13301 W HUBBARD ST 91342

Certificate Information: 13301 W HUBBARD ST 91342

Application / Permit
20016-20000-07447
Plan Check / Job No.
B20VN04562
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMOVE AND REPLACE INTERIOR BEARING WALLS WITH BEAMS ALL WORK PER ENGINEERING
Permit Issued
Issued on 6/17/2020
Issuing Office
Valley
Current Status
Permit Finaled on 1/11/2023

Permit Application Status History

Submitted 3/13/2020 APPLICANT
Assigned to Plan Check Engineer 4/2/2020 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 4/8/2020 SEWADA ZADOORIAN MILAGARDI
Quality Review Completed 4/17/2020 STEVEN KIM
Building Plans Picked Up 4/24/2020 APPLICANT
Plan Check Approved 6/5/2020 SEWADA ZADOORAN MILAGARDI
Issued 6/17/2020 LADBS
Permit Finaled 1/11/2023 ARAM AVEDISIAN

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Owner-Builder       ,
Engineer Sayah,, Daniel Hoshyar; Lic. No.: C67905 15233 VENTURA BLVD STE 1130      SHERMAN OAKS, CA 91403

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/4/2020 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 8/6/2020 No Access for Inspection MISAEL ESPARZA
Footing/Foundation/Slab 8/12/2020 Partial Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 6/7/2021 Not Ready for Inspection MISAEL ESPARZA
ELECTRICAL-Rough 8/2/2021 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Rough 8/2/2021 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 8/17/2021 Partial Approval MISAEL ESPARZA
ELECTRICAL-Rough 8/20/2021 Partial Approval MISAEL ESPARZA
PLUMBING-Rough 8/20/2021 Approved MISAEL ESPARZA
Insulation 9/1/2021 Corrections Issued MISAEL ESPARZA
Rough-Elec/Plmb/HVAC 9/1/2021 Approved MISAEL ESPARZA
Smoke Detectors 9/1/2021 Not Ready for Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 9/14/2021 Approved JOHN HAYES
Shower Pan 9/14/2021 Approved JOHN HAYES
Drywall Nailing 10/4/2021 Approved JOHN HAYES
Interior/Exterior Lathing 10/4/2021 Approved JOHN HAYES
Final 1/4/2023 Corrections Issued ARAM AVEDISIAN
Smoke Detectors 1/4/2023 Approved ARAM AVEDISIAN
Final 1/11/2023 Permit Finaled ARAM AVEDISIAN