15028 W DEVONSHIRE ST 91345

Certificate Information: 15028 W DEVONSHIRE ST 91345

Application / Permit
20016-20000-08020
Plan Check / Job No.
B20VN04902
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EX DETACHED REC RM/STORAGE BUILDING INTO ACCESSORY DWELLING UNIT. ALL WORK PER WFPP.
Permit Issued
Issued on 5/15/2020
Issuing Office
Valley
Current Status
CofO Issued on 6/12/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/20/2020 APPLICANT
Assigned to Plan Check Engineer 3/24/2020 HAYATO TSUCHIYA
Corrections Issued 3/24/2020 HAYATO TSUCHIYA
Building Plans Picked Up 3/25/2020 APPLICANT
Plan Check Approved 4/23/2020 HAYATO TSUCHIYA
Issued 5/15/2020 LADBS
CofO in Progress 4/21/2021 JENNIFER RABUCHIN
Permit Finaled 6/12/2021 MICHAEL SMITH
CofO Issued 6/12/2021 MICHAEL SMITH
Permit Finaled 6/12/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 4/1/2020 LEE GUILBEAUX
Sewer availability Cleared 4/1/2020 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 4/13/2020 JOHN TRIANTAFYLLOS

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 11/9/2020 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Rough 11/9/2020 Partial Approval JENNIFER RABUCHIN
Insulation 11/9/2020 Partial Approval JENNIFER RABUCHIN
BUILDING-Rough-Frame 11/12/2020 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 11/12/2020 Corrections Issued JENNIFER RABUCHIN
Green Building Rough 11/12/2020 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 11/12/2020 Corrections Issued JENNIFER RABUCHIN
BUILDING-Rough-Frame 11/16/2020 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Rough 11/16/2020 Approved JENNIFER RABUCHIN
PLUMBING-Rough 11/16/2020 Partial Approval JENNIFER RABUCHIN
BUILDING-Rough-Frame 11/19/2020 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 11/19/2020 Approved JENNIFER RABUCHIN
Green Building Rough 11/19/2020 Approved JENNIFER RABUCHIN
PLUMBING-Rough 11/19/2020 Approved JENNIFER RABUCHIN
Drywall Nailing 1/11/2021 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 1/11/2021 Corrections Issued JENNIFER RABUCHIN
Final 1/11/2021 Corrections Issued JENNIFER RABUCHIN
Green Building Final 1/11/2021 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Final 1/11/2021 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 1/11/2021 SGSOV Approved JENNIFER RABUCHIN
Smoke Detectors 1/11/2021 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 1/25/2021 Approved JENNIFER RABUCHIN
Final 1/25/2021 Partial Approval JENNIFER RABUCHIN
Green Building Final 1/25/2021 Approved JENNIFER RABUCHIN
HVAC-Final 1/25/2021 Approved JENNIFER RABUCHIN
PLUMBING-Final 1/25/2021 Approved JENNIFER RABUCHIN
Final 4/21/2021 OK to Issue CofO JENNIFER RABUCHIN