20107 W HAYNES ST 91306

Certificate Information: 20107 W HAYNES ST 91306

Application / Permit
20016-20000-07102
Plan Check / Job No.
B20VN04326
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DET. GARAGE/REC ROOM TO ACCESSORY DWELLING UNIT
Permit Issued
Issued on 8/28/2020
Issuing Office
Current Status
CofO Issued on 1/15/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/11/2020 APPLICANT
Green Plans Picked Up 3/25/2020 APPLICANT
Assigned to Plan Check Engineer 4/2/2020 SEAN SHAHMIRI
Corrections Issued 4/6/2020 SEAN SHAHMIRI
Quality Review Completed 4/20/2020 OMID HEDAYAT
Building Plans Picked Up 4/23/2020 APPLICANT
Plan Check Approved 8/4/2020 SEAN SHAHMIRI
Applicant returned to address corrections 8/11/2020 SEAN SHAHMIRI
Issued 8/28/2020 APPLICANT
CofO in Progress 1/14/2021 HENRY KIM
Permit Finaled 1/15/2021 JOHN JANSON
CofO Issued 1/15/2021 JOHN JANSON
Permit Finaled 1/15/2021 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 4/24/2020 ADRIAN CASTRO
Sewer availability Cleared 4/24/2020 ADRIAN CASTRO
ZI Cleared 4/27/2020 MIGUEL GAMBOA
Eng Process Fee Ord 176,300 Cleared 4/28/2020 ADRIAN CASTRO
Green Code Cleared 4/29/2020 AARON COSTA
Construction near power lines Cleared 7/20/2020 RIDWAN HARDY

Contact Information

Contractor Hillstar Construction Inc; Lic. No.: 972213-B 22647 VENTURA BLVD #173      WOODLAND HILLS, CA 91367
Engineer Hajdari,, Gentjan; Lic. No.: C88031 157 S LOS ROBLES AVE 12      PASADENA, CA 91101

Inspector Information

DAVID FASTIGGI, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI
ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/3/2020 Approved HENRY KIM
Footing/Foundation/Slab 9/14/2020 Approved HENRY KIM
PLUMBING-Rough 9/14/2020 Partial Approval HENRY KIM
BUILDING-Rough-Frame 10/2/2020 Not Ready for Inspection HENRY KIM
ELECTRICAL-Rough 10/2/2020 Not Ready for Inspection HENRY KIM
HVAC-Rough 10/2/2020 Not Ready for Inspection HENRY KIM
PLUMBING-Rough 10/2/2020 Corrections Issued HENRY KIM
BUILDING-Rough-Frame 10/7/2020 Corrections Issued HENRY KIM
PLUMBING-Rough 10/7/2020 Corrections Issued HENRY KIM
BUILDING-Rough-Frame 10/13/2020 Partial Approval HENRY KIM
ELECTRICAL-Rough 10/13/2020 Approved HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 10/13/2020 Approved HENRY KIM
Gas Test 10/13/2020 Partial Approval HENRY KIM
PLUMBING-Rough 10/13/2020 Approved HENRY KIM
Underground Mechanical 10/13/2020 Approved HENRY KIM
BUILDING-Rough-Frame 10/16/2020 Approved HENRY KIM
Green Building Rough 10/16/2020 Approved HENRY KIM
HVAC-Rough 10/16/2020 Approved HENRY KIM
Insulation 10/16/2020 Approved HENRY KIM
Interior/Exterior Lathing 10/20/2020 Approved HENRY KIM
Drywall Nailing 10/26/2020 Approved HENRY KIM
ELECTRICAL-Final 12/3/2020 Corrections Issued HENRY KIM
Final 12/3/2020 Corrections Issued HENRY KIM
Green Building Final 12/3/2020 Approved HENRY KIM
HVAC-Final 12/3/2020 Corrections Issued HENRY KIM
PLUMBING-Final 12/3/2020 Corrections Issued HENRY KIM
SGSOV-Seismic Gas S/O Valve 12/3/2020 SGSOV Approved HENRY KIM
Smoke Detectors 12/3/2020 Approved HENRY KIM
ELECTRICAL-Final 12/15/2020 No Access for Inspection HENRY KIM
Final 12/15/2020 No Access for Inspection HENRY KIM
HVAC-Final 12/15/2020 No Access for Inspection HENRY KIM
PLUMBING-Final 12/15/2020 No Access for Inspection HENRY KIM
ELECTRICAL-Final 1/14/2021 Approved HENRY KIM
Final 1/14/2021 OK to Issue CofO HENRY KIM
HVAC-Final 1/14/2021 Approved HENRY KIM
PLUMBING-Final 1/14/2021 Approved HENRY KIM