18041 W HATTERAS ST 91316

Certificate Information: 18041 W HATTERAS ST 91316

Application / Permit
20016-20000-07334
Plan Check / Job No.
B20VN04490
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT DETACHED GARAGE TO ACCESSORY DWELLING UNIT.
Permit Issued
Issued on 8/30/2020
Issuing Office
Current Status
CofO Issued on 7/7/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/13/2020 APPLICANT
Assigned to Plan Check Engineer 3/13/2020 ALDOUS CHIC
Corrections Issued 3/13/2020 ALDOUS CHIC
Plan Check Approved 7/20/2020 FARSHAD ALIMOHAMADI
Issued 8/30/2020 APPLICANT
CofO in Progress 7/6/2021 STEVEN BACK
Permit Finaled 7/7/2021 JOHN JANSON
CofO Issued 7/7/2021 JOHN JANSON
Permit Finaled 7/7/2021 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 3/13/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 3/13/2020 JOHN TRIANTAFYLLOS
Construction near power lines Cleared 6/16/2020 WALTER RAMIREZ
Eng Process Fee Ord 176,300 Cleared 6/26/2020 JOHN TRIANTAFYLLOS
Permit Cleared 6/26/2020 JOHN TRIANTAFYLLOS

Contact Information

Contractor Ts Construction & Design Inc; Lic. No.: 1064916-B 18375 VENTURA BLVD #375      TARZANA, CA 91356

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/8/2021 Approved STEVEN BACK
Footing/Foundation/Slab 2/19/2021 Approved STEVEN BACK
PLUMBING-Rough 2/19/2021 Partial Approval STEVEN BACK
BUILDING-Rough-Frame 2/22/2021 Not Ready for Inspection STEVEN BACK
ELECTRICAL-Rough 2/22/2021 Approved STEVEN BACK
Green Building Rough 2/22/2021 Not Ready for Inspection STEVEN BACK
HVAC-Rough 2/22/2021 Not Ready for Inspection STEVEN BACK
Sewer 2/22/2021 Approved STEVEN BACK
Insulation 2/24/2021 Partial Approval STEVEN BACK
PLUMBING-Rough 2/24/2021 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 2/25/2021 Corrections Issued STEVEN BACK
Insulation 2/25/2021 Not Ready for Inspection STEVEN BACK
Interior/Exterior Lathing 2/25/2021 Not Ready for Inspection STEVEN BACK
PLUMBING-Rough 2/25/2021 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 3/2/2021 Partial Approval STEVEN BACK
Insulation 3/2/2021 Partial Approval STEVEN BACK
BUILDING-Rough-Frame 3/4/2021 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 3/4/2021 Approved STEVEN BACK
Green Building Rough 3/4/2021 Approved STEVEN BACK
HVAC-Rough 3/4/2021 Approved STEVEN BACK
Insulation 3/4/2021 Approved STEVEN BACK
Drywall Nailing 3/8/2021 Approved STEVEN BACK
Interior/Exterior Lathing 3/8/2021 Approved STEVEN BACK
ELECTRICAL-Final 3/26/2021 Not Ready for Inspection STEVEN BACK
Final 3/26/2021 Not Ready for Inspection STEVEN BACK
Green Building Final 3/26/2021 Not Ready for Inspection STEVEN BACK
HVAC-Final 3/26/2021 Not Ready for Inspection STEVEN BACK
PLUMBING-Final 3/26/2021 Not Ready for Inspection STEVEN BACK
SGSOV-Seismic Gas S/O Valve 3/26/2021 SGSOV Not Ready STEVEN BACK
Smoke Detectors 3/26/2021 Not Ready for Inspection STEVEN BACK
Final 6/15/2021 Corrections Issued STEVEN BACK
Green Building Final 6/15/2021 No Access for Inspection STEVEN BACK
SGSOV-Seismic Gas S/O Valve 6/15/2021 SGSOV Not Ready STEVEN BACK
Smoke Detectors 6/15/2021 No Access for Inspection STEVEN BACK
ELECTRICAL-Final 7/6/2021 Approved STEVEN BACK
Final 7/6/2021 OK to Issue CofO STEVEN BACK
Green Building Final 7/6/2021 Approved STEVEN BACK
HVAC-Final 7/6/2021 Approved STEVEN BACK
PLUMBING-Final 7/6/2021 Approved STEVEN BACK
SGSOV-Seismic Gas S/O Valve 7/6/2021 SGSOV Approved STEVEN BACK
Smoke Detectors 7/6/2021 Approved STEVEN BACK