6728 N JUMILLA AVE 91306
Certificate Information: 6728 N JUMILLA AVE 91306
- Application / Permit
- 20016-20000-07194
- Plan Check / Job No.
- B20VN04403
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT 18'x19'10" DETACHED GARAGE TO ACCESSORY DWELLING UNIT.
- Permit Issued
- Issued on 3/13/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/20/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/12/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/12/2020 | ALDOUS CHIC |
| Corrections Issued | 3/12/2020 | ALDOUS CHIC |
| Plan Check Approved | 3/12/2020 | LUIS RINCON |
| Issued | 3/13/2020 | LADBS |
| CofO in Progress | 7/17/2020 | HENRY KIM |
| CofO Issued | 7/20/2020 | JOHN JANSON |
| Permit Finaled | 7/20/2020 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 3/12/2020 | JOHN LIN |
| Eng Process Fee Ord 176,300 | Cleared | 3/12/2020 | JOHN LIN |
| Sewer availability | Cleared | 3/12/2020 | JOHN LIN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/20/2020 | Conditional Approval | HENRY KIM |
| Deputy Drilled-In Anchors | 3/23/2020 | Conditional Approval | HENRY KIM |
| BUILDING-Rough-Frame | 4/17/2020 | Corrections Issued | HENRY KIM |
| Footing/Foundation/Slab | 4/17/2020 | Approved | HENRY KIM |
| PLUMBING-Rough | 4/17/2020 | Partial Inspection | HENRY KIM |
| Special/Order Compliance | 4/17/2020 | Corrections Issued | HENRY KIM |
| Underground Mechanical | 4/17/2020 | Corrections Issued | HENRY KIM |
| BUILDING-Rough-Frame | 4/28/2020 | Not Ready for Inspection | HENRY KIM |
| ELECTRICAL-Rough | 4/28/2020 | Approved | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 4/28/2020 | Not Ready for Inspection | HENRY KIM |
| Green Building Rough | 4/28/2020 | Not Ready for Inspection | HENRY KIM |
| Special/Order Compliance | 4/28/2020 | Approved | HENRY KIM |
| Underground Mechanical | 4/28/2020 | Partial Approval | HENRY KIM |
| BUILDING-Rough-Frame | 4/30/2020 | Corrections Issued | HENRY KIM |
| PLUMBING-Rough | 4/30/2020 | Approved | HENRY KIM |
| BUILDING-Rough-Frame | 5/1/2020 | Partial Approval | HENRY KIM |
| BUILDING-Rough-Frame | 5/6/2020 | Not Ready for Inspection | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 5/6/2020 | Corrections Issued | HENRY KIM |
| Insulation | 5/6/2020 | Approved | HENRY KIM |
| BUILDING-Rough-Frame | 5/15/2020 | Approved | HENRY KIM |
| Drywall Nailing | 5/15/2020 | Approved | HENRY KIM |
| ELECTRICAL-Final | 5/15/2020 | Corrections Issued | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 5/15/2020 | Approved | HENRY KIM |
| Green Building Rough | 5/15/2020 | Approved | HENRY KIM |
| Interior/Exterior Lathing | 5/15/2020 | Approved | HENRY KIM |
| Underground Mechanical | 5/15/2020 | Approved | HENRY KIM |
| ELECTRICAL-Final | 6/29/2020 | Corrections Issued | HENRY KIM |
| Final | 6/29/2020 | Corrections Issued | HENRY KIM |
| Green Building Final | 6/29/2020 | Approved | HENRY KIM |
| HVAC-Final | 6/29/2020 | Corrections Issued | HENRY KIM |
| PLUMBING-Final | 6/29/2020 | Corrections Issued | HENRY KIM |
| SGSOV-Seismic Gas S/O Valve | 6/29/2020 | SGSOV Approved | HENRY KIM |
| Smoke Detectors | 6/29/2020 | Approved | HENRY KIM |
| ELECTRICAL-Final | 7/13/2020 | Not Ready for Inspection | HENRY KIM |
| Final | 7/13/2020 | Corrections Issued | HENRY KIM |
| HVAC-Final | 7/13/2020 | Approved | HENRY KIM |
| PLUMBING-Final | 7/13/2020 | Approved | HENRY KIM |
| ELECTRICAL-Final | 7/17/2020 | Approved | HENRY KIM |
| Final | 7/17/2020 | OK to Issue CofO | HENRY KIM |