10332 W WILKINS AVE 90024

Certificate Information: 10332 W WILKINS AVE 90024

Application / Permit
20016-20000-08548
Plan Check / Job No.
B20VN05132
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
DIRECT CONVERSION OF (E) GARAGE TO ACCESSORY DWELLING UNIT (20'-0"X26'-0") all work per WFPP
Permit Issued
Issued on 8/24/2020
Issuing Office
Current Status
CofO Issued on 8/23/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/3/2020 APPLICANT
Assigned to Plan Check Engineer 4/16/2020 MOHAMMAD ESMAILI
Corrections Issued 4/27/2020 MOHAMMAD ESMAILI
Quality Review Completed 5/4/2020 OMID HEDAYAT
Green Plans Picked Up 5/4/2020 APPLICANT
Building Plans Picked Up 5/15/2020 APPLICANT
Applicant returned to address corrections 6/19/2020 MOHAMMAD ESMAILI
Applicant returned to address corrections 7/10/2020 MOHAMMAD ESMAILI
Plan Check Approved 8/24/2020 MOHAMMAD ESMAILI
Issued 8/24/2020 APPLICANT
CofO in Progress 7/16/2021 GERMAN RODRIGUEZ MENDOZA
CofO Issued 8/23/2021 VINCENT COTTON
Permit Finaled 8/23/2021 VINCENT COTTON

Permit Application Clearance Information

Address approval Cleared 5/14/2020 DINAH GARIN
Roof/Waste drainage to street Cleared 5/14/2020 DINAH GARIN
Sewer availability Cleared 5/14/2020 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 5/15/2020 DINAH GARIN
Green Code Cleared 6/24/2020 MICHAEL AYERS
Construction near power lines Cleared 7/30/2020 RIDWAN HARDY
Grading Pre-Inspection Cleared 8/24/2020 MOHAMMAD ESMAILI

Contact Information

Contractor Foundation To Roof Inc; Lic. No.: 767761-B 10800 SOUTH LA CIENEGA BL      INGLEWOOD, CA 90304

Inspector Information

DAVID SCANTLIN, (310) 914-3863 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/31/2020 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Deputy Drilled-In Anchors 9/24/2020 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Special/Order Compliance 9/24/2020 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 11/12/2020 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 11/24/2020 Partial Approval GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 12/9/2020 Approved GERMAN RODRIGUEZ MENDOZA
Floor/Roof Diaphrgm/Shear Wall 12/17/2020 Partial Approval GERMAN RODRIGUEZ MENDOZA
Final 7/14/2021 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Green Building Final 7/14/2021 Approved GERMAN RODRIGUEZ MENDOZA
Green Building Rough 7/14/2021 Approved GERMAN RODRIGUEZ MENDOZA
METHANE-Final 7/14/2021 Approved GERMAN RODRIGUEZ MENDOZA
METHANE-Rough 7/14/2021 Approved GERMAN RODRIGUEZ MENDOZA
SGSOV-Seismic Gas S/O Valve 7/14/2021 SGSOV Approved GERMAN RODRIGUEZ MENDOZA
Smoke Detectors 7/14/2021 Approved GERMAN RODRIGUEZ MENDOZA
Wood Frame 7/14/2021 Approved GERMAN RODRIGUEZ MENDOZA