3013 N GILROY ST 90039

Certificate Information: 3013 N GILROY ST 90039

Application / Permit
20016-20000-07661
Plan Check / Job No.
B20VN04702
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
CHANGE OF USE FROM WAREHOUSE TO OFFICE.
Permit Issued
Issued on 8/20/2020
Issuing Office
Current Status
CofO Issued on 5/29/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/17/2020 APPLICANT
Disabled Access Plans Picked Up 3/26/2020 APPLICANT
Assigned to Plan Check Engineer 4/2/2020 CHUNG-WEN CHUANG
Corrections Issued 4/16/2020 CHUNG-WEN CHUANG
Quality Review Completed 5/7/2020 KESETE HAREGOT
Applicant returned to address corrections 6/15/2020 CHUNG-WEN CHUANG
Plan Check Approved 7/22/2020 CHUNG-WEN CHUANG
Issued 8/20/2020 APPLICANT
TCO Issued (Expire Date: 12-15-2024) 6/18/2024 ERNESTO CORRAL
TCO Issued (Expire Date: 05-18-2025) 11/19/2024 ERNESTO CORRAL
TCO Issued (Expire Date: 10-25-2025) 4/28/2025 RAFAEL ESPINOZA
TCO Issued (Expire Date: 04-25-2026) 10/27/2025 RAFAEL ESPINOZA
TCO Issued (Expire Date: 10-12-2026) 4/15/2026 ERNESTO CORRAL
CofO in Progress 5/27/2026 SEAN POMISH
Permit Finaled 5/29/2026 RAFAEL ESPINOZA
CofO Issued 5/29/2026 RAFAEL ESPINOZA
Permit Finaled 5/29/2026 RAFAEL ESPINOZA

Permit Application Clearance Information

ZI Cleared 5/13/2020 TERRI OSBORNE
Eng Process Fee Ord 176,300 Cleared 6/1/2020 JUAN ASHTON
Sewer availability Cleared 6/1/2020 JUAN ASHTON
DAS Clearance Cleared 6/18/2020 NORLITO MEDRANO

Contact Information

Architect Mulcahy,, Kevin Patrick; Lic. No.: C31272 3048 N. COOLIDGE AVENUE      LOS ANGELES, CA 90039
Contractor Marcos Construction Inc; Lic. No.: 686859-B P O BOX 65552      LOS ANGELES, CA 90065

Inspector Information

SEAN POMISH, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL CORTES, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Masonry 9/22/2021 Conditional Approval JONATHAN QUACH
Deputy Reinf. Concrete 10/4/2021 Conditional Approval JONATHAN QUACH
Deputy Drilled-In Anchors 12/7/2021 Conditional Approval MARK FERRARI
Deputy Reinf. Concrete 12/7/2021 Partial Approval MARK FERRARI
Deputy Shotcrete 12/7/2021 Conditional Approval MARK FERRARI
Deputy Reinf. Masonry 1/4/2022 Approved MARK FERRARI
Deputy Wood Construction 1/24/2022 Conditional Approval DARRYL ARNOLD
Deputy Wood Construction 3/2/2022 Conditional Approval MARK FERRARI
Deputy Wood Construction 3/7/2022 Conditional Approval MARK FERRARI
Deputy Steel/Welding 3/24/2022 Conditional Approval MARK FERRARI
Deputy Wood Construction 4/4/2022 Conditional Approval MARK FERRARI
Final 6/10/2024 Corrections Issued RONALD JIMENEZ
SGSOV-Seismic Gas S/O Valve 6/10/2024 SGSOV Approved RONALD JIMENEZ
Smoke Detectors 6/10/2024 Approved RONALD JIMENEZ
Special/Order Compliance 11/13/2024 Approved RAFAEL CORTES
Special/Order Compliance 4/15/2025 Approved RAFAEL CORTES
Special/Order Compliance 4/21/2025 Approved RONALD JIMENEZ
Special/Order Compliance 4/22/2025 Approved RONALD JIMENEZ
Special/Order Compliance 9/30/2025 Approved RAFAEL CORTES
Special/Order Compliance 4/1/2026 Partial Approval SEAN POMISH
Final 5/27/2026 OK to Issue CofO SEAN POMISH