14767 W VINTAGE ST 91345

Certificate Information: 14767 W VINTAGE ST 91345

Application / Permit
20016-20000-08477
Plan Check / Job No.
B20VN05091
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 18' X 20' DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT. ALL WORK PER WFPP.
Permit Issued
Issued on 5/1/2020
Issuing Office
Current Status
CofO Issued on 10/28/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/16/2020 APPLICANT
Assigned to Plan Check Engineer 4/17/2020 RAPHAEL ROSAS
Corrections Issued 4/17/2020 RAPHAEL ROSAS
Plan Check Approved 4/30/2020 JENNIFER LEE
Issued 5/1/2020 APPLICANT
CofO in Progress 10/24/2025 JENNIFER RABUCHIN
Permit Finaled 10/28/2025 RUBEN SALAS
CofO Issued 10/28/2025 RUBEN SALAS
Permit Finaled 10/28/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 4/21/2020 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 4/21/2020 JEANIE LAM
Permit Cleared 4/21/2020 JEANIE LAM
Roof/Waste drainage to street Cleared 4/21/2020 JEANIE LAM
Sewer availability Cleared 4/21/2020 JEANIE LAM

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/16/2020 Approved JENNIFER RABUCHIN
PLUMBING-Rough 7/16/2020 Partial Approval JENNIFER RABUCHIN
BUILDING-Rough-Frame 7/30/2020 Partial Approval JENNIFER RABUCHIN
Insulation 8/7/2020 Corrections Issued MISAEL ESPARZA
BUILDING-Rough-Frame 11/19/2020 Corrections Issued JENNIFER RABUCHIN
Gas Test 11/19/2020 Partial Approval JENNIFER RABUCHIN
Sewer 11/19/2020 Not Ready for Inspection JENNIFER RABUCHIN
ELECTRICAL-Rough 5/13/2022 Corrections Issued JENNIFER RABUCHIN
Insulation 5/13/2022 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Rough 10/31/2022 Approved JENNIFER RABUCHIN
HVAC-Rough 10/31/2022 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 10/31/2022 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 10/31/2022 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 11/4/2022 Approved JENNIFER RABUCHIN
Green Building Rough 11/4/2022 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 11/4/2022 Approved JENNIFER RABUCHIN
Insulation 11/8/2022 Approved JENNIFER RABUCHIN
Drywall Nailing 11/14/2022 Approved JENNIFER RABUCHIN
Final 5/18/2023 Not Ready for Inspection JENNIFER RABUCHIN
Gas Test 5/18/2023 Partial Approval JENNIFER RABUCHIN
Green Building Final 5/18/2023 Not Ready for Inspection JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 5/18/2023 SGSOV Not Ready JENNIFER RABUCHIN
Smoke Detectors 5/18/2023 Not Ready for Inspection JENNIFER RABUCHIN
Pre-Inspection 5/23/2023 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 5/23/2023 SGSOV Approved JENNIFER RABUCHIN
Sewer 5/23/2023 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 11/14/2023 Corrections Issued JENNIFER RABUCHIN
Final 11/14/2023 Corrections Issued JENNIFER RABUCHIN
Green Building Final 11/14/2023 Corrections Issued JENNIFER RABUCHIN
Smoke Detectors 11/14/2023 Approved JENNIFER RABUCHIN
Final 10/9/2025 Corrections Issued JENNIFER RABUCHIN
Green Building Final 10/9/2025 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Final 10/23/2025 Approved JENNIFER RABUCHIN
Final 10/23/2025 OK to Issue CofO JENNIFER RABUCHIN
Green Building Final 10/23/2025 Approved JENNIFER RABUCHIN
HVAC-Final 10/23/2025 Approved JENNIFER RABUCHIN
PLUMBING-Final 10/23/2025 Approved JENNIFER RABUCHIN