5809 N CORBIN AVE 91356

Certificate Information: 5809 N CORBIN AVE 91356

Application / Permit
20016-20000-07118
Plan Check / Job No.
B20VN04339
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 18'-0" X 60'-0" GARAGE/STORAGE BUILDING TO (N) ACCESSORY DWELLING UNIT. ALL WORK PER WFPP.
Permit Issued
Issued on 5/27/2020
Issuing Office
Current Status
CofO Issued on 7/28/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/11/2020 APPLICANT
Assigned to Plan Check Engineer 3/17/2020 JENNIFER LEE
Plan Check Approved 3/17/2020 JENNIFER LEE
Issued 5/27/2020 APPLICANT
Building Plans Picked Up 5/28/2020 APPLICANT
CofO in Progress 7/27/2021 STEVEN BACK
Permit Finaled 7/28/2021 JOHN JANSON
CofO Issued 7/28/2021 JOHN JANSON
Permit Finaled 7/28/2021 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 3/16/2020 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 3/16/2020 GUILLERMO PETRA
Sewer availability Cleared 3/16/2020 GUILLERMO PETRA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/10/2020 Approved STEVEN BACK
PLUMBING-Rough 7/28/2020 Corrections Issued STEVEN BACK
Underground Mechanical 7/28/2020 Approved STEVEN BACK
Footing/Foundation/Slab 8/11/2020 Approved STEVEN BACK
PLUMBING-Rough 8/11/2020 Partial Approval STEVEN BACK
BUILDING-Rough-Frame 9/9/2020 Partial Approval STEVEN BACK
ELECTRICAL-Rough 9/9/2020 Approved STEVEN BACK
Gas Test 9/9/2020 Partial Approval STEVEN BACK
Green Building Rough 9/9/2020 Approved STEVEN BACK
HVAC-Rough 9/9/2020 Approved STEVEN BACK
MERV13>=Rough 9/9/2020 Approved STEVEN BACK
PLUMBING-Rough 9/9/2020 Approved STEVEN BACK
BUILDING-Rough-Frame 12/30/2020 Approved JOSEPH SAGEN
Insulation 12/30/2020 Approved JOSEPH SAGEN
Drywall Nailing 1/6/2021 Approved VINCENT HANLEY
Interior/Exterior Lathing 1/28/2021 Partial Approval CHRISTOPHER DELLEFIELD
Shower Pan 1/28/2021 Approved CHRISTOPHER DELLEFIELD
Gas Test 2/26/2021 Approved STEVEN BACK
Final 6/28/2021 Corrections Issued STEVEN BACK
Green Building Final 6/28/2021 Approved STEVEN BACK
MERV13>=Final 6/28/2021 Approved STEVEN BACK
SGSOV-Seismic Gas S/O Valve 6/28/2021 SGSOV Approved STEVEN BACK
Smoke Detectors 6/28/2021 Approved STEVEN BACK
Special/Order Compliance 6/28/2021 Partial Inspection RYAN SALAZAR
Special/Order Compliance 6/28/2021 Partial Inspection SHAVONNE ESPINOZA
Final 7/19/2021 Corrections Issued STEVEN BACK
Final 7/27/2021 OK to Issue CofO STEVEN BACK