15028 W DEVONSHIRE ST 91345
Certificate Information: 15028 W DEVONSHIRE ST 91345
- Application / Permit
- 20016-20000-08020
- Plan Check / Job No.
- B20VN04902
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EX DETACHED REC RM/STORAGE BUILDING INTO ACCESSORY DWELLING UNIT. ALL WORK PER WFPP.
- Permit Issued
- Issued on 5/15/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/12/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/20/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/24/2020 | HAYATO TSUCHIYA |
| Corrections Issued | 3/24/2020 | HAYATO TSUCHIYA |
| Building Plans Picked Up | 3/25/2020 | APPLICANT |
| Plan Check Approved | 4/23/2020 | HAYATO TSUCHIYA |
| Issued | 5/15/2020 | LADBS |
| CofO in Progress | 4/21/2021 | JENNIFER RABUCHIN |
| Permit Finaled | 6/12/2021 | MICHAEL SMITH |
| CofO Issued | 6/12/2021 | MICHAEL SMITH |
| Permit Finaled | 6/12/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 4/1/2020 | LEE GUILBEAUX |
| Sewer availability | Cleared | 4/1/2020 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 4/13/2020 | JOHN TRIANTAFYLLOS |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 11/9/2020 | Partial Approval | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 11/9/2020 | Partial Approval | JENNIFER RABUCHIN |
| Insulation | 11/9/2020 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 11/12/2020 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 11/12/2020 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Rough | 11/12/2020 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 11/12/2020 | Corrections Issued | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 11/16/2020 | Partial Approval | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 11/16/2020 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 11/16/2020 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 11/19/2020 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 11/19/2020 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 11/19/2020 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 11/19/2020 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 1/11/2021 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 1/11/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 1/11/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 1/11/2021 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Final | 1/11/2021 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 1/11/2021 | SGSOV Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 1/11/2021 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 1/25/2021 | Approved | JENNIFER RABUCHIN |
| Final | 1/25/2021 | Partial Approval | JENNIFER RABUCHIN |
| Green Building Final | 1/25/2021 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 1/25/2021 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 1/25/2021 | Approved | JENNIFER RABUCHIN |
| Final | 4/21/2021 | OK to Issue CofO | JENNIFER RABUCHIN |