14820 W ADDISON ST 91403
Certificate Information: 14820 W ADDISON ST 91403
- Application / Permit
- 20016-20000-08570
- Plan Check / Job No.
- B20VN05133
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT 19'-6" X 18'-6" 2-CAR GARAGE AND 26'-6" X 16'-6" RECREATION ROOM TO ACCESSORY DWELLING UNIT. ALL WORK DONE PER WFPP.
- Permit Issued
- Issued on 6/2/2020
- Issuing Office
- Current Status
- CofO Issued on 12/27/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Plan Check Approved | 6/2/2020 | ARTIN ZARUKIAN |
| Issued | 6/2/2020 | APPLICANT |
| CofO in Progress | 12/23/2022 | CHRISTOPHE COCHRAN |
| CofO Issued | 12/27/2022 | MICHAEL SMITH |
| Permit Finaled | 12/27/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 4/17/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 4/17/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 4/17/2020 | ADRIAN CASTRO |
| ZI | Cleared | 5/19/2020 | MIGUEL GAMBOA |
Contact Information
| Contractor | Pampa Investment Inc; Lic. No.: 832632-B | 984 BROADWAY #302 CHULA VISTA, CA 91911 |
Inspector Information
| RAUL OLAGI, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/14/2020 | Not Ready for Inspection | CHARLES POWELL |
| Footing/Foundation/Slab | 1/15/2021 | Corrections Issued | ARAM AVEDISIAN |
| Deputy Drilled-In Anchors | 1/19/2021 | Partial Approval | CHARLES POWELL |
| PLUMBING-Rough | 1/21/2021 | Corrections Issued | MATTHEW NELSON |
| PLUMBING-Rough | 2/19/2021 | Partial Approval | CHARLES POWELL |
| Deputy Drilled-In Anchors | 3/31/2021 | Approved | RICHARD DOCKUS |
| Footing/Foundation/Slab | 4/7/2021 | Approved | CHARLES POWELL |
| ELECTRICAL-Rough | 6/16/2021 | Corrections Issued | CHARLES POWELL |
| HVAC-Rough | 6/16/2021 | Partial Approval | CHARLES POWELL |
| PLUMBING-Rough | 6/16/2021 | Corrections Issued | CHARLES POWELL |
| ELECTRICAL-Rough | 11/17/2021 | Not Ready for Inspection | JACK KARGODORIAN |
| HVAC-Rough | 11/17/2021 | Corrections Issued | JACK KARGODORIAN |
| PLUMBING-Rough | 11/17/2021 | Not Ready for Inspection | JACK KARGODORIAN |
| ELECTRICAL-Rough | 11/23/2021 | Not Ready for Inspection | MARK JOHNSON |
| HVAC-Rough | 11/23/2021 | Not Ready for Inspection | MARK JOHNSON |
| PLUMBING-Rough | 11/23/2021 | Not Ready for Inspection | MARK JOHNSON |
| HVAC-Rough | 3/7/2022 | Partial Approval | JACK KARGODORIAN |
| MERV13>=Rough | 3/7/2022 | Approved | JACK KARGODORIAN |
| PLUMBING-Rough | 3/7/2022 | Partial Approval | JACK KARGODORIAN |
| ELECTRICAL-Rough | 3/14/2022 | Approved | JACK KARGODORIAN |
| Green Building Rough | 3/14/2022 | Approved | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 3/22/2022 | Corrections Issued | MICHAEL TEMPLE |
| Interior/Exterior Lathing | 3/22/2022 | Partial Approval | MICHAEL TEMPLE |
| Wood Frame | 6/20/2022 | Corrections Issued | MICHAEL PELHAM |
| BUILDING-Rough-Frame | 6/23/2022 | Approved | JACK KARGODORIAN |
| Wood Frame | 6/23/2022 | Approved | JACK KARGODORIAN |
| Insulation | 6/24/2022 | Off-Hour Fees Due | |
| Final | 12/13/2022 | Corrections Issued | CHRISTOPHE COCHRAN |
| Green Building Final | 12/13/2022 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| MERV13>=Final | 12/13/2022 | Approved | CHRISTOPHE COCHRAN |
| SGSOV-Seismic Gas S/O Valve | 12/13/2022 | SGSOV Approved | CHRISTOPHE COCHRAN |
| Smoke Detectors | 12/13/2022 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Final | 12/19/2022 | Corrections Issued | THOMAS FINNILA |
| Green Building Final | 12/19/2022 | Approved | THOMAS FINNILA |
| Smoke Detectors | 12/19/2022 | Approved | THOMAS FINNILA |
| HVAC-Final | 12/22/2022 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Final | 12/23/2022 | OK to Issue CofO | CHRISTOPHE COCHRAN |