FOR (N) ACCESSORY DWELLING UNIT. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 9/4/2020
- Issuing Office
- Current Status
- CofO Issued on 1/28/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Plan Check Approved | 9/4/2020 | JENNIFER LEE |
| Issued | 9/4/2020 | APPLICANT |
| CofO in Progress | 1/28/2026 | JEFFREY MEAD |
| Permit Finaled | 1/28/2026 | DEROLD HAUFF |
| CofO Issued | 1/28/2026 | DEROLD HAUFF |
| Permit Finaled | 1/28/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 5/6/2020 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 5/6/2020 | WALLIE JONG |
| Roof/Waste drainage to street | Cleared | 5/6/2020 | WALLIE JONG |
| Sewer availability | Cleared | 5/6/2020 | WALLIE JONG |
| ZI | Cleared | 7/28/2020 | SARAHI ORTEGA |
| Construction near power lines | Cleared | 8/9/2020 | RIDWAN HARDY |
Contact Information
| Contractor | Ofir Construction Inc; Lic. No.: 1036242-B | 20641 SCHOOLCRAFT STREET WINNETKA, CA 91306 |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 6631 MURIETTA AVE LOS ANGELES, CA 91405 |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/2/2020 | Approved | CHRIS CHRISTENSEN |
| METHANE-Barrier | 10/2/2020 | Approved | CHRIS CHRISTENSEN |
| METHANE-Subgrade | 10/2/2020 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 10/30/2020 | Approved | ARTHUR SARGSYAN |
| BUILDING-Rough-Frame | 11/10/2020 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 11/10/2020 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 11/10/2020 | Partial Approval | CHRIS CHRISTENSEN |
| Green Building Rough | 11/10/2020 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| METHANE-Rough | 11/10/2020 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 11/10/2020 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Wood Frame | 11/10/2020 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 11/17/2020 | Approved | CHRIS CHRISTENSEN |
| Deputy Wood Construction | 11/17/2020 | No Access for Inspection | ELMER BLAND |
| ELECTRICAL-Rough | 11/17/2020 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 11/17/2020 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| HVAC-Rough | 11/17/2020 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 11/17/2020 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 12/15/2020 | Approved | CHRIS CHRISTENSEN |
| Insulation | 12/15/2020 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 12/15/2020 | Partial Approval | CHRIS CHRISTENSEN |
| Shower Pan | 12/15/2020 | Approved | CHRIS CHRISTENSEN |
| Drywall Nailing | 12/23/2020 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Final | 3/2/2021 | Approved | CHRIS CHRISTENSEN |
| Final | 3/2/2021 | Corrections Issued | CHRIS CHRISTENSEN |
| Green Building Final | 3/2/2021 | Approved | CHRIS CHRISTENSEN |
| HVAC-Final | 3/2/2021 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Final | 3/2/2021 | Approved | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 3/2/2021 | SGSOV Approved | CHRIS CHRISTENSEN |
| Smoke Detectors | 3/2/2021 | Approved | CHRIS CHRISTENSEN |
| Final | 3/10/2021 | Corrections Issued | CHRIS CHRISTENSEN |
| Final | 4/23/2021 | Conditional Approval | CHRIS CHRISTENSEN |
| Special/Order Compliance | 5/13/2025 | Corrections Issued | RAUL BARAJAS |
| Special/Order Compliance | 1/5/2026 | Partial Inspection | JEFFREY MEAD |
| Final | 1/27/2026 | OK to Issue CofO | JEFFREY MEAD |