18628-18630 W LEMAY ST 91335
Certificate Information: 18628-18630 W LEMAY ST 91335
- Application / Permit
- 20016-20000-07009
- Plan Check / Job No.
- B20VN04277
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) ATTACHED GARAGE INTO ACCESSORY DWELLING UNIT PER ENGR DESIGN
- Permit Issued
- Issued on 12/29/2020
- Issuing Office
- Current Status
- CofO Issued on 7/12/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/10/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/11/2020 | HAYATO TSUCHIYA |
| Corrections Issued | 3/13/2020 | HAYATO TSUCHIYA |
| Building Plans Picked Up | 3/16/2020 | APPLICANT |
| Applicant returned to address corrections | 6/9/2020 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 11/18/2020 | HAYATO TSUCHIYA |
| Plan Check Approved | 12/15/2020 | HAYATO TSUCHIYA |
| Issued | 12/29/2020 | APPLICANT |
| CofO in Progress | 7/8/2021 | VINCENT HANLEY |
| Permit Finaled | 7/12/2021 | MICHAEL SMITH |
| CofO Issued | 7/12/2021 | MICHAEL SMITH |
| Permit Finaled | 7/12/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 6/5/2020 | GUILLERMO PETRA |
| Sewer availability | Cleared | 6/5/2020 | GUILLERMO PETRA |
| ZI | Cleared | 10/27/2020 | LAUREN PADICK |
| Eng Process Fee Ord 176,300 | Cleared | 10/30/2020 | GUILLERMO PETRA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Shagirian,, Ashot; Lic. No.: C79415 | 11337 RUNNYMEDE ST SUN VALLEY, CA 91352 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/31/2020 | Approved | VINCENT HANLEY |
| Underground Mechanical | 1/11/2021 | Partial Approval | VINCENT HANLEY |
| Footing/Foundation/Slab | 1/14/2021 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 2/8/2021 | Partial Approval | VINCENT HANLEY |
| ELECTRICAL-Rough | 2/8/2021 | Approved | VINCENT HANLEY |
| HVAC-Rough | 2/8/2021 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 2/8/2021 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 3/9/2021 | Partial Approval | VINCENT HANLEY |
| Green Building Rough | 3/9/2021 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 4/9/2021 | Partial Approval | VINCENT HANLEY |
| Green Building Rough | 4/9/2021 | Approved | VINCENT HANLEY |
| Insulation | 4/9/2021 | Approved | VINCENT HANLEY |
| Drywall Nailing | 4/21/2021 | Approved | SEAN WIRCH |
| Shower Pan | 4/21/2021 | Approved | SEAN WIRCH |
| Drywall Nailing | 4/22/2021 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 4/22/2021 | Partial Approval | VINCENT HANLEY |
| Shower Pan | 4/22/2021 | Approved | VINCENT HANLEY |
| Drywall Nailing | 4/23/2021 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 4/23/2021 | Approved | VINCENT HANLEY |
| Gas Test | 5/6/2021 | No Access for Inspection | VINCENT HANLEY |
| BUILDING-Rough-Frame | 6/28/2021 | Partial Approval | VINCENT HANLEY |
| FLOOD-Proofing Certificate | 6/28/2021 | Not Ready for Inspection | VINCENT HANLEY |
| Final | 6/28/2021 | Corrections Issued | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 6/28/2021 | SGSOV Approved | VINCENT HANLEY |
| Smoke Detectors | 6/28/2021 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 7/6/2021 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 7/6/2021 | Approved | VINCENT HANLEY |
| FLOOD-Proofing Certificate | 7/6/2021 | Not Ready for Inspection | VINCENT HANLEY |
| Final | 7/6/2021 | OK to Issue CofO | VINCENT HANLEY |
| Gas Test | 7/6/2021 | Approved | VINCENT HANLEY |
| HVAC-Final | 7/6/2021 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 7/6/2021 | Approved | VINCENT HANLEY |