2623 S GREENFIELD AVE 90064

Certificate Information: 2623 S GREENFIELD AVE 90064

Application / Permit
20016-20000-07175
Plan Check / Job No.
B20VN04391
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISITNG GARAGE/ REC ROOM/ STORAGE INTO ACCESSORY DWELLING UNIT (CONVERSION OF ACCESSORY BUILDING PER STATE LAW, CA Govt. Code 65852.2(e)(1)(A) )
Permit Issued
Issued on 5/28/2021
Issuing Office
Current Status
CofO Issued on 3/17/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/11/2020 APPLICANT
Assigned to Plan Check Engineer 4/9/2020 AUNG SOE
Corrections Issued 4/14/2020 AUNG SOE
Green Plans Picked Up 4/17/2020 APPLICANT
Quality Review Completed 5/7/2020 QUAN NGHIEM
Building Plans Picked Up 5/22/2020 APPLICANT
Applicant returned to address corrections 12/23/2020 AUNG SOE
Plan Check Approved 3/24/2021 AUNG SOE
Issued 5/28/2021 APPLICANT
CofO in Progress 3/4/2022 JOHNNY MIRANDA
Permit Finaled 3/17/2022 DANIEL ORRANTE
CofO Issued 3/17/2022 DANIEL ORRANTE
Permit Finaled 3/17/2022 DANIEL ORRANTE

Permit Application Clearance Information

Specific Plan Cleared 7/29/2020 ANACANY HURTADO
Green Code Cleared 10/14/2020 AARON COSTA
Address approval Cleared 10/30/2020 SAUL GARCIA
Sewer availability Cleared 10/30/2020 SAUL GARCIA
Eng Process Fee Ord 176,300 Cleared 3/9/2021 SAUL GARCIA
Hydrant and Access approval Cleared 3/9/2021 MATTHEW CRAIG
Specific Plan Cleared 3/9/2021 EDUARDO HERMOSO

Contact Information

Contractor Owner-Builder       ,
Engineer Wu,, Harold Ping-Hung; Lic. No.: C35693 1168 SAN GABRIEL BLVD NO N      ROSEMEAD, CA 91770

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/9/2021 Corrections Issued KEVIN SARGSYAN
Pre-Inspection 7/6/2021 Partial Inspection KEVIN SARGSYAN
BUILDING-Rough-Frame 8/4/2021 Not Ready for Inspection KEVIN SARGSYAN
Excavation/Setback/Form/Re-Bar 8/4/2021 Not Ready for Inspection KEVIN SARGSYAN
Footing/Foundation/Slab 8/4/2021 Not Ready for Inspection KEVIN SARGSYAN
Green Building Rough 8/4/2021 Not Ready for Inspection KEVIN SARGSYAN
Wood Frame 8/4/2021 Not Ready for Inspection KEVIN SARGSYAN
Footing/Foundation/Slab 8/6/2021 Corrections Issued KEVIN SARGSYAN
Footing/Foundation/Slab 8/10/2021 Partial Approval PIERRE VEGA
PLUMBING-Rough 8/19/2021 Not Ready for Inspection OGANES TARAKHCHYAN
Sewer 8/19/2021 Not Ready for Inspection OGANES TARAKHCHYAN
Wood Frame 8/19/2021 Not Ready for Inspection OGANES TARAKHCHYAN
PLUMBING-Rough 9/1/2021 Approved EVAN COOPER
Sewer 9/1/2021 Approved EVAN COOPER
BUILDING-Rough-Frame 9/20/2021 Corrections Issued EVAN COOPER
ELECTRICAL-Rough 9/20/2021 Corrections Issued EVAN COOPER
Green Building Rough 9/20/2021 Not Ready for Inspection EVAN COOPER
HVAC-Rough 9/20/2021 Corrections Issued EVAN COOPER
Shower Pan 9/20/2021 Approved EVAN COOPER
Wood Frame 9/20/2021 Not Ready for Inspection EVAN COOPER
Insulation 10/1/2021 Not Ready for Inspection EVAN COOPER
Wood Frame 10/1/2021 Corrections Issued EVAN COOPER
BUILDING-Rough-Frame 10/27/2021 Partial Approval KENNETH NAGLE
Green Building Rough 10/27/2021 Not Ready for Inspection KENNETH NAGLE
BUILDING-Rough-Frame 11/1/2021 Approved KENNETH NAGLE
Green Building Rough 11/1/2021 Approved KENNETH NAGLE
Insulation 11/1/2021 Approved KENNETH NAGLE
Interior/Exterior Lathing 11/1/2021 Approved KENNETH NAGLE
Rough-Elec/Plmb/HVAC 11/1/2021 Approved KENNETH NAGLE
Drywall Nailing 11/9/2021 Approved JOHNNY MIRANDA
Final 2/15/2022 Corrections Issued JOHNNY MIRANDA
Footing/Foundation/Slab 2/15/2022 Approved JOHNNY MIRANDA
Green Building Final 2/15/2022 Approved JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 2/15/2022 SGSOV Not Ready JOHNNY MIRANDA
Smoke Detectors 2/15/2022 Approved JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 2/28/2022 SGSOV Approved OGANES TARAKHCHYAN
Final 3/1/2022 OK to Issue CofO JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 3/1/2022 SGSOV Approved JOHNNY MIRANDA