2730 S BURKSHIRE AVE 90064

Certificate Information: 2730 S BURKSHIRE AVE 90064

Application / Permit
20016-20000-07847
Plan Check / Job No.
B20VN04813
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 20' 1" X 20' 5" DETACHED GARAGE TO ACCESSORY DWELLING UNIT. ALL WORK DONE PER STRUCTURAL ENGINEERING.
Permit Issued
Issued on 8/5/2020
Issuing Office
Valley
Current Status
CofO Issued on 6/15/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/19/2020 APPLICANT
Assigned to Plan Check Engineer 3/19/2020 GURUNATH NESARAJAH
Corrections Issued 3/19/2020 GURUNATH NESARAJAH
Building Plans Picked Up 3/27/2020 APPLICANT
Plan Check Approved 7/21/2020 GURUNATH NESARAJAH
Issued 8/5/2020 APPLICANT
CofO in Progress 6/7/2021 OGANES TARAKHCHYAN
CofO Issued 6/15/2021 RONALD MYRICK
Permit Finaled 6/15/2021 RONALD MYRICK

Permit Application Clearance Information

Address approval Cleared 4/1/2020 DINAH GARIN
Sewer availability Cleared 4/1/2020 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 4/6/2020 GABRIEL ROBLES
Specific Plan Cleared 4/6/2020 PABLO ESTRADA
Construction near power lines Cleared 6/7/2020 RIDWAN HARDY

Contact Information

Contractor Amerbuild Inc; Lic. No.: 1024554-B 22108 VANOWEN STREET      WOODLAND HILLS, CA 91303
Engineer Terrio,, Greyson Franklin; Lic. No.: C87383 1561 RUGBY CIR      THOUSAND OAKS, CA 91360

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/9/2021 Conditional Approval RICHARD ROBLES
Sewer 2/11/2021 Partial Approval RICHARD ROBLES
Footing/Foundation/Slab 2/18/2021 Approved RICHARD ROBLES
BUILDING-Rough-Frame 3/23/2021 Not Ready for Inspection EVAN COOPER
ELECTRICAL-Rough 3/23/2021 Not Ready for Inspection EVAN COOPER
PLUMBING-Rough 3/23/2021 Approved EVAN COOPER
Pre-Inspection 3/23/2021 Corrections Issued EVAN COOPER
BUILDING-Rough-Frame 4/1/2021 Partial Approval OGANES TARAKHCHYAN
ELECTRICAL-Rough 4/1/2021 Approved OGANES TARAKHCHYAN
Green Building Rough 4/1/2021 Approved OGANES TARAKHCHYAN
HVAC-Rough 4/1/2021 Partial Approval OGANES TARAKHCHYAN
PLUMBING-Rough 4/1/2021 Approved OGANES TARAKHCHYAN
Insulation 4/16/2021 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 4/16/2021 Approved OGANES TARAKHCHYAN
Shower Pan 4/16/2021 Approved OGANES TARAKHCHYAN
Drywall Nailing 4/27/2021 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 5/24/2021 Approved EVAN COOPER
Final 5/24/2021 Corrections Issued EVAN COOPER
Green Building Final 5/24/2021 Not Ready for Inspection EVAN COOPER
SGSOV-Seismic Gas S/O Valve 5/24/2021 SGSOV Approved EVAN COOPER
Smoke Detectors 5/24/2021 Approved EVAN COOPER
Final 6/4/2021 OK to Issue CofO OGANES TARAKHCHYAN
Green Building Final 6/4/2021 Approved OGANES TARAKHCHYAN