6144-6146 N FALLBROOK AVE 91367

Certificate Information: 6144-6146 N FALLBROOK AVE 91367

Application / Permit
20016-20000-07143
Plan Check / Job No.
B20VN04355
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) 19'2" X 19'6" ATTACHED GARAGE AND (E) 18'6" X 20' PORTION OF SFD TO ACCESSORY DWELLING UNIT (683 SQ.FT.) ATTACHED TO (E) SFD , ALL WORK PER ENGINEERING
Permit Issued
Issued on 4/28/2020
Issuing Office
Current Status
CofO Issued on 9/9/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/11/2020 APPLICANT
Assigned to Plan Check Engineer 3/12/2020 RARES BODEA
Corrections Issued 3/12/2020 RARES BODEA
Building Plans Picked Up 3/16/2020 APPLICANT
Plan Check Approved 4/28/2020 RARES BODEA
Issued 4/28/2020 APPLICANT
CofO in Progress 8/31/2020 TROY SANDERS
CofO Issued 9/9/2020 JOHN JANSON
Permit Finaled 9/9/2020 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 4/7/2020 GABRIEL ROBLES
Sewer availability Cleared 4/7/2020 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 4/15/2020 LEE GUILBEAUX
Grading Pre-Inspection Cleared 4/20/2020 BRIAN MILLER

Contact Information

Contractor Owner-Builder       ,
Engineer Askarian,, Soroosh Namaghi; Lic. No.: C83413 22287 MULHOLLAND HWY 163      CALABASAS, CA 91302

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 5/19/2020 Corrections Issued JOHN KIDWELL
Green Building Rough 5/19/2020 Not Ready for Inspection JOHN KIDWELL
BUILDING-Rough-Frame 7/15/2020 Not Ready for Inspection TROY SANDERS
Green Building Rough 7/15/2020 Not Ready for Inspection TROY SANDERS
BUILDING-Rough-Frame 7/31/2020 Approved TROY SANDERS
ELECTRICAL-Rough 7/31/2020 Approved TROY SANDERS
Footing/Foundation/Slab 7/31/2020 Approved TROY SANDERS
Green Building Rough 7/31/2020 Approved TROY SANDERS
HVAC-Rough 7/31/2020 Approved TROY SANDERS
PLUMBING-Rough 7/31/2020 Approved TROY SANDERS
Drywall Nailing 8/12/2020 Approved TROY SANDERS
ELECTRICAL-Final 8/21/2020 Approved TROY SANDERS
Final 8/21/2020 Corrections Issued TROY SANDERS
Green Building Final 8/21/2020 Corrections Issued TROY SANDERS
HVAC-Final 8/21/2020 Corrections Issued TROY SANDERS
PLUMBING-Final 8/21/2020 Approved TROY SANDERS
SGSOV-Seismic Gas S/O Valve 8/21/2020 SGSOV Approved TROY SANDERS
Smoke Detectors 8/21/2020 Corrections Issued TROY SANDERS
Final 8/31/2020 OK to Issue CofO TROY SANDERS
Green Building Final 8/31/2020 Approved TROY SANDERS
HVAC-Final 8/31/2020 Approved TROY SANDERS
Smoke Detectors 8/31/2020 Approved TROY SANDERS