6612 W DREXEL AVE 90048
Certificate Information: 6612 W DREXEL AVE 90048
- Application / Permit
- 20016-20000-08411
- Plan Check / Job No.
- B20VN05082
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 18' X 18' DETACHED GARAGE FOR (N) ACCESSORY DWELLING UNIT W/ 5' X 12'-8" OVERHANG PER GCS 65852.2(E)(1)(A). ALL WORK PER ENGINEERING. [NFPA-13D FIRE SPRINKLERS REQUIRED THROUGHOUT]
- Permit Issued
- Issued on 8/19/2020
- Issuing Office
- Current Status
- Issued on 8/19/2020
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/2/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/7/2020 | JENNIFER LEE |
| Corrections Issued | 4/9/2020 | JENNIFER LEE |
| Applicant returned to address corrections | 6/26/2020 | LUIS RINCON |
| Applicant returned to address corrections | 7/6/2020 | ROSENDO MEDINA |
| Applicant returned to address corrections | 8/5/2020 | JENNIFER LEE |
| Plan Check Approved | 8/18/2020 | JENNIFER LEE |
| Issued | 8/19/2020 | APPLICANT |
Permit Application Clearance Information
| Sewer availability | Cleared | 5/6/2020 | JUAN ASHTON |
| Eng Process Fee Ord 176,300 | Cleared | 5/12/2020 | JUAN ASHTON |
| Address approval | Cleared | 5/18/2020 | JUAN ASHTON |
| CPC | Cleared | 6/15/2020 | PABLO ESTRADA |
| Construction near power lines | Cleared | 6/19/2020 | WALTER RAMIREZ |
| Construction within easement | Cleared | 6/19/2020 | WALTER RAMIREZ |
| Roof/Waste drainage to street | Cleared | 6/22/2020 | JUAN ASHTON |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Carrillo,, Jesus Eduardo; Lic. No.: C77737 | 8207 BROOKGREEN RD DOWNEY, CA 90240 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/21/2020 | Corrections Issued | EVAN COOPER |
| Sewer | 8/21/2020 | Not Ready for Inspection | EVAN COOPER |
| Underground Mechanical | 8/21/2020 | Partial Approval | EVAN COOPER |
| Footing/Foundation/Slab | 8/31/2020 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 9/22/2020 | Partial Approval | EVAN COOPER |
| ELECTRICAL-Rough | 9/22/2020 | Approved | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 9/22/2020 | Approved | EVAN COOPER |
| Green Building Rough | 9/22/2020 | Not Ready for Inspection | EVAN COOPER |
| HVAC-Rough | 9/22/2020 | Approved | EVAN COOPER |
| METHANE-Rough | 9/22/2020 | Approved | EVAN COOPER |
| PLUMBING-Rough | 9/22/2020 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 9/24/2020 | Partial Approval | EVAN COOPER |
| Service/Power Release | 9/24/2020 | Approved | EVAN COOPER |
| Shower Pan | 9/24/2020 | Approved | EVAN COOPER |
| Insulation | 9/25/2020 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 9/25/2020 | Partial Approval | EVAN COOPER |
| Drywall Nailing | 9/28/2020 | Approved | EVAN COOPER |
| Green Building Rough | 9/28/2020 | Approved | EVAN COOPER |
| Service/Power Release | 10/20/2020 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 11/9/2020 | Approved | EVAN COOPER |
| Final | 11/9/2020 | Corrections Issued | EVAN COOPER |
| Green Building Final | 11/9/2020 | Not Ready for Inspection | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 11/9/2020 | SGSOV Approved | EVAN COOPER |
| Smoke Detectors | 11/9/2020 | Approved | EVAN COOPER |