13301 W HUBBARD ST 91342
Certificate Information: 13301 W HUBBARD ST 91342
- Application / Permit
- 20016-20000-07447
- Plan Check / Job No.
- B20VN04562
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMOVE AND REPLACE INTERIOR BEARING WALLS WITH BEAMS ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 6/17/2020
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 1/11/2023
Permit Application Status History
| Submitted | 3/13/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/2/2020 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 4/8/2020 | SEWADA ZADOORIAN MILAGARDI |
| Quality Review Completed | 4/17/2020 | STEVEN KIM |
| Building Plans Picked Up | 4/24/2020 | APPLICANT |
| Plan Check Approved | 6/5/2020 | SEWADA ZADOORAN MILAGARDI |
| Issued | 6/17/2020 | LADBS |
| Permit Finaled | 1/11/2023 | ARAM AVEDISIAN |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Sayah,, Daniel Hoshyar; Lic. No.: C67905 | 15233 VENTURA BLVD STE 1130 SHERMAN OAKS, CA 91403 |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/4/2020 | Corrections Issued | MISAEL ESPARZA |
| Footing/Foundation/Slab | 8/6/2020 | No Access for Inspection | MISAEL ESPARZA |
| Footing/Foundation/Slab | 8/12/2020 | Partial Inspection | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 6/7/2021 | Not Ready for Inspection | MISAEL ESPARZA |
| ELECTRICAL-Rough | 8/2/2021 | Not Ready for Inspection | MISAEL ESPARZA |
| PLUMBING-Rough | 8/2/2021 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Rough | 8/17/2021 | Partial Approval | MISAEL ESPARZA |
| ELECTRICAL-Rough | 8/20/2021 | Partial Approval | MISAEL ESPARZA |
| PLUMBING-Rough | 8/20/2021 | Approved | MISAEL ESPARZA |
| Insulation | 9/1/2021 | Corrections Issued | MISAEL ESPARZA |
| Rough-Elec/Plmb/HVAC | 9/1/2021 | Approved | MISAEL ESPARZA |
| Smoke Detectors | 9/1/2021 | Not Ready for Inspection | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 9/14/2021 | Approved | JOHN HAYES |
| Shower Pan | 9/14/2021 | Approved | JOHN HAYES |
| Drywall Nailing | 10/4/2021 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 10/4/2021 | Approved | JOHN HAYES |
| Final | 1/4/2023 | Corrections Issued | ARAM AVEDISIAN |
| Smoke Detectors | 1/4/2023 | Approved | ARAM AVEDISIAN |
| Final | 1/11/2023 | Permit Finaled | ARAM AVEDISIAN |