14820 W ADDISON ST 91403

Certificate Information: 14820 W ADDISON ST 91403

Application / Permit
20016-20000-08570
Plan Check / Job No.
B20VN05133
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT 19'-6" X 18'-6" 2-CAR GARAGE AND 26'-6" X 16'-6" RECREATION ROOM TO ACCESSORY DWELLING UNIT. ALL WORK DONE PER WFPP.
Permit Issued
Issued on 6/2/2020
Issuing Office
Current Status
CofO Issued on 12/27/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Plan Check Approved 6/2/2020 ARTIN ZARUKIAN
Issued 6/2/2020 APPLICANT
CofO in Progress 12/23/2022 CHRISTOPHE COCHRAN
CofO Issued 12/27/2022 MICHAEL SMITH
Permit Finaled 12/27/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 4/17/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 4/17/2020 ADRIAN CASTRO
Sewer availability Cleared 4/17/2020 ADRIAN CASTRO
ZI Cleared 5/19/2020 MIGUEL GAMBOA

Contact Information

Contractor Pampa Investment Inc; Lic. No.: 832632-B 984 BROADWAY #302      CHULA VISTA, CA 91911

Inspector Information

RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/14/2020 Not Ready for Inspection CHARLES POWELL
Footing/Foundation/Slab 1/15/2021 Corrections Issued ARAM AVEDISIAN
Deputy Drilled-In Anchors 1/19/2021 Partial Approval CHARLES POWELL
PLUMBING-Rough 1/21/2021 Corrections Issued MATTHEW NELSON
PLUMBING-Rough 2/19/2021 Partial Approval CHARLES POWELL
Deputy Drilled-In Anchors 3/31/2021 Approved RICHARD DOCKUS
Footing/Foundation/Slab 4/7/2021 Approved CHARLES POWELL
ELECTRICAL-Rough 6/16/2021 Corrections Issued CHARLES POWELL
HVAC-Rough 6/16/2021 Partial Approval CHARLES POWELL
PLUMBING-Rough 6/16/2021 Corrections Issued CHARLES POWELL
ELECTRICAL-Rough 11/17/2021 Not Ready for Inspection JACK KARGODORIAN
HVAC-Rough 11/17/2021 Corrections Issued JACK KARGODORIAN
PLUMBING-Rough 11/17/2021 Not Ready for Inspection JACK KARGODORIAN
ELECTRICAL-Rough 11/23/2021 Not Ready for Inspection MARK JOHNSON
HVAC-Rough 11/23/2021 Not Ready for Inspection MARK JOHNSON
PLUMBING-Rough 11/23/2021 Not Ready for Inspection MARK JOHNSON
HVAC-Rough 3/7/2022 Partial Approval JACK KARGODORIAN
MERV13>=Rough 3/7/2022 Approved JACK KARGODORIAN
PLUMBING-Rough 3/7/2022 Partial Approval JACK KARGODORIAN
ELECTRICAL-Rough 3/14/2022 Approved JACK KARGODORIAN
Green Building Rough 3/14/2022 Approved JACK KARGODORIAN
BUILDING-Rough-Frame 3/22/2022 Corrections Issued MICHAEL TEMPLE
Interior/Exterior Lathing 3/22/2022 Partial Approval MICHAEL TEMPLE
Wood Frame 6/20/2022 Corrections Issued MICHAEL PELHAM
BUILDING-Rough-Frame 6/23/2022 Approved JACK KARGODORIAN
Wood Frame 6/23/2022 Approved JACK KARGODORIAN
Insulation 6/24/2022 Off-Hour Fees Due
Final 12/13/2022 Corrections Issued CHRISTOPHE COCHRAN
Green Building Final 12/13/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
MERV13>=Final 12/13/2022 Approved CHRISTOPHE COCHRAN
SGSOV-Seismic Gas S/O Valve 12/13/2022 SGSOV Approved CHRISTOPHE COCHRAN
Smoke Detectors 12/13/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
Final 12/19/2022 Corrections Issued THOMAS FINNILA
Green Building Final 12/19/2022 Approved THOMAS FINNILA
Smoke Detectors 12/19/2022 Approved THOMAS FINNILA
HVAC-Final 12/22/2022 Partial Approval CHRISTOPHER DELLEFIELD
Final 12/23/2022 OK to Issue CofO CHRISTOPHE COCHRAN