11958 1/2 W WAGNER ST 90230
Certificate Information: 11958 1/2 W WAGNER ST 90230
- Application / Permit
- 20016-20000-07481
- Plan Check / Job No.
- B20VN04580
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT 18'-3" X 20'-4" DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER DESIGN
- Permit Issued
- Issued on 3/16/2020
- Issuing Office
- Valley
- Current Status
- Issued on 3/16/2020
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/16/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/16/2020 | RAPHAEL ROSAS |
| Corrections Issued | 3/16/2020 | RAPHAEL ROSAS |
| Plan Check Approved | 3/16/2020 | ALDOUS CHIC |
| Issued | 3/16/2020 | LADBS |
Permit Application Clearance Information
| Address approval | Cleared | 3/16/2020 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 3/16/2020 | GUILLERMO PETRA |
| Roof/Waste drainage to street | Cleared | 3/16/2020 | GUILLERMO PETRA |
| Sewer availability | Cleared | 3/16/2020 | GUILLERMO PETRA |
Contact Information
| Engineer | Lee,, Richard C C; Lic. No.: S1371 | 19558 GAULT ST RESEDA, CA 91335 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Gas Test | 4/17/2020 | Approved | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 4/17/2020 | SGSOV Not Ready | JOHNNY MIRANDA |
| Sewer | 4/17/2020 | Approved | JOHNNY MIRANDA |
| Deputy Drilled-In Anchors | 5/20/2020 | Conditional Approval | DAVID FEILER |
| Excavation/Setback/Form/Re-Bar | 5/20/2020 | Corrections Issued | DAVID FEILER |
| Excavation/Setback/Form/Re-Bar | 5/27/2020 | Approved | DAVID FEILER |
| Footing/Foundation/Slab | 5/27/2020 | Approved | DAVID FEILER |
| BUILDING-Rough-Frame | 6/23/2020 | Not Ready for Inspection | JUAN VALENZUELA |
| ELECTRICAL-Rough | 6/23/2020 | Corrections Issued | JUAN VALENZUELA |
| Green Building Rough | 6/23/2020 | Not Ready for Inspection | JUAN VALENZUELA |
| HVAC-Rough | 6/23/2020 | Not Ready for Inspection | JUAN VALENZUELA |
| PLUMBING-Rough | 6/23/2020 | Corrections Issued | JUAN VALENZUELA |
| ELECTRICAL-Rough | 6/26/2020 | No Access for Inspection | JOHNNY MIRANDA |
| PLUMBING-Rough | 6/26/2020 | No Access for Inspection | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 7/8/2020 | Partial Approval | JUAN VALENZUELA |
| Green Building Rough | 7/8/2020 | Not Ready for Inspection | JUAN VALENZUELA |
| PLUMBING-Rough | 7/8/2020 | Approved | JUAN VALENZUELA |
| ELECTRICAL-Rough | 7/17/2020 | Corrections Issued | ANTHONY MCDOWALL |
| HVAC-Rough | 7/17/2020 | Corrections Issued | ANTHONY MCDOWALL |
| ELECTRICAL-Rough | 7/22/2020 | Partial Approval | ANTHONY MCDOWALL |
| HVAC-Rough | 7/22/2020 | Partial Approval | ANTHONY MCDOWALL |
| Interior/Exterior Lathing | 7/22/2020 | Partial Approval | ANTHONY MCDOWALL |
| BUILDING-Rough-Frame | 7/27/2020 | Approved | ANTHONY MCDOWALL |
| ELECTRICAL-Rough | 7/27/2020 | Approved | ANTHONY MCDOWALL |
| Green Building Rough | 7/27/2020 | Approved | ANTHONY MCDOWALL |
| Insulation | 7/29/2020 | Approved | ANTHONY MCDOWALL |
| Floor/Roof Diaphrgm/Shear Wall | 7/31/2020 | Approved | ANTHONY MCDOWALL |
| Floor/Roof Diaphrgm/Shear Wall | 8/19/2020 | No Access for Inspection | KENNETH NAGLE |
| Excavation/Setback/Form/Re-Bar | 9/3/2020 | Approved | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 10/9/2020 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 10/14/2020 | Partial Approval | JOHNNY MIRANDA |
| Final | 6/29/2021 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Final | 6/29/2021 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 6/29/2021 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 6/29/2021 | Approved | ENRIQUE MIRELES |
| Final | 10/22/2021 | Corrections Issued | ENRIQUE MIRELES |
| Final | 3/15/2023 | Corrections Issued | JESUS RODRIGUEZ |