17333 W BULLOCK ST 91316
Certificate Information: 17333 W BULLOCK ST 91316
- Application / Permit
- 20016-20000-08219
- Plan Check / Job No.
- B20VN04985
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT 20' X ' 30' (E) GARAGE AND STORAGE INTO A (N) ACCESSORY DWELLING UNIT. ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 5/4/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/10/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/27/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/1/2020 | RAPHAEL ROSAS |
| Corrections Issued | 4/3/2020 | RAPHAEL ROSAS |
| Plan Check Approved | 4/17/2020 | RAPHAEL ROSAS |
| Issued | 5/4/2020 | LADBS |
| CofO in Progress | 10/18/2022 | SEAN HAUPT |
| Permit Finaled | 2/10/2023 | JOHN JANSON |
| CofO Issued | 2/10/2023 | JOHN JANSON |
| Permit Finaled | 2/10/2023 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 4/7/2020 | GABRIEL ROBLES |
| Miscellaneous | Cleared | 4/7/2020 | GABRIEL ROBLES |
| Permit | Cleared | 4/7/2020 | GABRIEL ROBLES |
| Roof/Waste drainage to street | Cleared | 4/7/2020 | GABRIEL ROBLES |
| Sewer availability | Cleared | 4/7/2020 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 4/8/2020 | ADRIAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/24/2020 | Approved | STEVEN BACK |
| Footing/Foundation/Slab | 9/25/2020 | Approved | STEVEN BACK |
| Pre-Inspection | 9/25/2020 | Approved | STEVEN BACK |
| PLUMBING-Rough | 10/1/2020 | Partial Approval | STEVEN BACK |
| Sewer | 10/1/2020 | Approved | STEVEN BACK |
| Pre-Inspection | 1/22/2021 | No Access for Inspection | DAVID SCANTLIN |
| Rough-Elec/Plmb/HVAC | 1/22/2021 | No Access for Inspection | DAVID SCANTLIN |
| Wood Frame | 1/22/2021 | No Access for Inspection | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 1/28/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| ELECTRICAL-Rough | 1/28/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| Green Building Rough | 1/28/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| HVAC-Rough | 1/28/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| PLUMBING-Rough | 1/28/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| ELECTRICAL-Rough | 2/16/2021 | Corrections Issued | STEVEN BACK |
| HVAC-Rough | 2/16/2021 | Corrections Issued | STEVEN BACK |
| PLUMBING-Rough | 2/16/2021 | Corrections Issued | STEVEN BACK |
| BUILDING-Rough-Frame | 3/3/2021 | Partial Approval | STEVEN BACK |
| ELECTRICAL-Rough | 3/3/2021 | Approved | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 3/3/2021 | Partial Approval | STEVEN BACK |
| HVAC-Rough | 3/3/2021 | Approved | STEVEN BACK |
| PLUMBING-Rough | 3/3/2021 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 3/19/2021 | Partial Approval | STEVEN BACK |
| Green Building Rough | 3/19/2021 | Approved | STEVEN BACK |
| Insulation | 3/19/2021 | Partial Approval | STEVEN BACK |
| Insulation | 4/6/2021 | Approved | STEVEN BACK |
| Drywall Nailing | 5/14/2021 | Approved | STEPHANIE SWANSON |
| Pre-Inspection | 5/14/2021 | Partial Inspection | JESUS PINEDA |
| Shower Pan | 5/14/2021 | Approved | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 7/28/2021 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 4/26/2022 | Approved | SEAN HAUPT |
| ELECTRICAL-Final | 4/26/2022 | Corrections Issued | SEAN HAUPT |
| Final | 4/26/2022 | Corrections Issued | SEAN HAUPT |
| Green Building Final | 4/26/2022 | Approved | SEAN HAUPT |
| HVAC-Final | 4/26/2022 | Approved | SEAN HAUPT |
| PLUMBING-Final | 4/26/2022 | Approved | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 4/26/2022 | SGSOV Approved | SEAN HAUPT |
| Smoke Detectors | 4/26/2022 | Approved | SEAN HAUPT |
| ELECTRICAL-Final | 5/27/2022 | Not Ready for Inspection | SEAN HAUPT |
| Final | 5/27/2022 | Corrections Issued | SEAN HAUPT |
| ELECTRICAL-Final | 10/17/2022 | Approved | DAVID SCANTLIN |
| Final | 10/17/2022 | Not Ready for Inspection | DAVID SCANTLIN |
| Final | 10/18/2022 | OK to Issue CofO | SEAN HAUPT |