4643 N VESPER AVE 91403

Certificate Information: 4643 N VESPER AVE 91403

Application / Permit
20016-20000-06527
Plan Check / Job No.
B20VN03930
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 16' X 23'-6" IRREGULAR SHAPED DETACHED GARAGE INTO ACCESSORY DWELLING UNIT
Permit Issued
Issued on 9/2/2020
Issuing Office
Valley
Current Status
CofO Issued on 6/22/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/4/2020 APPLICANT
Assigned to Plan Check Engineer 3/6/2020 RAPHAEL ROSAS
Corrections Issued 3/8/2020 RAPHAEL ROSAS
Building Plans Picked Up 7/14/2020 APPLICANT
Plan Check Approved 8/17/2020 RAPHAEL ROSAS
Issued 9/2/2020 APPLICANT
CofO in Progress 6/8/2021 DANIEL ORRANTE
Permit Finaled 6/22/2021 DANIEL ORRANTE
CofO Issued 6/22/2021 DANIEL ORRANTE
Permit Finaled 6/22/2021 DANIEL ORRANTE

Permit Application Clearance Information

Construction near power lines Cleared 7/12/2020 RIDWAN HARDY
Address approval Cleared 8/3/2020 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 8/3/2020 GABRIEL ROBLES
Roof/Waste drainage to street Cleared 8/3/2020 GABRIEL ROBLES
Sewer availability Cleared 8/3/2020 GABRIEL ROBLES

Contact Information

Architect Chiedu, Chijindu; Lic. No.: C33595       ,
Contractor Kearney Joe Construction; Lic. No.: 612030-B 15127 DEL GADO DRIVE      SHERMAN OAKS, CA 91403

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/25/2020 Corrections Issued CHARLES POWELL
BUILDING-Rough-Frame 10/16/2020 Corrections Issued CHARLES POWELL
ELECTRICAL-Rough 10/16/2020 Not Ready for Inspection CHARLES POWELL
Green Building Rough 10/16/2020 Corrections Issued CHARLES POWELL
MERV13>=Rough 10/16/2020 Not Ready for Inspection CHARLES POWELL
Footing/Foundation/Slab 10/29/2020 Partial Approval CHARLES POWELL
Floor/Roof Diaphrgm/Shear Wall 11/6/2020 Approved DANIEL DREW
Footing/Foundation/Slab 11/6/2020 Approved DANIEL DREW
Interior/Exterior Lathing 11/13/2020 Approved CHARLES POWELL
BUILDING-Rough-Frame 11/17/2020 Approved CHARLES POWELL
ELECTRICAL-Rough 11/17/2020 Approved CHARLES POWELL
Green Building Rough 11/17/2020 Approved CHARLES POWELL
Insulation 11/17/2020 Approved CHARLES POWELL
MERV13>=Rough 11/17/2020 Approved CHARLES POWELL
Drywall Nailing 11/25/2020 Approved CHARLES POWELL
Floor/Roof Diaphrgm/Shear Wall 12/16/2020 Approved CHARLES POWELL
Green Building Final 12/16/2020 Not Ready for Inspection CHARLES POWELL
MERV13>=Final 12/16/2020 Not Ready for Inspection CHARLES POWELL
SGSOV-Seismic Gas S/O Valve 12/16/2020 SGSOV No Gas CHARLES POWELL
Smoke Detectors 12/16/2020 Not Ready for Inspection CHARLES POWELL
Final 2/26/2021 Corrections Issued CHARLES POWELL
Green Building Final 2/26/2021 Approved CHARLES POWELL
MERV13>=Final 2/26/2021 Approved CHARLES POWELL
Smoke Detectors 2/26/2021 Approved CHARLES POWELL
Final 3/17/2021 Partial Approval CHARLES POWELL