20620 W CHATSBORO DR 91364

Certificate Information: 20620 W CHATSBORO DR 91364

Application / Permit
20016-20000-07757
Plan Check / Job No.
B20VN04770
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Patio Cover
Work Description
REMODEL TO SINGLE FAMILY DWELLING INCLUDING: FAMILY ROOM, LAUNDRY ROOM AND (E) STAIRCASE ON FIRST FLOOR AND REMODEL BEDROOM AND CONVERT FAMILY ROOM INTO BEDROOM ON SECOND FLOOR OF (E) SINGLE FAMILY DWELLING AND ADD (N) 30'-4" X 16'-1" OPEN TRELLIS TO REAR ALL WORK PER ENGINEERING
Permit Issued
Issued on 9/24/2020
Issuing Office
Current Status
CofO Issued on 1/25/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/18/2020 APPLICANT
Assigned to Plan Check Engineer 4/9/2020 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 4/20/2020 SEWADA ZADOORIAN MILAGARDI
Quality Review Completed 5/5/2020 OMID HEDAYAT
Building Plans Picked Up 5/12/2020 APPLICANT
Applicant returned to address corrections 8/10/2020 SEWADA ZADOORIAN MILAGARDI
Plan Check Approved 9/24/2020 SEWADA ZADOORAN MILAGARDI
Issued 9/24/2020 APPLICANT
CofO in Progress 12/20/2022 PETER FOLLING
Permit Finaled 1/25/2023 JOHN JANSON
CofO Issued 1/25/2023 JOHN JANSON
Permit Finaled 1/25/2023 JOHN JANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/15/2020 JOHN TRIANTAFYLLOS
Roof/Waste drainage to street Cleared 5/15/2020 JOHN TRIANTAFYLLOS
Specific Plan Cleared 7/15/2020 TRACY WILLIAMS
ZI Cleared 7/15/2020 TRACY WILLIAMS
Grading Pre-Inspection Cleared 9/24/2020 SEWADA ZADOORAN MILAGARDI

Contact Information

Contractor Dixie Builders Inc; Lic. No.: 899179-B 20058 VENTURA BLVD #240      WOODLAND HILLS, CA 91364
Engineer Yuzon,, Benigno S; Lic. No.: S3454 25531 PRADO DELAS BELLOTAS      CALABASAS, CA 91302

Inspector Information

JOHN HAYES, (818) 774-4302 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 2/16/2021 Not Ready for Inspection PAUL CHOPP
Underground Mechanical 2/16/2021 Partial Inspection PAUL CHOPP
Footing/Foundation/Slab 3/3/2021 Approved RONALD COWAN
Underground Mechanical 3/3/2021 Approved RONALD COWAN
Wood Frame 5/10/2021 Partial Approval DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 9/29/2021 Partial Approval PETER FOLLING
BUILDING-Rough-Frame 12/3/2021 Partial Approval ROBERT GOLD
Rough-Elec/Plmb/HVAC 12/3/2021 Approved ROBERT GOLD
Deputy Wood Construction 12/7/2021 Conditional Approval JAVIER RAMOS JR
BUILDING-Rough-Frame 12/13/2021 Approved PETER FOLLING
Floor/Roof Diaphrgm/Shear Wall 12/13/2021 Approved PETER FOLLING
Insulation 1/5/2022 Approved JUSTIN HAWLEY
Shower Pan 1/21/2022 Partial Approval JESUS PINEDA
Interior/Exterior Lathing 1/26/2022 Partial Approval JESUS PINEDA
Drywall Nailing 2/3/2022 Approved JESUS PINEDA
Shower Pan 2/3/2022 Approved JESUS PINEDA
Interior/Exterior Lathing 2/10/2022 Approved JAVIER RAMOS JR
ELECTRICAL-Final 12/1/2022 Not Ready for Inspection PETER FOLLING
ELECTRICAL-Final 12/19/2022 Approved PETER FOLLING
Final 12/19/2022 OK to Issue CofO PETER FOLLING
HVAC-Final 12/19/2022 Approved PETER FOLLING
PLUMBING-Final 12/19/2022 Approved PETER FOLLING
SGSOV-Seismic Gas S/O Valve 12/19/2022 SGSOV Approved PETER FOLLING
Smoke Detectors 12/19/2022 Approved PETER FOLLING
ELECTRICAL-Final 12/28/2022 Approved PETER FOLLING
HVAC-Final 12/28/2022 Approved PETER FOLLING
PLUMBING-Final 12/28/2022 Approved PETER FOLLING