6144-6146 N FALLBROOK AVE 91367
Certificate Information: 6144-6146 N FALLBROOK AVE 91367
- Application / Permit
- 20016-20000-07143
- Plan Check / Job No.
- B20VN04355
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) 19'2" X 19'6" ATTACHED GARAGE AND (E) 18'6" X 20' PORTION OF SFD TO ACCESSORY DWELLING UNIT (683 SQ.FT.) ATTACHED TO (E) SFD , ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 4/28/2020
- Issuing Office
- Current Status
- CofO Issued on 9/9/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/11/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/12/2020 | RARES BODEA |
| Corrections Issued | 3/12/2020 | RARES BODEA |
| Building Plans Picked Up | 3/16/2020 | APPLICANT |
| Plan Check Approved | 4/28/2020 | RARES BODEA |
| Issued | 4/28/2020 | APPLICANT |
| CofO in Progress | 8/31/2020 | TROY SANDERS |
| CofO Issued | 9/9/2020 | JOHN JANSON |
| Permit Finaled | 9/9/2020 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 4/7/2020 | GABRIEL ROBLES |
| Sewer availability | Cleared | 4/7/2020 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 4/15/2020 | LEE GUILBEAUX |
| Grading Pre-Inspection | Cleared | 4/20/2020 | BRIAN MILLER |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Askarian,, Soroosh Namaghi; Lic. No.: C83413 | 22287 MULHOLLAND HWY 163 CALABASAS, CA 91302 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 5/19/2020 | Corrections Issued | JOHN KIDWELL |
| Green Building Rough | 5/19/2020 | Not Ready for Inspection | JOHN KIDWELL |
| BUILDING-Rough-Frame | 7/15/2020 | Not Ready for Inspection | TROY SANDERS |
| Green Building Rough | 7/15/2020 | Not Ready for Inspection | TROY SANDERS |
| BUILDING-Rough-Frame | 7/31/2020 | Approved | TROY SANDERS |
| ELECTRICAL-Rough | 7/31/2020 | Approved | TROY SANDERS |
| Footing/Foundation/Slab | 7/31/2020 | Approved | TROY SANDERS |
| Green Building Rough | 7/31/2020 | Approved | TROY SANDERS |
| HVAC-Rough | 7/31/2020 | Approved | TROY SANDERS |
| PLUMBING-Rough | 7/31/2020 | Approved | TROY SANDERS |
| Drywall Nailing | 8/12/2020 | Approved | TROY SANDERS |
| ELECTRICAL-Final | 8/21/2020 | Approved | TROY SANDERS |
| Final | 8/21/2020 | Corrections Issued | TROY SANDERS |
| Green Building Final | 8/21/2020 | Corrections Issued | TROY SANDERS |
| HVAC-Final | 8/21/2020 | Corrections Issued | TROY SANDERS |
| PLUMBING-Final | 8/21/2020 | Approved | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 8/21/2020 | SGSOV Approved | TROY SANDERS |
| Smoke Detectors | 8/21/2020 | Corrections Issued | TROY SANDERS |
| Final | 8/31/2020 | OK to Issue CofO | TROY SANDERS |
| Green Building Final | 8/31/2020 | Approved | TROY SANDERS |
| HVAC-Final | 8/31/2020 | Approved | TROY SANDERS |
| Smoke Detectors | 8/31/2020 | Approved | TROY SANDERS |