11532 N BALBOA BLVD 91344
Certificate Information: 11532 N BALBOA BLVD 91344
- Application / Permit
- 20016-20000-07919
- Plan Check / Job No.
- B20VN04859
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 43' x 19'6" GARAGE/STORAGE TO ACCESSORY DWELLING UNIT "COMPLY WITH DEPARTMENT ORDER effective date 03/02/2020. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
- Permit Issued
- Issued on 5/29/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/28/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/19/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/19/2020 | JEFFREY TANGONAN |
| Corrections Issued | 3/19/2020 | JEFFREY TANGONAN |
| Building Plans Picked Up | 3/26/2020 | APPLICANT |
| Issued | 5/29/2020 | LADBS |
| CofO in Progress | 3/25/2021 | HAGOP BADOSSIAN |
| Permit Finaled | 4/28/2021 | DAVID JAMES |
| CofO Issued | 4/28/2021 | DAVID JAMES |
| Permit Finaled | 4/28/2021 | DAVID JAMES |
Permit Application Clearance Information
| Address approval | Cleared | 4/6/2020 | ADRIAN CASTRO |
| Roof/Waste drainage to street | Cleared | 4/6/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 4/6/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 4/13/2020 | LEE GUILBEAUX |
| Construction near power lines | Cleared | 5/13/2020 | RIDWAN HARDY |
| Hold | Cleared | 7/28/2020 | JASON SHEETS |
Contact Information
| Contractor | Vargas & Sons Construction Inc; Lic. No.: 1059942-B | 6851 JAMIESON AVENUE RESEDA, CA 91335 |
Inspector Information
| ARA SINANIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HASANTHA WEERASEKARA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| SCOTT SHUSTER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOEL GUARDADO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIYA MIHALEVA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOSE RUBIO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID JAMES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID HICKMAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN HAMILTON, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN STEPHENS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| PIERRE VEGA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK VAN SLOOTEN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MICKEY YAMASHITA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RICHARD ROBLES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HAGOP BADOSSIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM BEAUCHAMP, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK DOVICO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| THOMAS WOODS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL VASQUEZ, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| AUGUSTUS ALBAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| LEO MILBAUER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIO CUEVAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Floor/Roof Diaphrgm/Shear Wall | 8/10/2020 | Approved | HAGOP BADOSSIAN |
| Underground Mechanical | 9/28/2020 | Approved | HAGOP BADOSSIAN |
| Deputy Drilled-In Anchors | 10/1/2020 | Conditional Approval | HAGOP BADOSSIAN |
| Excavation/Setback/Form/Re-Bar | 10/6/2020 | Approved | HAGOP BADOSSIAN |
| ELECTRICAL-Rough | 10/28/2020 | Approved | HAGOP BADOSSIAN |
| PLUMBING-Rough | 10/28/2020 | Approved | HAGOP BADOSSIAN |
| Wood Frame | 10/28/2020 | Corrections Issued | HAGOP BADOSSIAN |
| Footing/Foundation/Slab | 12/7/2020 | No Access for Inspection | HAGOP BADOSSIAN |
| MERV13>=Rough | 12/7/2020 | No Access for Inspection | HAGOP BADOSSIAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/9/2020 | Partial Approval | HAGOP BADOSSIAN |
| HVAC-Rough | 12/9/2020 | Approved | HAGOP BADOSSIAN |
| BUILDING-Rough-Frame | 12/10/2020 | Approved | HAGOP BADOSSIAN |
| Green Building Rough | 12/10/2020 | Approved | HAGOP BADOSSIAN |
| Insulation | 12/10/2020 | Approved | HAGOP BADOSSIAN |
| MERV13>=Rough | 12/10/2020 | Approved | HAGOP BADOSSIAN |
| Drywall Nailing | 12/17/2020 | Corrections Issued | HAGOP BADOSSIAN |
| Special/Order Compliance | 12/21/2020 | Corrections Issued | HAGOP BADOSSIAN |
| Shower Pan | 12/28/2020 | Approved | HAGOP BADOSSIAN |
| Wood Frame | 12/28/2020 | Not Ready for Inspection | HAGOP BADOSSIAN |
| Interior/Exterior Lathing | 12/29/2020 | Approved | HAGOP BADOSSIAN |
| Shower Pan | 12/29/2020 | Approved | HAGOP BADOSSIAN |
| Special/Order Compliance | 12/29/2020 | Approved | HAGOP BADOSSIAN |
| PLUMBING-Rough | 1/7/2021 | Corrections Issued | ROBERT SUNSERI |
| Sewer | 1/12/2021 | Approved | HAGOP BADOSSIAN |
| Drywall Nailing | 3/1/2021 | Approved | HAGOP BADOSSIAN |
| Final | 3/1/2021 | Corrections Issued | HAGOP BADOSSIAN |
| Green Building Final | 3/1/2021 | Approved | HAGOP BADOSSIAN |
| MERV13>=Final | 3/1/2021 | Approved | HAGOP BADOSSIAN |
| SGSOV-Seismic Gas S/O Valve | 3/1/2021 | SGSOV Not Ready | HAGOP BADOSSIAN |
| Smoke Detectors | 3/1/2021 | Approved | HAGOP BADOSSIAN |
| Final | 3/24/2021 | OK to Issue CofO | HAGOP BADOSSIAN |
| SGSOV-Seismic Gas S/O Valve | 3/24/2021 | SGSOV Approved | HAGOP BADOSSIAN |